Sign in

Kapil Business Park

BVM ENERGY AND RESIDENCY PRIVATE LIMITED · Rangareddy · RERA P02400002352

KAPIL BUSINESS PARK is a commercial project at SHAMSHABAD AIRPORT ROAD, Hardware Park, Kancha Imarat, Ravirala, Maheshwaram, Ranga Reddy. The registered promoter is BVM ENERGY AND RESIDENCY PRIVATE LIMITED. The project covers 40,821 sq. m and comprises two buildings, BUSINESS BLDNG and HOTEL BLDNG: the business building has 4 Cellar + 1 Ground + 11 upper floors, and the hotel building has 4 Cellar + 1 Ground + 12 upper floors; the RERA unit table lists 27 floor-labelled units. Configurations are listed from Ground Floor through Twelveth Floor. It is registered under TG-RERA number P02400002352, and the project identity record gives proposed completion as 09/01/2027.

01What we found

Period endedTG-RERA registration ran to 9 Sep 2026 - check its extension on TG-RERA
12documents on file - each fact links to its page
2court cases on this project's land (survey 1, Ravirala)
10items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

10 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from justdial.comPhoto from justdial.com
▦ View all 2 photos
Ravirala, Maheshwaram, Ranga Reddy · geocoded — approximate.

1. Project at a glance

Project identity

ItemRecord
Registered project nameKAPIL BUSINESS PARK RERA record
Project typeCommercial project in the RERA record; the filed building permission provides for a business building and a hotel building. RERA record
Phase / registered portionRegistration is for the project; a separate phase name or phase-wise registration scope is not disclosed. The permit identifies Plot No. CFC-1. RERA record
TG-RERA registrationP02400002352, issued 20/11/2020; the certificate states validity through 09/09/2026. RERA record
RERA statusThe supplied registration record lists the project as “New Project.” The registration record was captured 10/09/2026; current status or any extension is not established by the supplied evidence. RERA record Approvals record
Registered promoterBVM ENERGY AND RESIDENCY PRIVATE LIMITED, a private limited company. RERA record Corporate record

Land and geographic identity

ItemRecord
Locality / site descriptionSHAMSHABAD AIRPORT ROAD; TSIIC Industrial Development Area, Plot No. CFC-1, Hardware Park, Kancha Imarat. RERA record RERA filing
Revenue villageRavirala in the project identity record; the building permit and title documents use Raviryal/Raviryala, and the title report also identifies Kancha Imarat Village. RERA record
Mandal / district / PINMaheshwaram / Ranga Reddy / 501510. RERA record RERA filing
Project survey number(s)1/1. No project subdivision is stated in the RERA project record or building-permit extraction. RERA record
RERA-filed site area40,821 sq. m total and net area; road-affected area recorded as 0 sq. m in the building-permit extraction. RERA filing
BoundariesNorth: Airport Road; South: TSIIC land and VEM Technologies; East: TAJ GVK; West: TSIIC land. RERA filing

Development identity

ItemRecord
Sanctioning authorityTSIIC–IALA, Hardware Park Kancha Imarat. Approvals record
Principal building approvalBuilding Permit Order IIC/0153/2020, dated 09 September 2020. Approvals record
Approved building arrangementTwo buildings: BUSINESS BLDNG and HOTEL BLDNG.
Sanctioned floor configurationPermit extraction: Business Building—4 Cellar + 1 Ground + 11 upper floors; Hotel Building—4 Cellar + 1 Ground + 12 upper floors.
Building heightsBusiness Building: 47.48 m; Hotel Building: 47.83 m.
Approved built-up areaRERA identity record: 172,556.65 sq. m. The building-permit extraction separately lists floor-area figures of 6,845.08 and 82,416.63 for the business building, and 1,763.25 and 23,456.62 for the hotel building; the supplied extraction does not label these as the project’s total approved built-up area. RERA filing
Parking levels / provisionFour cellar levels appear in the permit’s floor configuration. A parking-space count, parking allocation, or parking-level plan is not supplied.
Unit countRERA unit table lists 27 units across two buildings/blocks; it does not provide a conventional office-unit configuration in the supplied normalized record. RERA unit table RERA unit details

Offering and status

ItemRecord
RERA-filed unit listingFloor-labelled entries from Ground Floor through Twelveth Floor; the filing classifies these as floors rather than a standard office configuration. RERA unit details RERA unit table
RERA-filed saleable areaOverall listed range: 2,660.0–6,529.45 sq. m per filed row. Individual floor-labelled entries and counts are summarised below. RERA unit table RERA unit table
Booked / available8 booked / 19 available, as last read from the TG-RERA portal; no as-of date is supplied, so these are indicative. RERA unit table
Construction stageThe supplied records establish a building permit and RERA filing, but do not establish current construction progress or independently verified site completion. RERA amenities
Completion timelinePromoter’s Form B undertaking: 09/09/2026. The project identity record gives proposed completion 09/01/2027. RERA record
Occupancy / completion certificateNo completion certificate or occupancy certificate is evidenced in the supplied documents. The building permit states that an occupancy certificate is required before occupation.

2. The project story

KAPIL BUSINESS PARK is a RERA-registered commercial project at Plot No. CFC-1 in the TSIIC Industrial Development Area at Hardware Park, Kancha Imarat, on Shamshabad Airport Road. The building permit provides for two commercial-use buildings: a business building and a hotel building, each with four cellar levels, a ground floor and upper floors. RERA record

The RERA filing lists 27 units using floor labels rather than a standard office-space configuration. It records 8 as booked and 19 as available, but the portal extract has no as-of date; those figures should therefore be treated as indicative, not as a live inventory confirmation. RERA unit details RERA unit table

The available evidence documents permission and promoter-filed commitments, not the present physical stage of construction. The supplied amenities record reports 0% for each listed item, and no project-specific completion or occupancy certificate is included. No independent site inspection or construction-progress verification is provided. RERA amenities Document index

3. Master plan, architecture & building design

The building permit identifies a 40,821 sq. m site and sanctions two buildings: a business building and a hotel building. Its extracted floor configuration is four cellar levels plus ground and 11 upper floors for the business building, and four cellar levels plus ground and 12 upper floors for the hotel building. The extracted building heights are 47.48 m and 47.83 m respectively.

The project identity record reports 172,556.65 sq. m as approved built-up area. The permit extraction also contains building floor-area entries, but it does not identify them as one consolidated project-wide built-up figure. These figures should not be treated as carpet area or as the RERA-filed saleable area. RERA filing

The permit lists a tot-lot of 9,798.58 sq. m, transformer space, a garbage house and a rainwater-harvesting structure (percolation pit). It requires the tot-lot to be maintained at not less than 5% of plot area. The supplied material does not include readable drawing-derived details for building footprints, floor-by-floor office layouts, lifts, stairs, internal circulation, landscaping plans, or phase organization. Floor plans

4. Homes, configurations & floor plans

This is a commercial project, not a residential homes offering. The RERA unit table records floor-labelled rows; the supplied normalized data does not establish those labels as a standard office configuration. The RERA-filed area below is the recorded saleable area, not carpet area. RERA unit details RERA unit table RERA unit table

Configuration / filed labelUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
Ground Floor2025,857.51 sq. mNot availableNot supplied
First Floor2025,821.51 sq. mNot availableNot supplied
Second Floor3034,318.94 sq. mNot availableNot supplied
Third Floor3124,318.94 sq. mNot availableNot supplied
Fourth Floor2116,478.41 sq. mNot availableNot supplied
Fifth Floor2116,478.41 sq. mNot availableNot supplied
Sixth Floor2116,529.45 sq. mNot availableNot supplied
Seventh Floor2116,478.41 sq. mNot availableNot supplied
Eighth Floor2116,478.41 sq. mNot availableNot supplied
Ninth Floor2116,529.45 sq. mNot availableNot supplied
Tenth Floor2116,478.41 sq. mNot availableNot supplied
Eleventh Floor2026,478.41 sq. mNot availableNot supplied
Twelveth Floor1012,660.0 sq. mNot availableNot supplied
Total27819———

The floor-plan dataset contains three drawings, with two measured and one scan pending. It provides no usable configuration-level carpet-area measurement in the supplied unit details. Any software-measured carpet area would be a drawing-based measurement, not a RERA disclosure; no such figures are provided here. Saleable area may include a share of common areas, so it should not be read as carpet area. Floor plans RERA unit details

5. Parking & vehicle circulation

The sanctioned floor configuration includes four cellar levels for each building, but the supplied extraction does not establish how those levels are allocated or how many vehicle spaces are provided. No resident, visitor, accessible, two-wheeler, or EV-charging counts are supplied, and no unit-specific parking allocation is evidenced.

The building-permit conditions include a requirement that vehicles not be parked roadside. The available records do not describe parking ramps, driveway routes, pedestrian separation, or an approved parking-space schedule. A cellar level alone does not establish a number of parking spaces or an exclusive parking entitlement.

6. Amenities, recreation & open spaces

Landscape/open space — tot-lot
Description / sizePermit extraction lists 9,798.58 sq. m and requires maintenance at not less than 5% of plot area.
Evidence sourceSanctioned building-permit extraction
Declared progress / verified statusSanctioned provision; the RERA amenities record shows 0%. No independent completion verification.
Convenience/community — transformer space
Description / sizeSpace for transformer is listed.
Evidence sourceSanctioned building-permit extraction
Declared progress / verified statusSanctioned provision; completion not verified.
Convenience/community — garbage house
Description / sizeGarbage house within the premises is listed as a permit condition.
Evidence sourceSanctioned building-permit extraction
Declared progress / verified statusRequired by permit; completion not verified.
Utilities-related — rainwater harvesting
Description / sizeRainwater-harvesting structure (percolation pit) is listed.
Evidence sourceSanctioned building-permit extraction
Declared progress / verified statusSanctioned/required provision; completion not verified.
RERA-listed infrastructure and services
Description / sizeInternal roads and footpaths, water supply, sewerage, storm-water drains, green strip/tot-lot/park, street lighting, community buildings, sewage and sullage treatment/disposal, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, and electrical meter room/sub-station/receiving station.
Evidence sourceTG-RERA amenities record RERA amenities
Declared progress / verified statusListed in the filing; each supplied progress field is 0%. This does not establish delivery.

The supplied vendor material also lists facilities such as a clubhouse, pool, gym and indoor sports, but these are not established as sanctioned or delivered facilities by the project-specific evidence reviewed for this Overview. Promoter website

7. Utilities, building services & safety

The RERA amenities record lists water supply, sewerage and sewage/sullage treatment and disposal, storm-water drains, rainwater harvesting, solid-waste management, energy management, fire protection, and electrical meter room/sub-station/receiving station. The supplied progress fields for these listed items are 0%; the evidence does not establish their current installation or operation. RERA amenities

The building-permit extraction identifies a transformer space, garbage house and rainwater-harvesting percolation pit. It also states that sanitation, plumbing, fire-safety requirements, lifts and electrical installations are to be executed under qualified technical supervision; the extraction does not provide system specifications or capacities.

The permit requires an occupancy certificate before occupation and places structural and fire-safety requirements on the owner, builder/developer, architect and structural engineer. No occupancy certificate, fire-clearance certificate, lift schedule, water-storage or treatment capacity, backup-power capacity, accessibility drawing, or independently verified safety-completion record is supplied. Document index

8. Location, access & connectivity

The registered project location is Ravirala, Maheshwaram Mandal, Ranga Reddy District, PIN 501510, at SHAMSHABAD AIRPORT ROAD. The permit describes the site as Plot No. CFC-1 in the TSIIC Industrial Development Area at Hardware Park, Kancha Imarat. RERA record RERA filing

The RERA-filed boundaries identify Airport Road to the north, TSIIC land to the west, TAJ GVK to the east, and TSIIC land and VEM Technologies to the south. A location dataset gives the nearest sampled Outer Ring Road interchange at approximately 5.0 km. The evidence supplied does not identify public-transport routes or measured distances to other landmarks. RERA filing Location record

9. Developer & development status

The registered promoter is BVM ENERGY AND RESIDENCY PRIVATE LIMITED, a company, with the project promoter address recorded at Kapil Towers, IT Park, Kancha Imarat, Shamshabad Airport Road, Maheshwaram, Ranga Reddy, 501510. The project filing identifies Krishnaiah Vaddanapu as managing director and authorized signatory. Corporate record Parties record RERA filing

The registration certificate records the project’s RERA number and validity through 09/09/2026. The promoter’s Form B affidavit declares a completion undertaking of 09/09/2026; the project identity record gives a proposed completion date of 09/01/2027. These are recorded deadlines/undertakings, not evidence that construction was completed by either date. No extension order or occupancy certificate is supplied. RERA record Document index

The available contact/site information includes https://kapilbusinesspark.com/. No independently verified construction-progress report is included. Parties record

10. Approvals, official records & documents

TG-RERA registration certificate
DetailsForm C; project KAPIL BUSINESS PARK, registration P02400002352; issued 20/11/2020; certificate states validity through 09/09/2026.
Building permit
DetailsTSIIC–IALA Building Permit Order IIC/0153/2020, dated 09 September 2020, for business and hotel buildings at Survey No. 1/1, Plot CFC-1.
Building-permit conditions and parameters
DetailsIncludes site and building parameters, permitted floor configurations, heights, tot-lot, transformer space, garbage house and rainwater-harvesting structure.
Form B promoter declaration
DetailsPromoter declaration including a completion undertaking of 09/09/2026.
Layout / floor-plan evidence
DetailsThe supplied document register includes layout-plan entries, but their extractions are unavailable. Floor-plan data records three drawings: two measured and one scan pending.
EvidenceDocument index Floor plans
Completion / occupancy record
DetailsNo completion certificate or occupancy certificate is included in the supplied project documents.
EvidenceDocument index

The permit states that permission does not confer ownership rights and requires the sanctioned plan to be followed. This Overview records the permit and RERA-filed material; it does not establish construction completion or occupancy certification.

Frequently asked questions

Is KAPIL BUSINESS PARK registered with Telangana RERA?

Yes. KAPIL BUSINESS PARK is registered with the Telangana Real Estate Regulatory Authority as P02400002352; the registration status is New Project.

Who is the developer of KAPIL BUSINESS PARK?

The promoter named in the RERA registration is BVM ENERGY AND RESIDENCY PRIVATE LIMITED.

Where is KAPIL BUSINESS PARK located?

KAPIL BUSINESS PARK is in SHAMSHABAD AIRPORT ROAD, Ravirala, Maheshwaram, Rangareddy, Telangana (501510).

When will KAPIL BUSINESS PARK be completed?

The promoter's proposed date of completion filed with RERA is 09/01/2027. This is the promoter's declaration, not a guarantee.

More projects in Ravirala