Sign in

Abinandana Emerald

ABINANDANA INFRA REALITY LLP · Rangareddy · RERA P02400005934

ABINANDANA EMERALD is a commercial project in Manikonda Jagir, Gandipet mandal, Ranga Reddy district, developed by registered promoter ABINANDANA INFRA REALITY LLP. It covers 3,726.10 sq.m of land and comprises 1 building, described as an IT office building, with 2Cellar + 1Ground + 3 Upper floors. The RERA record lists four floor-labelled entries, each with a filed saleable area of 1,875.19 sq.m. Its TG-RERA registration number is P02400005934, and the proposed completion date is 30/04/2028.

More from Abinandana Infra Reality LLP · 3 projects →

01What we found

RegisteredTG-RERA
13documents on file - each fact links to its page
7court cases on this project's land (survey 264, Manikonda)
13items to check - 7 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

13 items to check before you pay, 7 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemProject record
Registered nameABINANDANA EMERALD RERA record
Project typeCommercial; the HMDA technical approval describes an IT office building. RERA record
Phase / registered portionPhase not separately identified in the supplied record; TG-RERA registration covers the project. RERA record
TG-RERA registrationP02400005934 RERA record
Registration validityCertificate states valid from 01/04/2023 to 31/12/2027, unless extended. No extension is recorded in the supplied certificate. This is registration validity, not the project completion deadline.
Registered promoterABINANDANA INFRA REALITY LLP RERA record Corporate record
RERA statusProject record identifies it as a New Project; certificate records registration granted under section 5. RERA record

Land and geographic identity

ItemProject record
LocalityManikonda Jagir RERA record RERA filing
Revenue villageManikonda (Jagir)
MandalGandipet RERA record
DistrictRanga Reddy RERA record
PIN500089 RERA record
Project survey number / subdivision264/EE RERA record Land records
Total land area3,726.10 sq.m RERA filing
Road-affected area807.04 sq.m in the RERA land details; HMDA approval records 807.1 sq.m as road-widening area, addressed by gift deed document 12334/2021. RERA filing
Net area2,919.06 sq.m RERA filing
BoundariesEast: others’ land; west, north and south: road. RERA filing

Development identity

ItemProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA); the technical approval states plans are to be sanctioned by the Executive Authority in conformity with HMDA’s technical approval. Approvals record
Principal approval043751/SKP/C1/U6/HMDA/03032021, dated 31/12/2021 Approvals record
Approved built-up areaProject filing records 6,986.11 sq.m; HMDA technical approval lists “Built up Area 6870.41” and “Proposed Built-up Area 7541.76.” These are figures as labelled in the respective records. RERA filing
Building count1 building in the RERA land details; HMDA identifies it as “BLDG (IT OFFICE).” RERA filing
Sanctioned floor configuration2Cellar + 1Ground + 3 Upper floors, as stated in the HMDA approval.
Parking levels / countThe approval identifies two cellar levels; a parking-space count or parking allocation is not established in the supplied evidence. RERA amenities
Unit countRERA record lists 4 floor-labelled entries, one each for First, Ground, Second and Third Floor. These are floor labels, not evidence of four separately defined sale units or shops. RERA unit table RERA unit details
Mortgage areaRERA land details state 724.05 sq.m; HMDA approval describes this as 10% of built-up area mortgaged in favour of MC, HMDA under document 8964/2021. RERA filing

Offering and status

ItemProject record
RERA-listed offeringFour floor-labelled entries; the supplied RERA record does not give a named shop/showroom configuration. RERA unit details [unit_types]
Filed saleable area1,875.19 sq.m per floor-labelled entry; four entries in total. This is the filed saleable figure, not a measured carpet area. [unit_types]
Booked / availablePortal-derived counts show 0 booked and 4 available, last read without an as-of date; treat as indicative. [unit_types]
Construction stageNo construction-progress percentage or independently verified site-stage evidence is supplied. RERA record RERA amenities
Completion datesRERA Form B states a promoter undertaking of 31.12.2027; the project header gives a proposed completion date of 30/04/2028. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. HMDA approval says an occupancy certificate is compulsory before occupation and requires application after completion.

2. The project story

ABINANDANA EMERALD is registered as a commercial project at Manikonda Jagir, on survey 264/EE. HMDA’s technical approval describes one IT office building, with two cellar levels, a ground floor and three upper floors; the RERA filing also records one building. RERA record Land records

The RERA record’s four floor-labelled entries each carry a filed saleable area of 1,875.19 sq.m. The record does not identify these entries as individually defined shops or show a completed unit-level sale schedule, so the floor labels should not be read as a verified count of saleable shops. The supplied project data does not establish construction progress, completion of facilities, or an issued occupancy certificate. RERA unit details [unit_types] RERA amenities

3. Master plan, architecture & building design

The HMDA technical approval describes a single commercial IT-office building on a stated site extent of 2,919.06 sq.m, with 2Cellar + 1Ground + 3 Upper floors. The RERA land record separately reports total area 3,726.10 sq.m, affected area 807.04 sq.m and net area 2,919.06 sq.m. RERA filing

The approval records built-up figures under distinct labels: “Built up Area 6870.41” and “Proposed Built-up Area 7541.76.” The RERA filing records approved built-up area as 6,986.11 sq.m. These figures are reproduced as stated; the supplied material does not establish a reconciled drawing schedule explaining their scope. RERA filing

The approval also records a 724.05 sq.m mortgage area in favour of MC, HMDA, and a road-widening area of 807.1 sq.m to be handed over by gift deed. The filing records the mortgage area as 724.05 sq.m and the affected road area as 807.04 sq.m. RERA filing RERA filing

No measured architectural floor plans, building footprint, per-floor shop layout, internal circulation or detailed landscaping/open-space drawing is available in the supplied evidence. The two drawing records noted in the file were not identified as measured floor plans. Floor plans

4. Homes, configurations & floor plans

This is a commercial project, not a residential homes offering. RERA’s unit table contains four floor-labelled entries; the filing does not establish a named configuration of individual shops or show a unit-level floor plan. RERA record RERA unit details

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Floor-labelled entries: FIRST FLOOR, GROUND FLOOR, SECOND FLOOR, THIRD FLOOR4 entries (1 each)041,875.19 sq.m per entryNot measured from drawingsNot supplied

The floor-plan record reports two drawings, with no measured drawings and no flats identified. Accordingly, there is no software-measured carpet area to report. The vendor lists “Shops & Showrooms” and a carpet area of 1,875 sqft, but that is a promoter-marketed detail, not a RERA-filed unit configuration or drawing-based measurement. RERA unit table Floor plans Promoter website

5. Parking & vehicle circulation

HMDA’s technical approval specifies two cellar levels, but the supplied records do not establish how many parking spaces are sanctioned, whether they are car or two-wheeler spaces, or whether any are resident, visitor or accessible spaces. The RERA amenities record does not provide parking counts or an allocation schedule. RERA amenities

A promoter website/vendor record lists “Reserved Parking” and “covered car parking”; these are marketing claims and do not establish approved capacity or legal allocation to a particular unit. No parking allotment document or drawing showing count and circulation details is supplied. Promoter website

6. Amenities, recreation & open spaces

The RERA amenities record marks several infrastructure items “YES” but gives no completion progress; its percentage fields are recorded as 0. HMDA’s technical approval separately lists a transformer, garbage house and tot-lot. The supplied evidence does not establish that any facility is complete or independently verified. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Green strip / tot lot / parkSize not suppliedRERA amenities: “YES”; HMDA approval lists “Tot-lot” RERA amenitiesRERA progress field 0; completion not verified
Swimming poolNo size or capacity suppliedPromoter marketing Promoter websiteMarketing claim only; not established in the RERA amenities record
SpaNo size or capacity suppliedPromoter marketing Promoter websiteMarketing claim only
GymNo size or capacity suppliedPromoter marketing Promoter websiteMarketing claim only
Kids’ play area / children’s play areaNo size suppliedPromoter marketing Promoter websiteMarketing claim only
ClubhouseNo size suppliedPromoter marketing Promoter websiteMarketing claim only
ParksNo size suppliedPromoter marketing Promoter websiteMarketing claim only

7. Utilities, building services & safety

The RERA amenities record marks Water Supply, Sewerage (Chamber, Lines, Septic Tank, STP), Storm Water Drains, Water Conservation, Rain water Harvesting, Fire Protection And Fire Safety Requirements, and Electrical Meter Room, Sub-Station, Receiving Station as “YES.” It does not give capacities, technical design details or completed-status evidence; progress fields are recorded as 0. RERA amenities

HMDA’s approval lists a transformer and garbage house, and includes fire-service and building-code references among its stated approval requirements. The supplied record does not identify water source or storage capacity, STP capacity, electrical load or backup generation, lift count/capacity, fire-system equipment, accessible routes, security systems or waste-treatment arrangements. These facilities should not be treated as completed or as proof of statutory compliance solely from the RERA amenity entries or approval references. RERA amenities

8. Location, access & connectivity

The registered project location is Manikonda Jagir village, Gandipet mandal, Ranga Reddy district, PIN 500089, on survey 264/EE. The HMDA approval describes the site as Manikonda (Jagir), with roads on its north, south and west boundaries and others’ land to the east in the RERA land record. RERA record Land records

The supplied location record places HITEC City 4.0 km from the project parcel centroid. No approach-road route or public-transport details are supplied. Location record

9. Developer & development status

The registered promoter is ABINANDANA INFRA REALITY LLP; the corporate record identifies the entity type as LLP and lists GSTIN 36ABVFA4635P1ZM. The supplied RERA certificate gives the promoter office location as Hyderabad, PIN 500089, but does not provide a complete street address there. The project record lists VEERABOMMA VENKATESH as authorized signatory and VEERABOMMA SWAPNA as managing director. Corporate record Parties record

The promoter’s Form B states a completion undertaking of 31.12.2027. The project header separately records 30/04/2028 as the proposed completion date. The supplied evidence contains no construction-progress measurement or independently verified completion status. No occupancy certificate is supplied. RERA record

The promoter website is listed as https://www.abinandanainfra.com/projects/emerald-mall. The website/vendor material is not used here to establish the project’s registered identity or sanctioned design. Parties record Promoter website

10. Approvals, official records & documents

TG-RERA registration certificate
Reference and scopeP02400005934, Form C; issued 01/04/2023, valid to 31/12/2027 unless extended
Evidence noteNames ABINANDANA EMERALD and survey 264/EE; includes registration conditions.
HMDA technical building approval
Reference and scope043751/SKP/C1/U6/HMDA/03032021, dated 31/12/2021
Evidence noteTechnical approval for a commercial IT-office building; document states local-authority sanction and occupancy certificate remain subject to conditions.
HMDA mortgage document
Reference and scope8964/2021, dated 9/9/2021
Evidence noteApproval records 724.05 sq.m of built-up area mortgaged in favour of MC, HMDA.
Road-area gift deed reference
Reference and scope12334/2021, dated 18/12/2021
Evidence noteApproval records 807.1 sq.m affected by a proposed 36 mts wide road and a gift deed in favour of HMDA.
Promoter declaration, Form B
Reference and scopeProject completion undertaking 31.12.2027
Evidence noteExtracted affidavit/undertaking; OCR does not identify the registration number or provide a legible attestation date/place.
Occupancy / completion certificate
Reference and scopeNot supplied
Evidence noteHMDA approval states an occupancy certificate is compulsory before occupation and directs the applicant to approach HMDA after completion.
Layout approval
Reference and scopeNot established in the supplied record Document index HMDA
Evidence noteThe listed layout-plan document is a request for an approval copy or a declaration/equivalent document; no approved layout plan is supplied.

Frequently asked questions

Is ABINANDANA EMERALD registered with Telangana RERA?

Yes. ABINANDANA EMERALD is registered with the Telangana Real Estate Regulatory Authority as P02400005934; the registration status is New Project.

Who is the developer of ABINANDANA EMERALD?

The promoter named in the RERA registration is ABINANDANA INFRA REALITY LLP.

Where is ABINANDANA EMERALD located?

ABINANDANA EMERALD is in MANIKONDA JAGIR, Manikonda, Gandipet, Rangareddy, Telangana (500089).

When will ABINANDANA EMERALD be completed?

The promoter's proposed date of completion filed with RERA is 30/04/2028. This is the promoter's declaration, not a guarantee.