GOLDEN SPRINGS is a residential apartment project in Hanuman Nagar, Moula-Ali, Medchal-Malkajgiri District. The registered promoter is Sri Lakshmi Builders and Developers. The project covers 2,215.09 sq. m and comprises one building with 1 cellar, 1 stilt and 5 upper floors, with 30 3BHK apartments. It is registered under TG-RERA number P02200005918, with a promoter-declared completion date of 25 November 2025.

More from Sri Lakshmi Builders And Developers · 3 projects →

01What we found

Period endedTG-RERA registration ran to 25 Nov 2025 - check its extension on TG-RERA
20documents on file - each fact links to its page
1court case on this project's land (survey 389, Moula Ali)
5items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

5 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

ItemProject record
Registered project nameGOLDEN SPRINGS RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionNo separate phase name or phase-wise boundary is disclosed in the supplied record. The registration is for the project identified with Survey No. 389/3. RERA record
TG-RERA registrationP02200005918 RERA record
Registration validity29 March 2023 to 25 November 2025; the certificate states a two-year validity period, subject to any extension by the Authority. No extension is recorded in the supplied certificate. Registration validity is distinct from the completion deadline and occupancy certification.
Registered promoterSri Lakshmi Builders and Developers RERA record
RERA statusThe project header labels it “New Project.” The registration certificate records registration under section 5. The supplied registration period has ended; the pack does not show a registration extension. RERA record

Land and geographic identity

ItemProject record
Locality / site descriptionHanuman Nagar, Moula-Ali; Plot Nos. 13 and 14, H.No. 44-414/4 RERA filing
Revenue villageThe RERA record identifies Moula Ali. The building-permit and OC extractions state village Malkajgiri and locality Hanuman Nagar, Moula-Ali; the supplied records do not reconcile these village labels. RERA record
MandalNot disclosed in the project identity fields. The permit and OC extractions state Malkajgiri. Land records
DistrictMedchal-Malkajgiri RERA record
PIN500047 RERA record
Survey number(s)Survey No. 389/3 RERA record Land records
Registered site extent2,215.09 sq. m (the permit gives 2,215.09 sq. m; the RERA land record gives 2,215.09 sq. m total and net area). RERA filing
Road-affected / nala-affected area in permit0.0 sq. m for each, as recorded in the building-permit parameters.
Boundaries in RERA recordNorth: 30-0 wide road; South: railway property; East: neighbours’ land; West: House No. 44-1261. RERA filing

Development identity

ItemProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building permit4278/GHMC/SEC/2022-BP, approved 25 November 2022 Approvals record
Related permit file number009511/GHMC/4675/SEC1/2022-BP Approvals record
Approved built-up areaThe RERA field records 8,050.53 sq. m as approved built-up area. The permit extraction separately gives upper-floor area 5,446.20 sq. m; these are distinct recorded measures. RERA filing
Building count and floorsOne building; sanctioned as 1 cellar + 1 stilt + 5 upper floors. Permit-recorded height: 14.85 m. RERA filing
Parking levelsCellar and stilt are designated for parking in the sanctioned-plan conditions. The permit records a cellar parking area of 1,201.9 sq. m and total parking area of 2,477.8 sq. m.
UnitsOne building is recorded in the approved-plan and RERA project fields. The supplied RERA unit record lists 30 apartments; no separate approved-versus-filed unit-count reconciliation is supplied. RERA filing RERA unit table

Offering and status

ItemProject record
RERA-filed configuration3BHK apartments; 30 units RERA unit table
RERA-filed saleable area201.5 sq. m per listed 3BHK configuration RERA unit table
Booked / available11 booked; 19 available in the portal-derived record. The record has no as-of date, so these counts are indicative, not a current availability confirmation. RERA unit table
Construction stageThe filed RERA completion undertaking specified 25 November 2025. GHMC issued an occupancy certificate for the building on 21 June 2025; the certificate records a completion date of 28 February 2025.
Completion deadlinePromoter-declared completion date: 25 November 2025.
Occupancy certificateGHMC OC 1152/GHMC/SEC/2025-OC, dated 21 June 2025, for the residential building identified as MPL (PEDDI NAGARAJU), Survey No. 389/3, at the stated site.

The project story

Golden Springs is registered with TG-RERA as a residential apartment project on Survey No. 389/3, at Plot Nos. 13 and 14, H.No. 44-414/4, Hanuman Nagar, Moula-Ali. Its records describe a single residential building with one cellar, one stilt and five upper floors, for residential use. RERA record RERA filing

The RERA unit record lists 30 three-bedroom apartments, with 11 shown as booked and 19 available; the portal-derived booking counts have no stated “as of” date. RERA unit table

GHMC’s occupancy certificate identifies the building as MPL (PEDDI NAGARAJU), records the same survey number and site extent, and certifies the inspected building fit for occupation. The certificate records completion on 28 February 2025 and was issued on 21 June 2025. This is an authority-issued OC for the identified building, rather than a statement of independently observed current occupancy.

The promoter’s Form B declaration undertook completion by 25 November 2025. That declared deadline, the TG-RERA registration validity end date, and the GHMC OC date are separate milestones.

Master plan, architecture & building design

The GHMC building permit sanctions one residential building on a stated plot area of 2,215.09 sq. m, with one cellar, one stilt and five upper floors. It records a building height of 14.85 m, upper-floor area of 5,446.20 sq. m, and upper-floor area of 1,233.9 sq. m in a separate parameter entry. The project’s RERA fields record approved built-up area of 8,050.53 sq. m; these figures are reproduced as separately labelled source measures and should not be treated as interchangeable. RERA filing

The supplied records identify one building and one RERA-filed apartment configuration. They do not provide a complete drawing-based account of flat distribution by floor, building footprint, lift and stair arrangement, entries and exits, internal circulation, or residential versus common-area schedules. RERA filing RERA unit table

The sanctioned permit records a tot-lot of 139.45 sq. m, one rainwater-harvesting pit, transformer space and a garbage house.

The available layout-plan document entry is not extracted, and the supplied data do not establish a separately approved layout plan number. The permit lists 155/77/ZOM/HUDA as an approved-layout/LRS/subdivision reference. Document index

Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK301119201.5 sq. m147.8–147.9 sq. m; median 147.9 sq. m (software-measured from drawing geometry)27% (software-derived drawing comparison)

The TG-RERA filing lists 3BHK apartments and records 201.5 sq. m saleable area. The carpet-area range and loading are software measurements from the supplied approved-floor-plan drawing record, not RERA-filed figures; they require review against the drawing. Saleable area and carpet area are different measures: saleable area includes the home’s share of common areas, while carpet area represents the software-measured internal drawing area. RERA unit table RERA unit details Floor plans

The measured example drawing shows a dining/kitchen, drawing room, three bedrooms, toilets, foyer areas, a dress room and a puja area. The supplied drawing measurement lists dimensions, including a 5.61 m × 4.0 m dining/kitchen and a 4.0 m × 4.54 m drawing room. These are drawing-derived measurements, not RERA disclosures. RERA unit details

Parking & vehicle circulation

The sanctioned permit designates cellar and stilt areas for vehicle parking and states they are to be used exclusively for parking, without partition walls or rolling shutters. It records a total parking area of 2,477.8 sq. m and a cellar parking area of 1,201.9 sq. m. The GHMC OC extraction records parking area of 2,435.8 sq. m.

No verified count of car or two-wheeler spaces, visitor or accessible spaces, parking-allocation schedule, ramp arrangement, EV charging provision, or exclusive unit-level parking rights is supplied. The permit’s parking provision does not by itself establish allocation or exclusive ownership of a particular bay.

Amenities, recreation & open spaces

Tot-lot / recreational green area
Description / size139.45 sq. m; permit conditions require it to be fenced and maintained as greenery before issue of OC.
Evidence sourceGHMC building permit; OC extraction
Declared progress / verified statusThe OC extraction records a tot-lot area of 139.45 sq. m; no separate current condition inspection is supplied.
Rainwater harvesting
Description / sizeOne rainwater-harvesting pit in the permit; OC extraction also lists rainwater harvesting (RWH).
Evidence sourceGHMC building permit and OC
Declared progress / verified statusRecorded in the OC document; no independent operational verification supplied.
Water supply
Description / sizeRERA amenity record marks water supply “YES.”
Evidence sourceTG-RERA amenity record RERA amenities
Declared progress / verified statusDeclared; progress percentage shown as 0 in the supplied record.
Sewerage / sewage treatment
Description / sizeRERA amenity record marks sewerage (including chambers, lines, septic tank, STP) “YES.”
Evidence sourceTG-RERA amenity record RERA amenities
Declared progress / verified statusDeclared; progress percentage shown as 0 in the supplied record.
Electrical meter room / sub-station / receiving station
Description / sizeRERA amenity record marks “YES”; permit also requires transformer space.
Evidence sourceTG-RERA amenity record; GHMC permit RERA amenities
Declared progress / verified statusDeclared / required in permit; no independent operational verification supplied.

The RERA amenity schedule also lists internal roads and footpaths, storm-water drains, street lighting, community buildings, sewage and sullage treatment/disposal, solid-waste management, energy management, fire protection and safety, and aggregate recreational open space. The supplied schedule shows 0 progress for these entries and does not establish delivered status. RERA amenities

Utilities, building services & safety

  • Water and rainwater: The TG-RERA amenity record marks water supply and water conservation/rainwater harvesting as available. The permit requires one rainwater-harvesting pit, and the OC extraction records RWH. The supplied data do not specify water sources, storage capacity or treatment capacity. RERA amenities
  • Sewerage and drainage: Sewerage is marked “YES” in the RERA amenity record, which names chambers, lines, septic tank and STP; the schedule also lists storm-water drainage and sewage/sullage treatment and disposal. No capacity or separate operational verification is supplied. RERA amenities
  • Electrical: The RERA schedule marks the electrical meter room/sub-station/receiving-station item “YES”; the permit requires transformer space. No supply capacity, backup capacity or EV charging provision is established by the supplied project records. RERA amenities
  • Fire and life safety: The building permit requires automatic sprinklers in the cellar and other fire-safety systems as per the referenced NBC provision, and requires an occupancy fire NOC before issue of the OC. The supplied evidence does not include the fire NOC itself or a system-capacity schedule.
  • Waste and accessibility: The permit requires a garbage house, and the RERA schedule lists solid-waste management and disposal. No specific waste-segregation system, security/CCTV arrangement, accessible circulation or lift details are established by the supplied project records. RERA amenities

Location, access & connectivity

The registered project location is Moula Ali, Medchal-Malkajgiri District, Telangana, PIN 500047; the site is described as Hanuman Nagar, Plot Nos. 13 and 14, H.No. 44-414/4, Survey No. 389/3. The RERA land record gives a north boundary of a 30-0 wide road and a south boundary of railway property. RERA record RERA filing

A supplied location record gives Financial District (Nanakramguda): 1.2 km as a measured connectivity distance. Location record

The data do not provide verified public-transport routes, travel times or additional measured distances.

Developer & development status

The registered promoter is Sri Lakshmi Builders and Developers, recorded as a partnership. Its GSTIN is 36ADFFS6652J1ZN. The RERA project record identifies Pallepati Bhanu Kiran as an authorized signatory and Pallepati Naga Saritha as a partner. Parties record Corporate record RERA filing

The supplied registration certificate gives the promoter-office location as “Village: Mandal: District: Medchal-Malkajgiri, Pin: 500094,” with village and mandal left blank; a complete registered-office address and official contact details are not established in the supplied data.

The promoter’s Form B declaration undertook completion by 25 November 2025. GHMC’s OC is recorded for the identified building, with certificate date 21 June 2025 and recorded completion date 28 February 2025.

Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02200005918, issued 29 March 2023; validity to 25 November 2025
What the supplied evidence recordsForm C registration for GOLDEN SPRINGS, subject to the stated conditions.
GHMC building permit
Identifier / date4278/GHMC/SEC/2022-BP, 25 November 2022; file 009511/GHMC/4675/SEC1/2022-BP
What the supplied evidence recordsPermit order for one residential building on Survey No. 389/3, with 1 cellar, 1 stilt and 5 upper floors.
Approved-layout/LRS/subdivision reference in permit
Identifier / date155/77/ZOM/HUDA
What the supplied evidence recordsListed as an approved-layout/LRS/subdivision reference in the permit extraction.
GHMC occupancy certificate
Identifier / date1152/GHMC/SEC/2025-OC, 21 June 2025; application 002523/GHMC/1089/SEC1/2025-OC
What the supplied evidence recordsOC for the building identified as MPL (PEDDI NAGARAJU), Survey No. 389/3; the extraction records completion on 28 February 2025.
RERA promoter declaration
Identifier / dateForm B
What the supplied evidence recordsPromoter declaration for Golden Springs, including the 25 November 2025 completion undertaking and project-account commitments.
RERA title-search report
Identifier / date14 January 2023
What the supplied evidence recordsAdvocate’s title-search report filed for the project land.
Floor-plan drawing record
Identifier / dateDocument 297719
What the supplied evidence recordsDrawing source used for software measurements; the layout-plan entry is not extracted in the supplied records. Document index

The supplied documents include a GHMC-issued permit and occupancy certificate. No separate extracted document establishing a fire NOC is included in this Overview evidence set.

Frequently asked questions

Is GOLDEN SPRINGS registered with Telangana RERA?

Yes. GOLDEN SPRINGS is registered with the Telangana Real Estate Regulatory Authority as P02200005918; the registration status is New Project.

Who is the developer of GOLDEN SPRINGS?

The promoter named in the RERA registration is SRI LAKSHMI BUILDERS AND DEVELOPERS.

Where is GOLDEN SPRINGS located?

GOLDEN SPRINGS is in MOULA ALI, Medchal-Malkajgiri, Telangana (500047).

When will GOLDEN SPRINGS be completed?

The promoter's proposed date of completion filed with RERA is 25/11/2025. This is the promoter's declaration, not a guarantee.