Sai Venkateswara Phase-II
K LAVANYA AND OTHERS · Sangareddy · RERA P01100003988
SAI VENKATESWARA PHASE-II is a plotted development at MASANPALLY, KONDAPUR mandal, Sangareddy district, developed by registered promoter K LAVANYA AND OTHERS. The RERA-filed site area is 14,265.17 sq. m, and the draft-layout order identifies 42 plots; plot configurations are not supplied. The project is registered with TG-RERA as P01100003988, with proposed completion on 19/04/2023.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered project name | SAI VENKATESWARA PHASE-II RERA record |
| Project type | Plotted development / layout RERA record RERA filing |
| Phase / registered portion | Phase-II; the RERA certificate identifies the registered project as SAI VENKATESWARA PHASE-II. RERA record |
| TG-RERA registration | P01100003988 RERA record |
| Registration validity | 22/01/2022 to 19/04/2023; the supplied certificate says registration was not extended. This is registration validity, not a completion or occupancy certificate. |
| Registered promoter | K LAVANYA AND OTHERS RERA record |
| RERA-recorded project status | “New Project” in the project filing. The supplied record does not establish current on-site construction status. RERA filing |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | Mansanpally / MASANPALLY RERA record |
| Revenue village | MASANPALLY; the DT&CP draft-layout document identifies Mansanpally village / Mansanpally Gram Panchayat. RERA record |
| Mandal | KONDAPUR RERA record RERA filing |
| District | Sangareddy RERA record |
| PIN | 509325 RERA record |
| Project survey number | 33P in the RERA record; the draft layout states Sy. No. 33/P. No project subdivision is disclosed in the supplied project record. RERA record Land records |
| RERA-filed site area | 14,265.17 sq. m total and net area; affected area reported as 0 sq. m. RERA filing Land records |
| Draft-layout area | Ac.3.525 Cents; 17061.00 Sq. Yds. |
| Boundaries as filed | East: OWNERS EXISTING DTCP LAYOUT; West: NEIGHBOURS LAND; North: OWNERS LAND; South: 6 M NALA. RERA filing |
| Independently retrieved cadastral record | Whole survey 33 has a recorded extent of 48848.67 sq. m; this is a survey-level figure, not the project parcel area. Cadastral map |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | DT&CP order, delegated to Mansanpally Panchayat |
| Principal layout approval | Draft Technical Layout Pattern approval Draft-TLP.No.116/2021/HRO/H1, dated 19.04.2021; file no. r.ROC.No.508/2021/HRO/H1; application no. E. Panchayath No. 16093/1437. Approvals record |
| Layout scale in approval document | 42 plots |
| Area allocation in draft-layout document | Layout area: Ac.3.525 Cents; 17061.00 Sq. Yds.; plotted area: Ac.2.2525 Cents; 10902.10 Sa Yds. (63.90%); road area: Ac.0.92 Cents; 4452.80 Sq. Yds. (26.10%); open space: Ac.0.3525 Cents; 1706.10 Sq.Yds. (10.00 %). |
| Approved built-up area / buildings / floors | Not disclosed for this plotted-layout project in the supplied records. RERA filing |
| Mortgage area | RERA filing reports 1407.37 sq. m; the draft-layout order identifies plots 38 to 42, 1683.20 Sq. Yards, as mortgage area. RERA filing |
Offering and status
| Item | Project record |
|---|---|
| Unit type | Plots; the draft-layout order specifies 42 plots. Plot sizes and plot-wise inventory are not supplied here. RERA record |
| Booked / available counts | Not supplied. RERA filing |
| Construction / development stage | RERA filing gives 80% completeness; this is a filed figure, not independent site verification. RERA record |
| Completion dates in supplied records | RERA registration profile: proposed completion 19/04/2023. Form B declaration: completion undertaking by 11th December, 2022. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is supplied in the project evidence. Document index |
2. The project story
SAI VENKATESWARA PHASE-II is recorded with TG-RERA as a plotted development at Mansanpally, in Kondapur mandal, Sangareddy district. Its registered survey reference is 33P; the DT&CP draft-layout order describes the land as Sy. No. 33/P and a 42-plot layout. The approval document allocates land to plots, roads and open space, rather than describing apartment buildings or residential towers. RERA record RERA filing
The RERA profile reports 80% completeness, but the supplied materials do not provide a dated site-inspection record or other independent confirmation of that progress. The draft-layout order lists infrastructure and development works, including roads, drains, water supply, sewerage disposal, rainwater-harvesting pits, greenery, street lighting and electricity facilities; the documents do not establish that these works have been completed. RERA record
3. Master plan, architecture & building design
The supplied DT&CP order approves a draft technical layout pattern for 42 plots on Sy. No. 33/P. It records a layout area of Ac.3.525 Cents; 17061.00 Sq. Yds., with 63.90% allocated to plotted area, 26.10% to roads and 10.00 % to open space. The approval document names plots 38 to 42 as the mortgage area.
The evidence supplied does not include a readable layout drawing or plot schedule, so plot dimensions, individual plot arrangement, internal-road geometry and the precise location of open spaces cannot be described here. No building count, floor configuration, building footprint or approved built-up area is established for this plotted project. The RERA filing’s “Approved Built up Area” field states 9115.54 sq. m, but the supplied record does not explain its scope or how it applies to the plotted layout. RERA filing
4. Homes, configurations & floor plans
This is a plotted layout, not an apartment configuration schedule. The draft-layout order identifies 42 plots, but the supplied evidence does not provide plot-wise numbers beyond the mortgage plots, plot-size bands, booked/available counts or saleable-area schedule.
The supplied floor-plan record contains two drawings, both awaiting scan review; no software-measured areas or room dimensions are available. Apartment carpet-area or saleable-area comparisons are therefore not applicable on the evidence provided. Floor plans
5. Parking & vehicle circulation
The supplied project evidence does not establish sanctioned parking counts, parking areas, visitor or accessible spaces, or parking-allotment arrangements. The draft-layout approval identifies roads as Ac.0.92 cents; 4452.80 Sq. Yds. (26.10%) and requires roads to be opened for access to neighbouring sites; it does not provide road widths or a circulation drawing beyond the boundary description of a 6 M NALA to the south. RERA filing
6. Amenities, recreation & open spaces
| Description / size | Ac.0.3525 Cents; 1706.10 Sq.Yds. (10.00 %) in the draft-layout area allocation; the order states it is to be handed to the Gram Panchayat by registered gift deed before final layout release. |
|---|---|
| Declared progress / verified status | Required in the draft approval; completion or transfer is not evidenced. |
| Description / size | Listed as a layout development item. |
|---|---|
| Declared progress / verified status | Specified in the approval document; completion not evidenced. |
| Description / size | Listed as a layout development item. |
|---|---|
| Declared progress / verified status | Specified in the approval document; completion not evidenced. |
| Description / size | Listed in the RERA amenities record without a size or description. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity-field entry shows 0% progress; no completion verification supplied. |
| Description / size | RERA amenities record marks “YES”; no size or count supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Filed availability entry; completion not evidenced. |
A third-party listing mentions a clubhouse, swimming pool, gym and children’s play area, but these are not established as sanctioned or delivered facilities in the supplied project records; they are not treated as confirmed project amenities in this overview. Promoter website
7. Utilities, building services & safety
The draft-layout approval lists proposed layout infrastructure: drains and channelization of nalas; rainwater-harvesting pits; street lighting and electricity facilities; a sewerage-disposal system; and protected water supply. It does not provide capacities, engineering designs, completion certificates or independently verified operating status.
The RERA amenities record lists water supply, sewerage, storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection and an electrical meter room/sub-station/receiving station. These entries are filing disclosures; the supplied record does not establish their completion, capacity or statutory clearance. RERA amenities
8. Location, access & connectivity
The registered project location is MASANPALLY village, Kondapur mandal, Sangareddy district, PIN 509325. The filed boundary description places an existing DTCP layout to the east, neighbouring land to the west, owners’ land to the north and a 6 M NALA to the south. RERA record RERA filing
The supplied location data gives an approximate distance of 77.7 km to the nearest sampled Outer Ring Road interchange. No other measured approach-road, public-transport or landmark distances are supplied. Location record Cadastral map
9. Developer & development status
The registered promoter is K LAVANYA AND OTHERS. The RERA record describes the organization type as “Others” and the associated description as “Partnership”; a corporate registration identifier is not supplied in the project evidence. The RERA certificate lists the promoter office as Village Madhapur, Mandal Serilingampally, District Ranga Reddy, PIN 500081. RERA record RERA filing
The Form B affidavit is dated 18th July, 2021 and is made by K Lavanya as an authorized signatory for the promoter. It declares a legal-title or authenticated-title basis, states that the land is free from encumbrances, and undertakes completion by 11th December, 2022. These are promoter declarations in the filed affidavit.
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C registration certificate for SAI VENKATESWARA PHASE-II, registration P01100003988, issued 22/01/2022, valid through 19/04/2023. |
| Draft layout approval | DT&CP Draft Technical Layout Pattern approval Draft-TLP.No.116/2021/HRO/H1, dated 19.04.2021, file no. r.ROC.No.508/2021/HRO/H1, application no. E. Panchayath No. 16093/1437; delegated to Mansanpally Panchayat. |
| Promoter declaration | Form B affidavit-cum-declaration by K Lavanya, dated 18th July, 2021. |
| Final layout release / completion evidence | Not supplied. The draft approval itself states that it is subject to conditions before final layout release. |
| Occupancy / completion certificate | Not supplied in the available project documents. Document index |
1. Project at a glance
Project identity
Registered project name: SAI VENKATESWARA PHASE-II
Project type: Plotted development / layout
Phase / registered portion: Phase-II; the RERA certificate identifies the registered project as SAI VENKATESWARA PHASE-II.
TG-RERA registration: P01100003988
Registration validity: 22/01/2022 to 19/04/2023; the supplied certificate says registration was not extended. This is registration validity, not a completion or occupancy certificate.
Registered promoter: K LAVANYA AND OTHERS
RERA-recorded project status: “New Project” in the project filing. The supplied record does not establish current on-site construction status.
Land and geographic identity
Locality: Mansanpally / MASANPALLY
Revenue village: MASANPALLY; the DT&CP draft-layout document identifies Mansanpally village / Mansanpally Gram Panchayat.
Mandal: KONDAPUR
District: Sangareddy
PIN: 509325
Project survey number: 33P in the RERA record; the draft layout states Sy. No. 33/P. No project subdivision is disclosed in the supplied project record.
RERA-filed site area: 14,265.17 sq. m total and net area; affected area reported as 0 sq. m.
Draft-layout area: Ac.3.525 Cents; 17061.00 Sq. Yds.
Boundaries as filed: East: OWNERS EXISTING DTCP LAYOUT; West: NEIGHBOURS LAND; North: OWNERS LAND; South: 6 M NALA.
Independently retrieved cadastral record: Whole survey 33 has a recorded extent of 48848.67 sq. m; this is a survey-level figure, not the project parcel area.
Development identity
Sanctioning authority: DT&CP order, delegated to Mansanpally Panchayat
Principal layout approval: Draft Technical Layout Pattern approval Draft-TLP.No.116/2021/HRO/H1, dated 19.04.2021; file no. r.ROC.No.508/2021/HRO/H1; application no. E. Panchayath No. 16093/1437.
Layout scale in approval document: 42 plots
Area allocation in draft-layout document: Layout area: Ac.3.525 Cents; 17061.00 Sq. Yds.; plotted area: Ac.2.2525 Cents; 10902.10 Sa Yds. (63.90%); road area: Ac.0.92 Cents; 4452.80 Sq. Yds. (26.10%); open space: Ac.0.3525 Cents; 1706.10 Sq.Yds. (10.00 %).
Approved built-up area / buildings / floors: Not disclosed for this plotted-layout project in the supplied records.
Mortgage area: RERA filing reports 1407.37 sq. m; the draft-layout order identifies plots 38 to 42, 1683.20 Sq. Yards, as mortgage area.
Offering and status
Unit type: Plots; the draft-layout order specifies 42 plots. Plot sizes and plot-wise inventory are not supplied here.
Booked / available counts: Not supplied.
Construction / development stage: RERA filing gives 80% completeness; this is a filed figure, not independent site verification.
Completion dates in supplied records: RERA registration profile: proposed completion 19/04/2023. Form B declaration: completion undertaking by 11th December, 2022.
Occupancy / completion certificate: No occupancy or completion certificate is supplied in the project evidence.
2. The project story
SAI VENKATESWARA PHASE-II is recorded with TG-RERA as a plotted development at Mansanpally, in Kondapur mandal, Sangareddy district. Its registered survey reference is 33P; the DT&CP draft-layout order describes the land as Sy. No. 33/P and a 42-plot layout. The approval document allocates land to plots, roads and open space, rather than describing apartment buildings or residential towers.
The RERA profile reports 80% completeness, but the supplied materials do not provide a dated site-inspection record or other independent confirmation of that progress. The draft-layout order lists infrastructure and development works, including roads, drains, water supply, sewerage disposal, rainwater-harvesting pits, greenery, street lighting and electricity facilities; the documents do not establish that these works have been completed.
3. Master plan, architecture & building design
The supplied DT&CP order approves a draft technical layout pattern for 42 plots on Sy. No. 33/P. It records a layout area of Ac.3.525 Cents; 17061.00 Sq. Yds., with 63.90% allocated to plotted area, 26.10% to roads and 10.00 % to open space. The approval document names plots 38 to 42 as the mortgage area.
The evidence supplied does not include a readable layout drawing or plot schedule, so plot dimensions, individual plot arrangement, internal-road geometry and the precise location of open spaces cannot be described here. No building count, floor configuration, building footprint or approved built-up area is established for this plotted project. The RERA filing’s “Approved Built up Area” field states 9115.54 sq. m, but the supplied record does not explain its scope or how it applies to the plotted layout.
4. Homes, configurations & floor plans
This is a plotted layout, not an apartment configuration schedule. The draft-layout order identifies 42 plots, but the supplied evidence does not provide plot-wise numbers beyond the mortgage plots, plot-size bands, booked/available counts or saleable-area schedule.
The supplied floor-plan record contains two drawings, both awaiting scan review; no software-measured areas or room dimensions are available. Apartment carpet-area or saleable-area comparisons are therefore not applicable on the evidence provided.
5. Parking & vehicle circulation
The supplied project evidence does not establish sanctioned parking counts, parking areas, visitor or accessible spaces, or parking-allotment arrangements. The draft-layout approval identifies roads as Ac.0.92 cents; 4452.80 Sq. Yds. (26.10%) and requires roads to be opened for access to neighbouring sites; it does not provide road widths or a circulation drawing beyond the boundary description of a 6 M NALA to the south.
6. Amenities, recreation & open spaces
| Description / size | Ac.0.3525 Cents; 1706.10 Sq.Yds. (10.00 %) in the draft-layout area allocation; the order states it is to be handed to the Gram Panchayat by registered gift deed before final layout release. |
|---|---|
| Declared progress / verified status | Required in the draft approval; completion or transfer is not evidenced. |
| Description / size | Listed as a layout development item. |
|---|---|
| Declared progress / verified status | Specified in the approval document; completion not evidenced. |
| Description / size | Listed as a layout development item. |
|---|---|
| Declared progress / verified status | Specified in the approval document; completion not evidenced. |
| Description / size | Listed in the RERA amenities record without a size or description. |
|---|---|
| Declared progress / verified status | RERA amenity-field entry shows 0% progress; no completion verification supplied. |
| Description / size | RERA amenities record marks “YES”; no size or count supplied. |
|---|---|
| Declared progress / verified status | Filed availability entry; completion not evidenced. |
A third-party listing mentions a clubhouse, swimming pool, gym and children’s play area, but these are not established as sanctioned or delivered facilities in the supplied project records; they are not treated as confirmed project amenities in this overview.
7. Utilities, building services & safety
The draft-layout approval lists proposed layout infrastructure: drains and channelization of nalas; rainwater-harvesting pits; street lighting and electricity facilities; a sewerage-disposal system; and protected water supply. It does not provide capacities, engineering designs, completion certificates or independently verified operating status.
The RERA amenities record lists water supply, sewerage, storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management, water conservation/rainwater harvesting, energy management, fire protection and an electrical meter room/sub-station/receiving station. These entries are filing disclosures; the supplied record does not establish their completion, capacity or statutory clearance.
8. Location, access & connectivity
The registered project location is MASANPALLY village, Kondapur mandal, Sangareddy district, PIN 509325. The filed boundary description places an existing DTCP layout to the east, neighbouring land to the west, owners’ land to the north and a 6 M NALA to the south.
The supplied location data gives an approximate distance of 77.7 km to the nearest sampled Outer Ring Road interchange. No other measured approach-road, public-transport or landmark distances are supplied.
9. Developer & development status
The registered promoter is K LAVANYA AND OTHERS. The RERA record describes the organization type as “Others” and the associated description as “Partnership”; a corporate registration identifier is not supplied in the project evidence. The RERA certificate lists the promoter office as Village Madhapur, Mandal Serilingampally, District Ranga Reddy, PIN 500081.
The Form B affidavit is dated 18th July, 2021 and is made by K Lavanya as an authorized signatory for the promoter. It declares a legal-title or authenticated-title basis, states that the land is free from encumbrances, and undertakes completion by 11th December, 2022. These are promoter declarations in the filed affidavit.
10. Approvals, official records & documents
TG-RERA registration: Form C registration certificate for SAI VENKATESWARA PHASE-II, registration P01100003988, issued 22/01/2022, valid through 19/04/2023.
Draft layout approval: DT&CP Draft Technical Layout Pattern approval Draft-TLP.No.116/2021/HRO/H1, dated 19.04.2021, file no. r.ROC.No.508/2021/HRO/H1, application no. E. Panchayath No. 16093/1437; delegated to Mansanpally Panchayat.
Promoter declaration: Form B affidavit-cum-declaration by K Lavanya, dated 18th July, 2021.
Final layout release / completion evidence: Not supplied. The draft approval itself states that it is subject to conditions before final layout release.
Occupancy / completion certificate: Not supplied in the available project documents.
Other registrations of Sai Venkateswara
Frequently asked questions
Is SAI VENKATESWARA PHASE-II registered with Telangana RERA?
Yes. SAI VENKATESWARA PHASE-II is registered with the Telangana Real Estate Regulatory Authority as P01100003988; the registration status is New Project.
Who is the developer of SAI VENKATESWARA PHASE-II?
The promoter named in the RERA registration is K LAVANYA AND OTHERS.
Where is SAI VENKATESWARA PHASE-II located?
SAI VENKATESWARA PHASE-II is in Mansanpally, MASANPALLY, KONDAPUR, Sangareddy, Telangana (509325).
When will SAI VENKATESWARA PHASE-II be completed?
The promoter's proposed date of completion filed with RERA is 19/04/2023. This is the promoter's declaration, not a guarantee.