Mantri A is a residential apartment project at Jubilee Hills Check Post, Shaikpet Mandal, Hyderabad District. The registered promoter is Jubilee Hills Landmark Projects Pvt Ltd. The project covers 23,661.77 sq. m and the RERA filing lists 8 buildings and 126 proposed units: 14 3BHK, 32 4BHK and 80 5BHK apartments. It is registered under TG-RERA **P02500000549**, issued 27/03/2019, with an original and revised proposed completion date of 30/09/2022.

More from Jubilee hills Landmark Projects Pvt Ltd · 2 projects →

01What we found

Period endedTG-RERA registration ran to 30 Sep 2022 - check its extension on TG-RERA
11documents on file - each fact links to its page
157court cases on this project's land (survey 16, 403, Jubilee Hills Check Post)
17items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

17 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemTG-RERA record
Registered project nameMantri A RERA record
Project type / useResidential apartment project RERA record RERA filing
Phase / registered portionThe supplied record does not identify a numbered phase; registration is for Mantri A.
TG-RERA registrationP02500000549, issued 27/03/2019; certificate states validity from 27/03/2019 to 30/09/2022. RERA record
Registered promoterJubilee Hills Landmark Projects Pvt Ltd RERA record
RERA statusListed as “On-Going Project”; the recorded registration validity ended 30/09/2022. No extension is evidenced in the supplied record. RERA record RERA filing

Land and geographic identity

ItemTG-RERA record
Locality / addressJubilee Hills Check Post; plot/address recorded as 8-2-293/82/A/CC RERA filing
Revenue villageShaikpet Village in the GHMC permit and title materials; the RERA project record also identifies “Jubilee Hills Check Post.”
Mandal / district / PINShaikpet / Hyderabad / 500033 RERA record
Project survey identifiers16/3 (P), 20/part, 403/Part (registration certificate); the GHMC permit identifies Sy.No.16/3(P).
Site area23,661.77 sq. m total; 383.37 sq. m road-affected area; 23,278.40 sq. m net area, as stated in the GHMC permit. RERA filing
Boundaries in RERA recordEast: Road No. 2, Banjara Hills; West: Road No. 1, Jubilee Hills; North: Road; South: KBR Park. RERA filing

Development identity

ItemRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building permit53442/HO/CZ/Cir-10/2016, approved 21 02 2018 Approvals record
Approved built-up area66,997.12 sq. m total, comprising residential area 63,659.14 and amenities area 3,337.98, as listed in the permit. RERA filing
Buildings / blocksRERA lists 8 total building units; the permit describes a multi-storied residential building and ground/first-floor amenities. The supplied materials do not explain how the eight RERA building units correspond to the permit’s building description. RERA filing
Sanctioned configuration in permit3 cellars, Ground + (7) upper floors; permit records height 28.80 m.
Parking levelsPermit records 5 parking floors and Cellars 3; it requires approved cellar and stilt areas to be used exclusively for parking. No parking-space count is supplied.
UnitsRERA filing lists 126 proposed units across 8 buildings; permit text separately states 128 Residential Units for the sanctioned plan. The permit also says a proposed modification to G+10 floors and 174 apartments was pending. RERA filing RERA unit table

Offering and status

ItemRecord
Configurations and RERA saleable area3BHK: 14 units, 309.74 sq. m; 4BHK: 32 units, 564.5 sq. m; 5BHK: 80 units, 666.35 sq. m. RERA unit table RERA unit details
Booked / available3BHK: 13 / 1; 4BHK: 11 / 21; 5BHK: 34 / 46. Counts are from the TG-RERA portal; no as-of date is supplied, so treat them as indicative. RERA unit table
Recorded completion datesOriginal and revised proposed completion dates: 30/09/2022. RERA record RERA filing
Construction stageRERA record reports 90% completeness; this is a recorded progress figure, not an independent site inspection. RERA record
Occupancy / completion certificateNo project or tower-specific occupancy/completion certificate is included in the supplied evidence. The permit says an occupancy certificate is required before occupation.

Registration validity, the promoter’s completion undertaking and occupancy-certificate status are distinct: the registration certificate records validity ending 30/09/2022; the RERA record gives the same date as the completion deadline; and the supplied documents do not establish that an occupancy certificate has been issued.

2. The project story

  • Mantri A is a residential apartment development recorded at Jubilee Hills Check Post, Shaikpet, Hyderabad, on land identified in the project materials by 16/3 (P), 20/part and 403/Part. The GHMC permit is for a multi-storied residential building with residential units and amenities; the RERA filing describes eight buildings and 126 proposed units. RERA record RERA unit table
  • The permit describes a sanctioned arrangement of three cellars and Ground + seven upper floors, with amenities on the ground and first floors. It also records a proposed modification to G+10 floors and 174 apartments as pending before the appropriate authorities; that pending proposal is not evidence of an approved modification.
  • The RERA record reports 90% completeness and the completion date of 30/09/2022. These are recorded project disclosures, not independent verification of current construction or completed facilities. No occupancy/completion certificate or tower-wise completion status is present in the supplied materials. RERA record RERA filing

3. Master plan, architecture & building design

  • The GHMC permit records a site area of 23,661.77 sq. m, a road-affected area of 383.37 sq. m, and a net area of 23,278.40 sq. m. It gives total approved built-up area as 66,997.12 sq. m, with 63,659.14 residential area and 3,337.98 amenities area. These are permit figures; the evidence does not separately identify FSI-counted area, gross built-up area or carpet area.
  • The permit describes 3 cellars, Ground + (7) upper floors, height 28.80 m, and amenities on the ground and first floors. It records five parking floors and states that the cellars and stilts approved for parking must remain for vehicle parking. The RERA filing lists eight buildings, but the supplied drawings/extractions do not establish their arrangement, footprints, flats per floor, lift and stair positions, internal circulation or tower-by-tower organization. RERA filing
  • The permit lists a 2387.49 m² tot-lot and requires the organized open space shown in the plan to be handed over to GHMC by registered gift deed before obtaining an occupancy certificate. The supplied evidence does not include a readable site or floor-plan drawing from which landscaping, roads, access routes or open-space layout can be described further. Floor plans

4. Homes, configurations & floor plans

The TG-RERA unit record lists 126 apartments in three configurations. Booked and available counts have no recorded as-of date and should be treated as indicative. The two available floor-plan drawings are scans pending measurement; no software-measured carpet areas or room dimensions are available. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK14131309.74 sq. mNot measuredNot supplied
4BHK321121564.5 sq. mNot measuredNot supplied
5BHK803446666.35 sq. mNot measuredNot supplied

Saleable area is the area recorded in the RERA unit filing. Carpet area is not measured in the supplied drawings; the evidence therefore does not support a carpet-area or loading figure, or descriptions of room sizes and typical floor arrangements. RERA unit details Floor plans

5. Parking & vehicle circulation

The GHMC permit records five parking floors and three cellars, and requires the approved cellar and stilt areas to be used exclusively for parking, without partitions or conversion to another use. It also requires one premises entry and one exit, each with minimum width 4.5 m and height clearance 5 m.

No sanctioned parking-space count, resident or visitor allocation, accessible-space count, bay dimensions, ramp arrangement, internal driveway details, EV charging provision or unit-specific parking allocation is established by the supplied evidence. A parking bay shown in a plan, if any, would not by itself establish exclusive ownership or allocation.

6. Amenities, recreation & open spaces

The table below separates facilities listed in the GHMC permit from RERA-declared amenity/infrastructure records and promoter-site claims. The supplied evidence does not independently verify completion of any facility. RERA amenities Promoter website

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot / open spacePermit lists 2387.49 m² tot-lot; organized open space shown in the plan is to be handed over to GHMC through registered gift deed before OC.GHMC permitRequired by permit; completion/hand-over not evidenced
Swimming pool and separate toddlers’ poolListed without size or quantity detail.Promoter-site amenity listing Promoter websiteMarketing claim; delivery not verified
Basketball courtListed without dimensions.Promoter-site amenity listing Promoter websiteMarketing claim; delivery not verified
Squash courtListed without dimensions.Promoter-site amenity listing Promoter websiteMarketing claim; delivery not verified
Mini theatreListed without size or capacity.Promoter-site amenity listing Promoter websiteMarketing claim; delivery not verified
Business centreListed without size or capacity.Promoter-site amenity listing Promoter websiteMarketing claim; delivery not verified
Karaoke roomListed without size or capacity.Promoter-site amenity listing Promoter websiteMarketing claim; delivery not verified
Beauty parlour / hair salonListed without size.Promoter-site amenity listing Promoter websiteMarketing claim; delivery not verified
Steam, sauna and massage roomListed in promoter-site amenity material.Promoter-site amenity listing Promoter websiteMarketing claim; delivery not verified
Private swimming poolPromoter-site listing refers to private pools for apartments with terraces and penthouses.Promoter-site amenity listing Promoter websiteMarketing claim; unit-specific provision and delivery not verified

7. Utilities, building services & safety

  • The GHMC permit requires a water-recycling plant, service utilities, storm-water disposal, sewerage, rainwater-harvesting pits, garbage disposal, a garbage house and space for a transformer. It specifies separate underground static water storage and residential terrace tanks of 25,000 litres each, and 12 rainwater-harvesting pits. These are permit requirements; the supplied evidence does not verify installation, capacity in operation or service connections.
  • The permit lists hose reels and down-comers and requires an automatic sprinkler system if basement area exceeds 200 sq. m. It also references conditions in Fire Services Department letter RCNo.3768/MSB/CR/Hyd/2013 dated 05-06-2013. No fire-clearance certificate, as-built fire-system record, lift schedule, generator/backup specification, security-system plan or accessibility details are supplied.
  • RERA’s amenity record marks water supply, sewerage, storm-water drains, sewage/sullage treatment, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection, electrical meter/sub-station/receiving station, internal roads/footpaths, street lighting, community buildings and recreational open space as available items. Its percentages range from 0% to 10%; these are portal progress fields, not independent completion verification. RERA amenities

8. Location, access & connectivity

The registered project location is Jubilee Hills Check Post, Shaikpet, Hyderabad, PIN 500033; the permit identifies Shaikpet Village and gives the site address as 8-2-293/82/A/CC in the RERA record. The RERA-recorded boundaries are Road No. 2, Banjara Hills to the east; Road No. 1, Jubilee Hills to the west; a road to the north; and KBR Park to the south. RERA record RERA filing RERA filing

The GHMC permit refers to an 18 mt. road width and requires a 4.5 m-wide entry and exit with 5 m height clearance. The supplied location data identifies Financial District (Nanakramguda) at 1.2 km; it does not provide a source or measurement method for that distance. Location record

9. Developer & development status

  • The registered legal promoter is Jubilee Hills Landmark Projects Pvt Ltd, a company. The RERA record lists GSTIN 36AABCJ6531F1ZR. Its registration certificate states a promoter office as “Village: VENKATGIRI I, Mandal: Shaikpet, District: Hyderabad, Pin: 500033”; no registered office street address or official contact details are supplied in the project evidence. RERA record Corporate record
  • The promoter’s Form B declarations give a completion undertaking of 30.09.2022. The revised declaration identifies loans from Allahabad Bank Limited and Yes Bank Limited as encumbrances; these are promoter disclosures, not lender confirmations. The project record gives 90% completeness, but the supplied data does not provide a verified current site inspection or tower-wise progress breakdown. RERA record
  • The promoter website is listed as mantri.in in the project record. Details on that site, including amenities, are marketing material rather than evidence of sanction or delivery. Parties record Promoter website

10. Approvals, official records & documents

TG-RERA registration
Supplied evidenceRegistration Certificate, P02500000549, Form C, issued 27/03/2019
What it establishesRegistration for Mantri A; certificate states validity ending 30/09/2022 and includes the separate-account condition.
GHMC building permit
Supplied evidencePermit 53442/HO/CZ/Cir-10/2016, approved 21 02 2018
What it establishesConditional sanction for the building configuration and related conditions summarized above.
RERA Form B declarations
Supplied evidenceDocuments 16613 and 88107
What it establishesPromoter declarations on title, encumbrances, project funds, approvals and completion undertaking.
Title due-diligence report
Supplied evidenceDocument 26013
What it establishesTitle-report material concerning the project land; detailed title-chain review is addressed separately.
Status of conveyance / sale deed
Supplied evidenceDocument 16645
What it establishesExtracted record of a registered sale deed dated 19 September 2006 for the stated land extent.
Building / layout drawings
Supplied evidenceFloor-plan data records two drawings, both scans pending measurement; no layout plan is supplied in the evidence available for this section. Floor plans
What it establishesDrawing-based unit measurement and detailed layout description are unavailable.
Occupancy/completion certificate
Supplied evidenceNot present in supplied documents
What it establishesIssuance and tower/phase scope are not established by this evidence.

The GHMC permit sets out project conditions, including submission of commencement and completion notices, obtaining an occupancy certificate before occupation, and prior approval for construction modifications. The permit’s detailed conditions and their compliance status are not determined here.

Other registrations of Mantri A

Frequently asked questions

Is Mantri A registered with Telangana RERA?

Yes. Mantri A is registered with the Telangana Real Estate Regulatory Authority as P02500000549; the registration status is On-Going Project.

Who is the developer of Mantri A?

The promoter named in the RERA registration is Jubilee hills Landmark Projects Pvt Ltd.

Where is Mantri A located?

Mantri A is in Jubilee hills check post, Shaikpet, Hyderabad, Telangana (500033).

When will Mantri A be completed?

The promoter's proposed date of completion filed with RERA is 30/09/2022. This is the promoter's declaration, not a guarantee.