Maphar's & Baig's Pinnacle
MAPHAR CONSTRUCTIONS PVT LTD · Hyderabad · RERA P02500002385
MAPHAR'S & BAIG'S PINNACLE is a residential apartment project in Red Hills, Asif Nagar mandal, Hyderabad district, developed by MAPHAR CONSTRUCTIONS PVT LTD. The recorded site area is 1739.12 m², with one building, Building A-1, configured as 1 Cellar + Stilt + 5 upper floors. The project has 30 homes: 5 2BHK units of 94.32 m² each and 25 3BHK units of 103.84 m² each. Its TG-RERA registration is P02500002385, issued 17/12/2020 and valid through 31/03/2022; the promoter’s Form B declaration undertakes completion by 03-09-2022.
More from Maphar Constructions Pvt Ltd · 6 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | MAPHAR'S & BAIG'S PINNACLE RERA record |
| Project type / status | Residential apartment project; TG-RERA filing labels it “New Project.” RERA record RERA filing |
| Phase / registered portion | Phase not separately identified in the supplied record; the registration is for the project under the name above. RERA record |
| TG-RERA registration | P02500002385; Form C records grant under section 5, issued 17/12/2020, valid from 17/12/2020 to 31/03/2022. The supplied certificate does not record an extension. RERA record |
| Registered promoter | MAPHAR CONSTRUCTIONS PVT LTD. RERA record Corporate record |
| RERA status | Registration certificate supplied; the certificate’s stated validity ended 31/03/2022. Current registration status is not established by the supplied record. |
Land and geographic identity
| Item | Record |
|---|---|
| Locality / revenue village | Red Hills; the building-permit extraction specifies “RED HILLS -7.” RERA record RERA filing |
| Mandal / district / PIN | Asif Nagar / Hyderabad / 500004. RERA record RERA filing |
| Survey number and subdivision | Not disclosed in the supplied project identity or land records. The filed site identifier is Plot No. 11-5-296. Land records |
| Site extent | 1739.12 m² total and net area; affected area is recorded as 0. RERA filing |
| Boundaries | East: PUBLIC ROAD AND RED HILLS GARDEN; West: NEIGHBOURS HOUSE KAMAL VILLA; North: C C TO RED HILLS; South: NEIGHBOURS HOUSE. RERA filing Land records |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). Approvals record |
| Principal building approval | Building Permit Order No. 1/C12/03154/2020, approved 03 March 2020. The permit also lists file No. 1/C12/23104/2019. Approvals record |
| Approved built-up area | 4,376.20 m², as recorded in the RERA filing and building-permit extraction. RERA filing |
| Building count and configuration | One building, identified in the permit as Building A-1; sanctioned configuration: 1 Cellar + Stilt + 5 upper floors. RERA filing |
| Height / parking levels | Permit lists building height as 14.79 m and identifies the cellar and stilt as approved for parking. |
| Unit counts | 30 units in the RERA filing: 25 3BHK and 5 2BHK. The permit conditions say the sanctioned number of units must not be increased without prior GHMC approval; a separate sanctioned unit count is not stated in the supplied extraction. RERA unit table |
Offering and status
| Item | Record |
|---|---|
| Configurations and RERA saleable areas | 2BHK: 5 units, 94.32 m² each; 3BHK: 25 units, 103.84 m² each. RERA unit table |
| Booked / available | Portal-derived counts show 0 booked and 5 available 2BHK units, and 0 booked and 25 available 3BHK units. These counts are indicative: the supplied portal record has no as-of date. RERA unit table |
| Construction stage | No independently verified construction-stage or site-progress record is supplied. The RERA record declares 0% for each of the 14 listed infrastructure/facility items; this is a portal declaration, not an independent site inspection. RERA amenities |
| Completion dates | The registration certificate states validity ending 31/03/2022. The promoter’s Form B declaration undertakes completion by 03-09-2022. These are different recorded dates and are presented according to their document scopes. |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents. The building permit states that an occupancy certificate is required before occupation. Document index |
The project story
MAPHAR'S & BAIG'S PINNACLE is registered as a residential apartment project at Plot No. 11-5-296, Red Hills, Hyderabad, in the Asif Nagar mandal. The recorded site area is 1739.12 m², and the project is associated in the GHMC building-permit extraction with Building A-1. RERA record Land records
The GHMC permit describes a single building with a cellar, stilt and five upper floors, for residential use. The RERA filing lists 30 homes: 25 3BHK and 5 2BHK units. The filed portal record shows all 30 as available and none booked, but gives no count date. RERA unit table
The available evidence does not establish whether construction is underway, completed, or independently inspected. Likewise, no occupancy or completion certificate is supplied. The permit says an occupancy certificate is compulsory before occupation; that requirement is not evidence that a certificate has been issued. Document index RERA amenities
Master plan, architecture & building design
The project record identifies a 1739.12 m² site and 4,376.20 m² approved built-up area. The GHMC permit records 1739.12 m² as both site area and net area, 0 road-affected area, and a tot-lot of 86.96 m². It identifies one residential building, A-1, with 1 Cellar + Stilt + 5 upper floors and a listed height of 14.79 m. The permit separately records cellar area of 934.44 m² and stilt area of 848.31 m². These are permit-extracted figures, not measured from a completed building. RERA filing RERA filing
The supplied drawing record is an approved-plan document, but its layout-plan extraction is not available. Consequently, the evidence supplied here does not establish the building footprint, flats per floor, number or position of lifts and stairs, internal circulation, entrances, landscaped-area distribution, or detailed residential/common-area breakdown. The permit names a tot-lot and requires periphery greenery, tree planting and a rainwater-harvesting structure; it does not establish that these have been completed.
The approved built-up area is not presented as carpet area or saleable area. RERA saleable areas and software-measured drawing carpet areas are listed separately below. RERA filing RERA unit table Floor plans
Homes, configurations & floor plans
The RERA filing lists 30 units across two configurations. Drawing-based carpet figures below are software measurements from the approved floor-plan drawing, not RERA-filed carpet disclosures; the supplied drawing analysis says these measurements need review. RERA saleable area is a separate measure and includes a home’s share of common areas. RERA unit table Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 94.32 m² | 81.6 m² (software-measured; median and range) | Not supplied |
| 3BHK | 25 | 0 | 25 | 103.84 m² | 95.9–103.7 m² (software-measured; median 96.0 m²) | Not supplied |
The drawing measurement covers 2 flat designs for 2BHK and 7 for 3BHK. In the supplied 3BHK example, the drawing labels bedrooms, toilets, kitchen, living/dining, a balcony and a utility; the balcony and utility are excluded from the software-measured carpet figure. A supplied 2BHK example labels bedrooms, hall, dining, kitchen and toilets. Individual room dimensions and measured areas are drawing-derived and should be checked against the plan. RERA unit details Floor plans
Parking & vehicle circulation
The GHMC permit states that the cellar and stilt approved in the plan are to be used exclusively for vehicle parking, without partition walls or rolling shutters, and not converted to another use. It also records 934.44 m² for the cellar and 848.31 m² for the stilt.
A total parking-space count, resident or visitor allocation, accessible spaces, two-wheeler provision, parking allotment by unit, and vehicle circulation details are not established by the supplied evidence. The permit’s parking designation does not by itself establish exclusive ownership of any parking bay. Document index
Amenities, recreation & open spaces
The RERA amenities record lists 14 infrastructure or facility categories. Each carries a recorded progress figure of 0%; where “YES” appears, it is a portal availability entry, not independent confirmation of completion. The permit separately includes a tot-lot and rainwater harvesting structure among its conditions and requirements. RERA amenities
| Description / size | Listed as a facility category; no size or description supplied. |
|---|---|
| Evidence source | RERA amenities record RERA amenities |
| Declared progress / verified status | 0%; no independent completion verification |
| Description / size | RERA lists the category as available; permit records a tot-lot of 86.96 m² and requires it to be fenced and maintained as greenery. |
|---|---|
| Evidence source | RERA amenities record RERA amenities; GHMC permit |
| Declared progress / verified status | 0% in RERA record; completion not verified |
| Description / size | Listed as available; no further description supplied. |
|---|---|
| Evidence source | RERA amenities record RERA amenities |
| Declared progress / verified status | 0%; no independent completion verification |
| Description / size | Listed; no dimensions supplied. |
|---|---|
| Evidence source | RERA amenities record RERA amenities |
| Declared progress / verified status | 0%; no independent completion verification |
| Description / size | Listed; no further detail supplied. |
|---|---|
| Evidence source | RERA amenities record RERA amenities |
| Declared progress / verified status | 0%; no independent completion verification |
No clubhouse or indoor-recreation facilities, sports facilities, capacities, or additional landscaped-space measurements are established by the supplied evidence. Site utilities are addressed in the next section. RERA amenities Document index
Utilities, building services & safety
The RERA amenities record lists water supply, sewerage, storm-water drains, sewage and sullage treatment/disposal, solid-waste management, rainwater harvesting, fire protection, and an electrical meter room/sub-station/receiving station. These entries show 0% progress; the “YES” availability entries are not independent proof of installation or operation. RERA amenities
The GHMC permit requires a rainwater-harvesting structure, space for a transformer, and a garbage house. It also states that cellar and stilt parking must remain in parking use and requires the building’s sanitation, plumbing, fire-safety systems, lifts and electrical installations to be executed under qualified technical supervision. It requires an occupancy fire NOC before issue of an occupancy certificate and says an occupancy certificate is required before occupation. No supplied record confirms completion of these systems or issuance of the NOC or certificate.
The evidence does not specify water source or storage capacity, an STP’s capacity or reuse arrangements, storm-water design, electrical supply or backup capacity, lift count or capacity, fire-system equipment details, CCTV or access-control provisions, or accessible circulation. RERA amenities Document index
Location, access & connectivity
The registered project location is Red Hills, Asif Nagar mandal, Hyderabad district, PIN 500004. The cadastral-parcel-centroid coordinates supplied are 17.41528, 78.35459. The site boundaries identify a public road and Red Hills Garden to the east, neighbouring houses to the west and south, and “C C TO RED HILLS” to the north. RERA record RERA filing RERA filing Location record
The supplied location dataset gives these distances: Financial District (Nanakramguda), 1.2 km; IndusInd Bank, 0.4 km; an unnamed bus station, 2.2 km; Manuu Polytechnic Hyderabad, 1.6 km; Sankaraya Eye Hospital, 1.6 km; ADP, 0.0 km; South India Shopping Mall, 2.6 km; an unnamed park, 1.2 km; and Nanakramguda Government Primary School, 0.5 km. These are supplied distance records; no travel times or specific public-transport routes are provided. Location record
Developer & development status
The registered legal promoter is MAPHAR CONSTRUCTIONS PVT LTD, a private limited company; its supplied GSTIN is 36AAJCM5061F1ZH. The RERA registration certificate lists the promoter’s office as Village Bazar Ghat, Nampally, Hyderabad, PIN 500028. The RERA filing separately gives the promoter address as MAPHAR CASTLE, Masab Tank, Red Hills, Asif Nagar, Hyderabad, PIN 500004. Corporate record RERA filing
The RERA filing identifies one building and 30 units. The supplied documents do not establish phase-wise construction, current site progress, or completion. Form B is a promoter declaration signed by director Abdul Wahab Khan Usama on 03 March 2020, undertaking completion by 03-09-2022. The TG-RERA certificate states validity through 31/03/2022 and no extension is recorded in that certificate. No current-status confirmation or occupancy/completion certificate is supplied. RERA unit table Document index
Approvals, official records & documents
| Record | What the supplied evidence establishes |
|---|---|
| TG-RERA registration certificate, Form C | Registration P02500002385 granted to Maphar Constructions Pvt Ltd under section 5; issued 17/12/2020, valid through 31/03/2022. |
| GHMC Building Permit Order | Approval No. 1/C12/03154/2020, approved 03 March 2020; file No. 1/C12/23104/2019; permits Building A-1 with 1 Cellar + Stilt + 5 upper floors. |
| Approved plan / layout-plan filing | TG-RERA filing includes a layout-plan document entry, but the supplied document is not extracted; detailed layout information is therefore not established here. |
| Promoter Form B declaration | Dated 03 March 2020; includes the promoter’s completion undertaking, title-basis and encumbrance declarations, and project-fund undertakings. |
| Occupancy / completion certificate | Not included in the supplied project documents. Document index |
The GHMC permit lists a contractor’s all-risk policy number, 431500/44/2020/230, and a validity date of 17 February 2026. It also records mortgage registration numbers 1137/2020 and 1136/2020; full treatment of those entries belongs in the approvals and land-and-title review.
Project at a glance
Project identity
Registered project name: MAPHAR'S & BAIG'S PINNACLE
Project type / status: Residential apartment project; TG-RERA filing labels it “New Project.”
Phase / registered portion: Phase not separately identified in the supplied record; the registration is for the project under the name above.
TG-RERA registration: P02500002385; Form C records grant under section 5, issued 17/12/2020, valid from 17/12/2020 to 31/03/2022. The supplied certificate does not record an extension.
Registered promoter: MAPHAR CONSTRUCTIONS PVT LTD.
RERA status: Registration certificate supplied; the certificate’s stated validity ended 31/03/2022. Current registration status is not established by the supplied record.
Land and geographic identity
Locality / revenue village: Red Hills; the building-permit extraction specifies “RED HILLS -7.”
Mandal / district / PIN: Asif Nagar / Hyderabad / 500004.
Survey number and subdivision: Not disclosed in the supplied project identity or land records. The filed site identifier is Plot No. 11-5-296.
Site extent: 1739.12 m² total and net area; affected area is recorded as 0.
Boundaries: East: PUBLIC ROAD AND RED HILLS GARDEN; West: NEIGHBOURS HOUSE KAMAL VILLA; North: C C TO RED HILLS; South: NEIGHBOURS HOUSE.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal building approval: Building Permit Order No. 1/C12/03154/2020, approved 03 March 2020. The permit also lists file No. 1/C12/23104/2019.
Approved built-up area: 4,376.20 m², as recorded in the RERA filing and building-permit extraction.
Building count and configuration: One building, identified in the permit as Building A-1; sanctioned configuration: 1 Cellar + Stilt + 5 upper floors.
Height / parking levels: Permit lists building height as 14.79 m and identifies the cellar and stilt as approved for parking.
Unit counts: 30 units in the RERA filing: 25 3BHK and 5 2BHK. The permit conditions say the sanctioned number of units must not be increased without prior GHMC approval; a separate sanctioned unit count is not stated in the supplied extraction.
Offering and status
Configurations and RERA saleable areas: 2BHK: 5 units, 94.32 m² each; 3BHK: 25 units, 103.84 m² each.
Booked / available: Portal-derived counts show 0 booked and 5 available 2BHK units, and 0 booked and 25 available 3BHK units. These counts are indicative: the supplied portal record has no as-of date.
Construction stage: No independently verified construction-stage or site-progress record is supplied. The RERA record declares 0% for each of the 14 listed infrastructure/facility items; this is a portal declaration, not an independent site inspection.
Completion dates: The registration certificate states validity ending 31/03/2022. The promoter’s Form B declaration undertakes completion by 03-09-2022. These are different recorded dates and are presented according to their document scopes.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents. The building permit states that an occupancy certificate is required before occupation.
The project story
MAPHAR'S & BAIG'S PINNACLE is registered as a residential apartment project at Plot No. 11-5-296, Red Hills, Hyderabad, in the Asif Nagar mandal. The recorded site area is 1739.12 m², and the project is associated in the GHMC building-permit extraction with Building A-1.
The GHMC permit describes a single building with a cellar, stilt and five upper floors, for residential use. The RERA filing lists 30 homes: 25 3BHK and 5 2BHK units. The filed portal record shows all 30 as available and none booked, but gives no count date.
The available evidence does not establish whether construction is underway, completed, or independently inspected. Likewise, no occupancy or completion certificate is supplied. The permit says an occupancy certificate is compulsory before occupation; that requirement is not evidence that a certificate has been issued.
Master plan, architecture & building design
The project record identifies a 1739.12 m² site and 4,376.20 m² approved built-up area. The GHMC permit records 1739.12 m² as both site area and net area, 0 road-affected area, and a tot-lot of 86.96 m². It identifies one residential building, A-1, with 1 Cellar + Stilt + 5 upper floors and a listed height of 14.79 m. The permit separately records cellar area of 934.44 m² and stilt area of 848.31 m². These are permit-extracted figures, not measured from a completed building.
The supplied drawing record is an approved-plan document, but its layout-plan extraction is not available. Consequently, the evidence supplied here does not establish the building footprint, flats per floor, number or position of lifts and stairs, internal circulation, entrances, landscaped-area distribution, or detailed residential/common-area breakdown. The permit names a tot-lot and requires periphery greenery, tree planting and a rainwater-harvesting structure; it does not establish that these have been completed.
The approved built-up area is not presented as carpet area or saleable area. RERA saleable areas and software-measured drawing carpet areas are listed separately below.
Homes, configurations & floor plans
The RERA filing lists 30 units across two configurations. Drawing-based carpet figures below are software measurements from the approved floor-plan drawing, not RERA-filed carpet disclosures; the supplied drawing analysis says these measurements need review. RERA saleable area is a separate measure and includes a home’s share of common areas.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 94.32 m² | 81.6 m² (software-measured; median and range) | Not supplied |
| 3BHK | 25 | 0 | 25 | 103.84 m² | 95.9–103.7 m² (software-measured; median 96.0 m²) | Not supplied |
The drawing measurement covers 2 flat designs for 2BHK and 7 for 3BHK. In the supplied 3BHK example, the drawing labels bedrooms, toilets, kitchen, living/dining, a balcony and a utility; the balcony and utility are excluded from the software-measured carpet figure. A supplied 2BHK example labels bedrooms, hall, dining, kitchen and toilets. Individual room dimensions and measured areas are drawing-derived and should be checked against the plan.
Parking & vehicle circulation
The GHMC permit states that the cellar and stilt approved in the plan are to be used exclusively for vehicle parking, without partition walls or rolling shutters, and not converted to another use. It also records 934.44 m² for the cellar and 848.31 m² for the stilt.
A total parking-space count, resident or visitor allocation, accessible spaces, two-wheeler provision, parking allotment by unit, and vehicle circulation details are not established by the supplied evidence. The permit’s parking designation does not by itself establish exclusive ownership of any parking bay.
Amenities, recreation & open spaces
The RERA amenities record lists 14 infrastructure or facility categories. Each carries a recorded progress figure of 0%; where “YES” appears, it is a portal availability entry, not independent confirmation of completion. The permit separately includes a tot-lot and rainwater harvesting structure among its conditions and requirements.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Community buildings | Listed as a facility category; no size or description supplied. | RERA amenities record | 0%; no independent completion verification |
| Green strip / tot-lot / park | RERA lists the category as available; permit records a tot-lot of 86.96 m² and requires it to be fenced and maintained as greenery. | RERA amenities record; GHMC permit | 0% in RERA record; completion not verified |
| Aggregate recreational open space | Listed as available; no further description supplied. | RERA amenities record | 0%; no independent completion verification |
| Internal roads and footpaths | Listed; no dimensions supplied. | RERA amenities record | 0%; no independent completion verification |
| Street lighting | Listed; no further detail supplied. | RERA amenities record | 0%; no independent completion verification |
No clubhouse or indoor-recreation facilities, sports facilities, capacities, or additional landscaped-space measurements are established by the supplied evidence. Site utilities are addressed in the next section.
Utilities, building services & safety
The RERA amenities record lists water supply, sewerage, storm-water drains, sewage and sullage treatment/disposal, solid-waste management, rainwater harvesting, fire protection, and an electrical meter room/sub-station/receiving station. These entries show 0% progress; the “YES” availability entries are not independent proof of installation or operation.
The GHMC permit requires a rainwater-harvesting structure, space for a transformer, and a garbage house. It also states that cellar and stilt parking must remain in parking use and requires the building’s sanitation, plumbing, fire-safety systems, lifts and electrical installations to be executed under qualified technical supervision. It requires an occupancy fire NOC before issue of an occupancy certificate and says an occupancy certificate is required before occupation. No supplied record confirms completion of these systems or issuance of the NOC or certificate.
The evidence does not specify water source or storage capacity, an STP’s capacity or reuse arrangements, storm-water design, electrical supply or backup capacity, lift count or capacity, fire-system equipment details, CCTV or access-control provisions, or accessible circulation.
Location, access & connectivity
The registered project location is Red Hills, Asif Nagar mandal, Hyderabad district, PIN 500004. The cadastral-parcel-centroid coordinates supplied are 17.41528, 78.35459. The site boundaries identify a public road and Red Hills Garden to the east, neighbouring houses to the west and south, and “C C TO RED HILLS” to the north.
The supplied location dataset gives these distances: Financial District (Nanakramguda), 1.2 km; IndusInd Bank, 0.4 km; an unnamed bus station, 2.2 km; Manuu Polytechnic Hyderabad, 1.6 km; Sankaraya Eye Hospital, 1.6 km; ADP, 0.0 km; South India Shopping Mall, 2.6 km; an unnamed park, 1.2 km; and Nanakramguda Government Primary School, 0.5 km. These are supplied distance records; no travel times or specific public-transport routes are provided.
Developer & development status
The registered legal promoter is MAPHAR CONSTRUCTIONS PVT LTD, a private limited company; its supplied GSTIN is 36AAJCM5061F1ZH. The RERA registration certificate lists the promoter’s office as Village Bazar Ghat, Nampally, Hyderabad, PIN 500028. The RERA filing separately gives the promoter address as MAPHAR CASTLE, Masab Tank, Red Hills, Asif Nagar, Hyderabad, PIN 500004.
The RERA filing identifies one building and 30 units. The supplied documents do not establish phase-wise construction, current site progress, or completion. Form B is a promoter declaration signed by director Abdul Wahab Khan Usama on 03 March 2020, undertaking completion by 03-09-2022. The TG-RERA certificate states validity through 31/03/2022 and no extension is recorded in that certificate. No current-status confirmation or occupancy/completion certificate is supplied.
Approvals, official records & documents
TG-RERA registration certificate, Form C: Registration P02500002385 granted to Maphar Constructions Pvt Ltd under section 5; issued 17/12/2020, valid through 31/03/2022.
GHMC Building Permit Order: Approval No. 1/C12/03154/2020, approved 03 March 2020; file No. 1/C12/23104/2019; permits Building A-1 with 1 Cellar + Stilt + 5 upper floors.
Approved plan / layout-plan filing: TG-RERA filing includes a layout-plan document entry, but the supplied document is not extracted; detailed layout information is therefore not established here.
Promoter Form B declaration: Dated 03 March 2020; includes the promoter’s completion undertaking, title-basis and encumbrance declarations, and project-fund undertakings.
Occupancy / completion certificate: Not included in the supplied project documents.
The GHMC permit lists a contractor’s all-risk policy number, 431500/44/2020/230, and a validity date of 17 February 2026. It also records mortgage registration numbers 1137/2020 and 1136/2020; full treatment of those entries belongs in the approvals and land-and-title review.
Frequently asked questions
Is MAPHAR'S & BAIG'S PINNACLE registered with Telangana RERA?
Yes. MAPHAR'S & BAIG'S PINNACLE is registered with the Telangana Real Estate Regulatory Authority as P02500002385; the registration status is New Project.
Who is the developer of MAPHAR'S & BAIG'S PINNACLE?
The promoter named in the RERA registration is MAPHAR CONSTRUCTIONS PVT LTD.
Where is MAPHAR'S & BAIG'S PINNACLE located?
MAPHAR'S & BAIG'S PINNACLE is in RED HILLS, ASIF NAGAR, Hyderabad, Telangana (500004).
When will MAPHAR'S & BAIG'S PINNACLE be completed?
The promoter's proposed date of completion filed with RERA is 31/03/2022. This is the promoter's declaration, not a guarantee.
More projects in Asif Nagar