MAPHAR'S & BAIG'S PINNACLE is a residential apartment project in Red Hills, Asif Nagar mandal, Hyderabad district, developed by MAPHAR CONSTRUCTIONS PVT LTD. The recorded site area is 1739.12 m², with one building, Building A-1, configured as 1 Cellar + Stilt + 5 upper floors. The project has 30 homes: 5 2BHK units of 94.32 m² each and 25 3BHK units of 103.84 m² each. Its TG-RERA registration is P02500002385, issued 17/12/2020 and valid through 31/03/2022; the promoter’s Form B declaration undertakes completion by 03-09-2022.

More from Maphar Constructions Pvt Ltd · 6 projects →

01What we found

RegisteredTG-RERA
9documents on file - each fact links to its page
0court cases on this project's land in the court records searched
6items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

6 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

ItemRecord
Registered project nameMAPHAR'S & BAIG'S PINNACLE RERA record
Project type / statusResidential apartment project; TG-RERA filing labels it “New Project.” RERA record RERA filing
Phase / registered portionPhase not separately identified in the supplied record; the registration is for the project under the name above. RERA record
TG-RERA registrationP02500002385; Form C records grant under section 5, issued 17/12/2020, valid from 17/12/2020 to 31/03/2022. The supplied certificate does not record an extension. RERA record
Registered promoterMAPHAR CONSTRUCTIONS PVT LTD. RERA record Corporate record
RERA statusRegistration certificate supplied; the certificate’s stated validity ended 31/03/2022. Current registration status is not established by the supplied record.

Land and geographic identity

ItemRecord
Locality / revenue villageRed Hills; the building-permit extraction specifies “RED HILLS -7.” RERA record RERA filing
Mandal / district / PINAsif Nagar / Hyderabad / 500004. RERA record RERA filing
Survey number and subdivisionNot disclosed in the supplied project identity or land records. The filed site identifier is Plot No. 11-5-296. Land records
Site extent1739.12 m² total and net area; affected area is recorded as 0. RERA filing
BoundariesEast: PUBLIC ROAD AND RED HILLS GARDEN; West: NEIGHBOURS HOUSE KAMAL VILLA; North: C C TO RED HILLS; South: NEIGHBOURS HOUSE. RERA filing Land records

Development identity

ItemRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC). Approvals record
Principal building approvalBuilding Permit Order No. 1/C12/03154/2020, approved 03 March 2020. The permit also lists file No. 1/C12/23104/2019. Approvals record
Approved built-up area4,376.20 m², as recorded in the RERA filing and building-permit extraction. RERA filing
Building count and configurationOne building, identified in the permit as Building A-1; sanctioned configuration: 1 Cellar + Stilt + 5 upper floors. RERA filing
Height / parking levelsPermit lists building height as 14.79 m and identifies the cellar and stilt as approved for parking.
Unit counts30 units in the RERA filing: 25 3BHK and 5 2BHK. The permit conditions say the sanctioned number of units must not be increased without prior GHMC approval; a separate sanctioned unit count is not stated in the supplied extraction. RERA unit table

Offering and status

ItemRecord
Configurations and RERA saleable areas2BHK: 5 units, 94.32 m² each; 3BHK: 25 units, 103.84 m² each. RERA unit table
Booked / availablePortal-derived counts show 0 booked and 5 available 2BHK units, and 0 booked and 25 available 3BHK units. These counts are indicative: the supplied portal record has no as-of date. RERA unit table
Construction stageNo independently verified construction-stage or site-progress record is supplied. The RERA record declares 0% for each of the 14 listed infrastructure/facility items; this is a portal declaration, not an independent site inspection. RERA amenities
Completion datesThe registration certificate states validity ending 31/03/2022. The promoter’s Form B declaration undertakes completion by 03-09-2022. These are different recorded dates and are presented according to their document scopes.
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied project documents. The building permit states that an occupancy certificate is required before occupation. Document index

The project story

MAPHAR'S & BAIG'S PINNACLE is registered as a residential apartment project at Plot No. 11-5-296, Red Hills, Hyderabad, in the Asif Nagar mandal. The recorded site area is 1739.12 m², and the project is associated in the GHMC building-permit extraction with Building A-1. RERA record Land records

The GHMC permit describes a single building with a cellar, stilt and five upper floors, for residential use. The RERA filing lists 30 homes: 25 3BHK and 5 2BHK units. The filed portal record shows all 30 as available and none booked, but gives no count date. RERA unit table

The available evidence does not establish whether construction is underway, completed, or independently inspected. Likewise, no occupancy or completion certificate is supplied. The permit says an occupancy certificate is compulsory before occupation; that requirement is not evidence that a certificate has been issued. Document index RERA amenities

Master plan, architecture & building design

The project record identifies a 1739.12 m² site and 4,376.20 m² approved built-up area. The GHMC permit records 1739.12 m² as both site area and net area, 0 road-affected area, and a tot-lot of 86.96 m². It identifies one residential building, A-1, with 1 Cellar + Stilt + 5 upper floors and a listed height of 14.79 m. The permit separately records cellar area of 934.44 m² and stilt area of 848.31 m². These are permit-extracted figures, not measured from a completed building. RERA filing RERA filing

The supplied drawing record is an approved-plan document, but its layout-plan extraction is not available. Consequently, the evidence supplied here does not establish the building footprint, flats per floor, number or position of lifts and stairs, internal circulation, entrances, landscaped-area distribution, or detailed residential/common-area breakdown. The permit names a tot-lot and requires periphery greenery, tree planting and a rainwater-harvesting structure; it does not establish that these have been completed.

The approved built-up area is not presented as carpet area or saleable area. RERA saleable areas and software-measured drawing carpet areas are listed separately below. RERA filing RERA unit table Floor plans

Homes, configurations & floor plans

The RERA filing lists 30 units across two configurations. Drawing-based carpet figures below are software measurements from the approved floor-plan drawing, not RERA-filed carpet disclosures; the supplied drawing analysis says these measurements need review. RERA saleable area is a separate measure and includes a home’s share of common areas. RERA unit table Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK50594.32 m²81.6 m² (software-measured; median and range)Not supplied
3BHK25025103.84 m²95.9–103.7 m² (software-measured; median 96.0 m²)Not supplied

The drawing measurement covers 2 flat designs for 2BHK and 7 for 3BHK. In the supplied 3BHK example, the drawing labels bedrooms, toilets, kitchen, living/dining, a balcony and a utility; the balcony and utility are excluded from the software-measured carpet figure. A supplied 2BHK example labels bedrooms, hall, dining, kitchen and toilets. Individual room dimensions and measured areas are drawing-derived and should be checked against the plan. RERA unit details Floor plans

Parking & vehicle circulation

The GHMC permit states that the cellar and stilt approved in the plan are to be used exclusively for vehicle parking, without partition walls or rolling shutters, and not converted to another use. It also records 934.44 m² for the cellar and 848.31 m² for the stilt.

A total parking-space count, resident or visitor allocation, accessible spaces, two-wheeler provision, parking allotment by unit, and vehicle circulation details are not established by the supplied evidence. The permit’s parking designation does not by itself establish exclusive ownership of any parking bay. Document index

Amenities, recreation & open spaces

The RERA amenities record lists 14 infrastructure or facility categories. Each carries a recorded progress figure of 0%; where “YES” appears, it is a portal availability entry, not independent confirmation of completion. The permit separately includes a tot-lot and rainwater harvesting structure among its conditions and requirements. RERA amenities

Community buildings
Description / sizeListed as a facility category; no size or description supplied.
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified status0%; no independent completion verification
Green strip / tot-lot / park
Description / sizeRERA lists the category as available; permit records a tot-lot of 86.96 m² and requires it to be fenced and maintained as greenery.
Evidence sourceRERA amenities record RERA amenities; GHMC permit
Declared progress / verified status0% in RERA record; completion not verified
Aggregate recreational open space
Description / sizeListed as available; no further description supplied.
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified status0%; no independent completion verification
Internal roads and footpaths
Description / sizeListed; no dimensions supplied.
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified status0%; no independent completion verification
Street lighting
Description / sizeListed; no further detail supplied.
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified status0%; no independent completion verification

No clubhouse or indoor-recreation facilities, sports facilities, capacities, or additional landscaped-space measurements are established by the supplied evidence. Site utilities are addressed in the next section. RERA amenities Document index

Utilities, building services & safety

The RERA amenities record lists water supply, sewerage, storm-water drains, sewage and sullage treatment/disposal, solid-waste management, rainwater harvesting, fire protection, and an electrical meter room/sub-station/receiving station. These entries show 0% progress; the “YES” availability entries are not independent proof of installation or operation. RERA amenities

The GHMC permit requires a rainwater-harvesting structure, space for a transformer, and a garbage house. It also states that cellar and stilt parking must remain in parking use and requires the building’s sanitation, plumbing, fire-safety systems, lifts and electrical installations to be executed under qualified technical supervision. It requires an occupancy fire NOC before issue of an occupancy certificate and says an occupancy certificate is required before occupation. No supplied record confirms completion of these systems or issuance of the NOC or certificate.

The evidence does not specify water source or storage capacity, an STP’s capacity or reuse arrangements, storm-water design, electrical supply or backup capacity, lift count or capacity, fire-system equipment details, CCTV or access-control provisions, or accessible circulation. RERA amenities Document index

Location, access & connectivity

The registered project location is Red Hills, Asif Nagar mandal, Hyderabad district, PIN 500004. The cadastral-parcel-centroid coordinates supplied are 17.41528, 78.35459. The site boundaries identify a public road and Red Hills Garden to the east, neighbouring houses to the west and south, and “C C TO RED HILLS” to the north. RERA record RERA filing RERA filing Location record

The supplied location dataset gives these distances: Financial District (Nanakramguda), 1.2 km; IndusInd Bank, 0.4 km; an unnamed bus station, 2.2 km; Manuu Polytechnic Hyderabad, 1.6 km; Sankaraya Eye Hospital, 1.6 km; ADP, 0.0 km; South India Shopping Mall, 2.6 km; an unnamed park, 1.2 km; and Nanakramguda Government Primary School, 0.5 km. These are supplied distance records; no travel times or specific public-transport routes are provided. Location record

Developer & development status

The registered legal promoter is MAPHAR CONSTRUCTIONS PVT LTD, a private limited company; its supplied GSTIN is 36AAJCM5061F1ZH. The RERA registration certificate lists the promoter’s office as Village Bazar Ghat, Nampally, Hyderabad, PIN 500028. The RERA filing separately gives the promoter address as MAPHAR CASTLE, Masab Tank, Red Hills, Asif Nagar, Hyderabad, PIN 500004. Corporate record RERA filing

The RERA filing identifies one building and 30 units. The supplied documents do not establish phase-wise construction, current site progress, or completion. Form B is a promoter declaration signed by director Abdul Wahab Khan Usama on 03 March 2020, undertaking completion by 03-09-2022. The TG-RERA certificate states validity through 31/03/2022 and no extension is recorded in that certificate. No current-status confirmation or occupancy/completion certificate is supplied. RERA unit table Document index

Approvals, official records & documents

RecordWhat the supplied evidence establishes
TG-RERA registration certificate, Form CRegistration P02500002385 granted to Maphar Constructions Pvt Ltd under section 5; issued 17/12/2020, valid through 31/03/2022.
GHMC Building Permit OrderApproval No. 1/C12/03154/2020, approved 03 March 2020; file No. 1/C12/23104/2019; permits Building A-1 with 1 Cellar + Stilt + 5 upper floors.
Approved plan / layout-plan filingTG-RERA filing includes a layout-plan document entry, but the supplied document is not extracted; detailed layout information is therefore not established here.
Promoter Form B declarationDated 03 March 2020; includes the promoter’s completion undertaking, title-basis and encumbrance declarations, and project-fund undertakings.
Occupancy / completion certificateNot included in the supplied project documents. Document index

The GHMC permit lists a contractor’s all-risk policy number, 431500/44/2020/230, and a validity date of 17 February 2026. It also records mortgage registration numbers 1137/2020 and 1136/2020; full treatment of those entries belongs in the approvals and land-and-title review.

Frequently asked questions

Is MAPHAR'S & BAIG'S PINNACLE registered with Telangana RERA?

Yes. MAPHAR'S & BAIG'S PINNACLE is registered with the Telangana Real Estate Regulatory Authority as P02500002385; the registration status is New Project.

Who is the developer of MAPHAR'S & BAIG'S PINNACLE?

The promoter named in the RERA registration is MAPHAR CONSTRUCTIONS PVT LTD.

Where is MAPHAR'S & BAIG'S PINNACLE located?

MAPHAR'S & BAIG'S PINNACLE is in RED HILLS, ASIF NAGAR, Hyderabad, Telangana (500004).

When will MAPHAR'S & BAIG'S PINNACLE be completed?

The promoter's proposed date of completion filed with RERA is 31/03/2022. This is the promoter's declaration, not a guarantee.