Sign in

Ambience Mathru Chaya III

AMBIENCE DEVELOPERS · Medchal-Malkajgiri · RERA P02200007205

AMBIENCE MATHRU CHAYA III is a residential apartment project in Yapral, Alwal, Medchal-Malkajgiri. It is being developed by registered promoter AMBIENCE DEVELOPERS, a partnership. The project has a site extent of 891.86 sq. m and one building with 1 Cellar + Stilt + 5 upper floors, comprising 20 apartments: 10 2BHK and 10 3BHK. Its TG-RERA registration number is P02200007205, and the promoter’s declaration undertakes completion on or before 06/12/2028.

More from Ambience Developers · 3 projects →

01What we found

RegisteredTG-RERA - valid till 6 Dec 2028
12documents on file - each fact links to its page
1court case on this project's land (survey 123, Yapral)
6items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

6 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from housing.com

1. Project at a glance

Project identity

ItemProject record
Registered project nameAMBIENCE MATHRU CHAYA III RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionRegistered portion is identified as AMBIENCE MATHRU CHAYA III; a separate phase number is not stated in the supplied registration record. RERA record
TG-RERA registration numberP02200007205 RERA record
Registration validity04/11/2023–06/12/2028, as stated on the Form C certificate. This is the registration period, not a construction-progress statement. RERA record
Registered promoterAMBIENCE DEVELOPERS; partnership. RERA record Corporate record
RERA statusRegistration certificate records registration under section 5; the supplied registration record states no extension.

Land and geographic identity

ItemProject record
Locality / revenue villageYapral; the filed land and project records identify Yapral. The building-permit extraction also labels the village ALWAL. RERA record RERA filing
Mandal / district / PINAlwal / Medchal-Malkajgiri / 500087 RERA record RERA filing
Survey number(s)Survey No. 123; no subdivision is specified in the RERA land details. RERA filing Land records
Plot numbers16, 17, 22 & 23 Land records
Registered site extent891.86 sq. m; RERA land details state total area and net area as 891.86 sq. m, with 0 area affected by road widening/FTL of tanks/nala widening. Land records
BoundariesEast: PLOT NO 9 AND 10; West: PLOT NO 18 AND 24; North and South: 12MT WIDE ROAD. Land records

Development identity

ItemProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building approvalApproval No. 2/C28/00464/2022, dated 06 December, 2022 Approvals record
Approved built-up area2,146.45 m² is recorded as residential area in the building-permit extraction and as approved built-up area in the RERA filing. RERA filing
Buildings / towers1 building / tower is recorded in the RERA land details and unit summary. Land records RERA unit table
Sanctioned floor configuration1 Cellar + Stilt + 5 upper floors; sanctioned height: 15 m.
Parking levels / areas in sanctionCellar parking area 273.39 m² and stilt parking area 343.22 m²; the sanction says cellar and stilt areas approved for parking are to be used exclusively for vehicle parking. No parking-space count is supplied.
Unit count1 total building unit is shown in the land-details fields; the RERA unit record lists 20 apartments. The building-permit extraction does not give a separate sanctioned apartment count. Land records RERA unit table

Offering and status

ItemProject record
RERA-filed configurations2BHK: 10 units; 3BHK: 10 units RERA unit table RERA unit details
RERA-filed saleable area2BHK: 111.62 m²; 3BHK: 135.62 m² RERA unit table RERA unit details
Booked / availableRERA portal data lists 0 booked and 10 available for each configuration (20 available in total). The portal extract supplies no as-of date, so counts are indicative. RERA unit table RERA unit details
Construction stageThe supplied RERA and approval extracts do not establish current construction progress; no independent site-progress evidence is provided. Document index RERA amenities
Completion dateThe Form B declaration undertakes completion on or before 06/12/2028. This is a promoter declaration.
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied project evidence; the supplied record does not establish that an OC has been issued for the building. Document index

2. The project story

AMBIENCE MATHRU CHAYA III is a RERA-registered residential apartment project at Yapral, Alwal, Medchal-Malkajgiri, on Plot Nos. 16, 17, 22 and 23 in Survey No. 123. The RERA-filed site extent is 891.86 sq. m. RERA record Land records

The GHMC building permit is for one residential building, identified in its extraction as Building - MPL-1, with a sanctioned configuration of 1 Cellar + Stilt + 5 upper floors and a height of 15 m. The RERA unit schedule records 20 homes: ten 2BHK and ten 3BHK apartments. RERA unit table

The promoter’s Form B declaration undertakes completion by 06/12/2028. The supplied documents do not report a verified construction stage or provide an occupancy/completion certificate, so the project’s physical progress and occupation status cannot be confirmed from this evidence. Document index

3. Master plan, architecture & building design

The GHMC building permit records a site area of 891.86 m², net area of 891.86 m², and road-affected area of 0 m². It records 2,146.45 m² as residential area; the RERA filing separately identifies 2,146.45 m² as approved built-up area. The supplied records do not state FSI-counted area, gross built-up area, or building footprint. RERA filing

The sanctioned scheme is one residential building with 1 Cellar + Stilt + 5 upper floors, 15 m height, and parking areas at cellar (273.39 m²) and stilt (343.22 m²) levels. The approval records a 44.72 m² tot-lot and 40 Trees. The approval’s parking instruction says the cellar and stilt areas approved for parking are to be used exclusively for vehicle parking.

The supplied extracts do not establish the number of flats per floor, the building footprint, lift or stair configuration, internal circulation, or the extent of other open or landscaped areas. No separate phase-wise building arrangement is described.

4. Homes, configurations & floor plans

RERA lists 20 apartments across two configurations. The saleable areas below are RERA-filed. Carpet-area figures are software measurements from the supplied floor-plan drawing record, not RERA disclosures; they should be checked against the drawings. Saleable area and carpet area are different measures: the provided software analysis treats saleable area as including the home’s share of common areas, while its measured carpet area excludes the balcony and utility where identified. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK10010111.62 m²69.2–70.1 m²; median 69.4 m²38%
3BHK10010135.62 m²86.5–86.9 m²; median 86.6 m²36%

Software-measured examples from the drawings show a 2BHK plan with drawing room, living/dining, bedroom, master bedroom, kitchen, toilets, foyer and utility; a balcony is also indicated. A measured 3BHK plan shows living/dining, kitchen, three bedrooms, toilets, foyer, a 1.05 M. WIDE BALC, and utility. These are drawing-derived descriptions, not additional RERA area disclosures. RERA unit details

5. Parking & vehicle circulation

The GHMC approval records 273.39 m² of cellar parking area and 343.22 m² of stilt parking area. It directs that the cellar and stilt spaces approved for parking be used exclusively for vehicle parking. The supplied approval does not state the number of car or two-wheeler spaces, visitor or accessible spaces, ramp arrangement, or unit-by-unit parking allocation.

RERA unit data marks both configurations as mortgaged. That is a filed unit-status field; the supplied evidence does not establish an individual buyer’s parking allocation or exclusive parking rights. RERA unit table

6. Amenities, recreation & open spaces

The following status and progress figures are from the RERA-filed amenities data; 0% is the recorded progress for the listed items, not an independent site inspection. The GHMC permit separately requires the tot-lot to be fenced and maintained as greenery before issue of the occupancy certificate. RERA amenities

Green Strip/TOT LOT/Park
Description / sizeRERA amenities record marks it available “YES”; GHMC permit records a 44.72 m² tot-lot. RERA amenities
Evidence sourceRERA amenities record and GHMC building permit
Declared progress / verified status0% in RERA amenities data; no independent completion verification. RERA amenities
Internal Roads & Footpaths
Description / sizeListed in RERA amenities; no size supplied. RERA amenities
Evidence sourceRERA amenities record
Declared progress / verified status0%; no independent completion verification. RERA amenities
Community Buildings
Description / sizeListed in RERA amenities; no size or facility details supplied. RERA amenities
Evidence sourceRERA amenities record
Declared progress / verified status0%; no independent completion verification. RERA amenities
Street Lighting
Description / sizeListed in RERA amenities; no quantity or specifications supplied. RERA amenities
Evidence sourceRERA amenities record
Declared progress / verified status0%; no independent completion verification. RERA amenities
Water Conservation / Rain water Harvesting
Description / sizeMarked available “YES” in the RERA amenities record; GHMC permit requires a rainwater-harvesting percolation pit. RERA amenities
Evidence sourceRERA amenities record and GHMC building permit
Declared progress / verified status0% in RERA amenities data; no independent completion verification. RERA amenities

No RERA-filed evidence supplied here establishes a clubhouse, indoor recreation facilities, sports facilities, or other convenience/community amenities. RERA amenities Document index

7. Utilities, building services & safety

The RERA amenities record marks Water Supply and Electrical Meter Room, Sub-Station, Receiving Station as available “YES”; their recorded progress is 0%. It also lists sewerage, storm-water drains, sewage/sullage treatment and disposal, solid-waste management, energy management, and fire-protection/fire-safety requirements, each at 0% in the supplied record. These are filing entries and do not verify installation or completion. RERA amenities

The GHMC building-permit conditions require an ETP as per standard specification and a garbage house within the premises, and call for construction to follow the sanctioned plan. The permit also requires a rainwater-harvesting structure (percolation pit). No water source, storage or treatment capacity, sewerage-treatment capacity, power-backup capacity, lift capacity, fire-system specification, CCTV arrangement, security system, or accessibility details are supplied.

8. Location, access & connectivity

The registered location is Yapral, Alwal, Medchal-Malkajgiri, Telangana, 500087. The project land is recorded as Survey No. 123, Plot Nos. 16, 17, 22 and 23; its listed boundaries include 12MT WIDE ROAD to both the north and south. RERA record Land records

A location record gives the nearest sampled Outer Ring Road interchange at approximately 3.7 km. The evidence does not identify a public-transport route or provide verified travel times to other landmarks. Location record

9. Developer & development status

The registered promoter is AMBIENCE DEVELOPERS, a partnership. The RERA filing identifies partners ROHAN RAMESH SUKHIJA, DISHA ROHAN SUKHIJA, and KHUSHBOO GABA, and authorized signatory DINESH GABA. The promoter GSTIN is 36ABQFA6838D1Z7. Corporate record Parties record

The promoter’s registered address in the project evidence is AMBIENCE HOUSE, SY NO 41, 42 AND 43,, SHREE ENCLAVE PHASE III, YAPRAL, Alwal, Medchal-Malkajgiri, 500087. No official project contact number, email address, or promoter website is supplied. Parties record RERA filing

The Form B declaration dated 26/10/2023 states the promoter’s undertaking to complete by 06/12/2028 and includes declarations concerning encumbrances, project funds, accounts and pending approvals. These are promoter declarations, not independent confirmation of land status, construction progress or completion.

10. Approvals, official records & documents

TG-RERA registration certificate
Reference and scopeForm C; P02200007205, issued 04/11/2023
What the supplied record establishesRegistration for AMBIENCE MATHRU CHAYA III, with validity stated through 06/12/2028.
GHMC building permit order
Reference and scopeApproval No. 2/C28/00464/2022, dated 06 December, 2022; file No. 2/C27/06781/2021
What the supplied record establishesPermit extraction describes a residential building at Yapral with 1 Cellar + Stilt + 5 upper floors.
RERA Form B declaration
Reference and scopeDeclaration dated 26/10/2023
What the supplied record establishesPromoter’s declared title basis and completion undertaking, among other declarations.
Project plan / drawing record
Reference and scopeLayout-plan document ID 361244
What the supplied record establishesFloor-plan drawing record used for the software-measured carpet-area and room-description figures above.
Title-related filed records
Reference and scopeDocument IDs 361240, 361242, and 361264
What the supplied record establishesFiled development-agreement/GPA and title-report materials concerning the project land and development rights.
Occupancy / completion certificate
Reference and scopeNot present in the supplied project documents Document index
What the supplied record establishesThe supplied evidence does not establish issuance of an occupancy or completion certificate.

The approval extraction also records a contractor’s all-risk policy number 433702/44/2022/9, the number 9503/2021 in a “Floor handed over” entry, and notarised affidavit number 9897/2021. These are identifiers appearing in the approval extraction; the supplied data does not establish them as separate project occupancy or completion certificates.

Frequently asked questions

Is AMBIENCE MATHRU CHAYA III registered with Telangana RERA?

Yes. AMBIENCE MATHRU CHAYA III is registered with the Telangana Real Estate Regulatory Authority as P02200007205; the registration status is New Project.

Who is the developer of AMBIENCE MATHRU CHAYA III?

The promoter named in the RERA registration is AMBIENCE DEVELOPERS.

Where is AMBIENCE MATHRU CHAYA III located?

AMBIENCE MATHRU CHAYA III is in YAPRAL, Alwal, Medchal-Malkajgiri, Telangana (500087).

When will AMBIENCE MATHRU CHAYA III be completed?

The promoter's proposed date of completion filed with RERA is 06/04/2029. This is the promoter's declaration, not a guarantee.