Vkr Residency
RAJPUROHIT · Mahabubnagar · RERA P01400007875
VKR RESIDENCY is a residential apartment project near Erra Satyam Junction Road, Ward No. 1, Station Road, in Mahabubnagar Urban, Mahabubnagar. The registered promoter is RAJPUROHIT. The project has a land area of 1693.84 sq.m and one building, Building - A (SHRAVAN DEVELOPER), with 1 stilt + 5 upper floors and 25 homes: 10 two-bedroom and 15 three-bedroom units. It is registered under TG-RERA number P01400007875, with proposed completion by 26th AUG, 2026.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | VKR RESIDENCY RERA record |
| Project type / phase | Residential apartment project; a single registered project/building is recorded. A separate phase name or phase number is not disclosed. RERA record RERA filing RERA unit table |
| TG-RERA registration | P01400007875; registration certificate issued 16/03/2024, valid through 26/08/2026. Registration validity is distinct from the completion date. RERA record |
| Registered promoter | RAJPUROHIT in the project record; the certificate names Mr./Ms. Rajpurohit Shravan. The promoter’s entity type is not disclosed in the supplied record. RERA record RERA filing |
| RERA record status | New Project; registration is recorded. The supplied record does not establish a later extension. RERA filing |
Land and geographic identity
| Item | Record |
|---|---|
| Locality / address | Near Erra Satyam Junction Road, Ward No. 1; Station Road is also recorded as the street/locality. RERA record RERA filing |
| Revenue village | Not disclosed in the project land record. The approval document names Mahaboobnagar, but the supplied evidence does not establish a revenue-village name for the project parcel. Land records |
| Mandal / district / PIN | Mahabubnagar Urban / Mahabubnagar / 509001. RERA record RERA filing |
| Plot identifiers | House Nos. 1-6-61 and 1-6-61/A. RERA filing |
| Survey numbers / subdivisions | Not disclosed in the project land record. Land records |
| Site extent | Total site area 1693.84 sq.m; road-affected area 174.42 sq.m; net area 1519.42 sq.m. RERA filing |
| Boundaries | East: houses of others; West: 12-00 feet wide road; North: road; South: 40-00 feet road. RERA filing |
| Additional plan area entry | The plan records 793.11 as “vacant plot area”; its measurement unit is not stated in the extracted field. |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Mahaboobnagar Municipality/Municipal Corporation. Approvals record |
| Principal building approval | Approval No. 0054/BP/3063/2023, dated 26 August 2023. Approvals record |
| Other approval references | File No. 008444/BP/DTCP/3063/0071/2023; application No. TS/049836/2023. These are approval-document references, not separate building counts. Approvals record |
| Building / floors | One residential building, Building - A (SHRAVAN DEVELOPER); 1 stilt + 5 upper floors. The approval lists residential upper-floor area 3,299.44 m² and stilt area 700.24 m². RERA filing |
| Approved built-up area | 4025.54 m² is recorded in the RERA project fields as approved built-up area. The plan separately labels 3,299.44 as proposed built-up area excluding parking and 4,025.54 including parking. RERA filing |
| Unit count | 25 units in the plan; RERA unit record also lists 25: 10 two-bedroom and 15 three-bedroom units. RERA unit table |
| Parking | The plan records parking area proposed as 726.10 and visitor parking as 69.54; the extracted entries do not give a reliable count of parking spaces. The approval requires stilt/cellar parking shown in the plan to be used for vehicle parking. |
Offering and status
| Item | Record |
|---|---|
| Configurations | 2BHK (10 units) and 3BHK (15 units). RERA unit table |
| RERA saleable area | 2BHK: 122.17 sq.m each; 3BHK: 156.08 sq.m each. RERA unit table |
| Booking / availability | Portal-derived counts show 0 booked and 10 available 2BHK units, and 0 booked and 15 available 3BHK units. The portal record has no as-of date, so counts are indicative. RERA unit table |
| Completion deadline | Promoter’s Form B declares completion by 26th AUG, 2026; the project record gives 26/08/2026. This is the declared project completion date, not the registration-validity statement or an OC. RERA record |
| Construction stage | Not established by the supplied evidence. The amenity record shows 0% for the listed progress fields; this does not independently establish the physical construction stage. RERA amenities |
| Occupancy certificate | No occupancy certificate for VKR RESIDENCY is established by the supplied project documents. The available OC document concerns a different project and is not evidence for this building. Document index |
2. The project story
- VKR RESIDENCY is registered as a residential apartment project at House Nos. 1-6-61 and 1-6-61/A, near Erra Satyam Junction Road, Ward No. 1, on Station Road in Mahabubnagar. Its filed land area is 1693.84 sq.m, including a recorded road-affected portion of 174.42 sq.m and a net area of 1519.42 sq.m. The project record does not disclose the revenue village or survey/subdivision numbers. RERA record RERA filing Land records
- The approval record describes one apartment building, Building - A, with a stilt level and five upper floors. The RERA unit schedule lists 25 homes: 10 two-bedroom and 15 three-bedroom units. The project completion date is declared as 26 August 2026. The supplied materials do not establish construction progress through an independent site inspection, or show an occupancy certificate for this project. RERA unit table
3. Master plan, architecture & building design
- The building-permission document records one residential apartment building with 1 stilt + 5 upper floors. Its area entries identify a 700.24 m² stilt and 3,299.44 m² of residential upper-floor area; the RERA fields list approved built-up area as 4025.54 m². The plan also gives 3,299.44 as proposed built-up area excluding parking and 4,025.54 including parking. These are the figures and labels in the supplied approval/filing record; no separate FSI-counted area or carpet area for the building is provided. RERA filing
- The plan identifies 174.42 sq.m as road-affected area and 1519.42 sq.m as net plot area. It records a front setback of 4.00 and rear and side setbacks of 5.00 each; the extracted entries do not state units for those setback figures. The plan also lists road widths of 3.66 M, 9.14 M, 9.14 MT, 15.24 MT, and 4.5 M. It does not provide enough verified drawing-derived information here to describe the building footprint, lifts, stairs, entrances, or floor-by-floor circulation.
4. Homes, configurations & floor plans
The RERA filing lists 10 two-bedroom and 15 three-bedroom apartments. The saleable areas below are RERA-filed. Carpet-area figures are software measurements from the filed plan drawing (document 396650), not RERA disclosures; the measurement record says the drawing measurements require review. Saleable area and carpet area are different measures, and the supplied evidence does not establish that the filed saleable areas are carpet areas. RERA unit table RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 122.17 sq.m | 78.6–83.3 sq.m; median 81.2 sq.m | 34% |
| 3BHK | 15 | 0 | 15 | 156.08 sq.m | 88.9–116.1 sq.m; median 107.3 sq.m | 31% |
The drawing’s typical-floor panel identifies hall, living/dining, kitchen, bedrooms, toilets, wash areas and balconies across the measured layouts. For example, a measured 2BHK layout includes a hall labelled 4.26 × 4.87 m, two bedrooms, dining/kitchen and two balconies; a measured 3BHK layout includes living/dining labelled 7.82 × 4.86 m, three bedrooms, kitchen/pooja, toilets, wash area and a balcony. These are drawing-based measurements, not RERA-filed room specifications. RERA unit details
5. Parking & vehicle circulation
- The building plan records proposed parking area of 726.10 and visitor parking of 69.54; the extracted area entries do not specify their measurement units or give a dependable total space count. The approval identifies stilt parking and requires cellar/stilt areas approved for parking to be used exclusively for vehicle parking, without partition walls or rolling shutters. The supplied record does not establish individual apartment parking allocations, accessible spaces, two-wheeler counts, or a verified spaces-per-home ratio.
- The building-permission conditions state that parking places are to be provided with electric-vehicle charging infrastructure. This is an approval condition, not evidence that charging equipment has been installed or is operational.
6. Amenities, recreation & open spaces
The RERA amenity schedule marks several facilities “YES” but records 0% in its progress fields. The building approval also identifies a tot-lot, greenery and rainwater-harvesting-related requirements. Neither the schedule nor the approval extract establishes that these facilities are complete or independently verified. RERA amenities
| Description / size | No project-specific clubhouse or indoor recreation facility is established in the supplied RERA amenity schedule. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Not established. |
| Description / size | Green Strip/TOT LOT/Park is marked “YES”; the approval refers to a tot-lot. No size or capacity is supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Amenity progress field: 0%; completion not independently verified. |
| Description / size | Green Strip/TOT LOT/Park is marked “YES”; the plan lists Green Belt and Green Strip. No area for aggregate recreational open space is supplied. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Amenity progress field: 0%; completion not independently verified. |
| Description / size | Community Buildings and Street Lighting appear in the schedule, without an indicated “YES” or supplied description/size. |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Not established. |
7. Utilities, building services & safety
- The RERA amenity schedule marks Water Supply, Sewerage, Storm Water Drains, Water Conservation/Rain Water Harvesting, Energy management, and Electrical Meter Room/Sub-Station/Receiving Station as “YES”; each listed progress field is 0%. It gives no source, capacity, treatment specifications, storage volumes or completion evidence. RERA amenities
- The building approval requires construction of a rainwater-harvesting structure/percolation pit, a transformer space and a garbage house. It also states requirements concerning fire safety, plumbing, electrical installations and lifts, but the supplied record does not establish the installed systems, capacities, lift count, emergency-stair arrangement, or completed safety clearances. These are approval conditions, not proof of delivery.
- The approval document includes an electric-vehicle charging-infrastructure condition and a condition that an Occupancy Certificate is to be granted only after the prescribed CTI requirements are in place. The supplied evidence does not confirm installation or commissioning of either system.
8. Location, access & connectivity
- The registered project location is near Erra Satyam Junction Road, Ward No. 1, on Station Road, Mahabubnagar, Mahabubnagar Urban, PIN 509001. The stated plot boundaries include a road on the north, a 40-00 feet road on the south, a 12-00 feet wide road on the west, and houses of others to the east. The supplied location record does not provide verified public-transport information or measured distances to nearby landmarks. RERA record RERA filing RERA filing
- The evidence does not establish a revenue-village name or survey number for the project parcel. The supplied cadastral coordinate entry is labelled as a parcel centroid, but no independently verified connectivity assessment is provided. Land records Location record
9. Developer & development status
- The project record identifies the registered promoter as RAJPUROHIT and the registration certificate names Mr./Ms. Rajpurohit Shravan. The project documents identify Shravan Rajpurohit as the developer and as the person signing the Form B declaration on behalf of the promoter. The promoter’s legal entity type, corporate registration identifiers, registered office and official contact details are not established in the supplied project record. RERA record Corporate record
- Form B declares completion by 26th AUG, 2026. That is a promoter declaration; the supplied evidence does not provide independently verified construction progress or an OC for VKR RESIDENCY. The registration certificate states validity through 26/08/2026; registration validity and the declared completion deadline are separate dates, even though the dates shown here coincide.
10. Approvals, official records & documents
| Identifier / date | P01400007875, issued 16/03/2024; valid to 26/08/2026 |
|---|---|
| What the supplied document establishes | FORM C registration certificate for VKR RESIDENCY. |
| Identifier / date | 0054/BP/3063/2023, 26 August 2023 |
|---|---|
| What the supplied document establishes | Mahaboobnagar Municipality/Municipal Corporation approval for Building - A, a residential building with 1 stilt + 5 upper floors. |
| Identifier / date | 008444/BP/DTCP/3063/0071/2023 |
|---|---|
| What the supplied document establishes | File reference shown in the building-approval record. |
| Identifier / date | TS/049836/2023, dated 24 July 2023 |
|---|---|
| What the supplied document establishes | Application reference shown in the proposed building-plan document. |
| Identifier / date | File No. G1/STR-ENG/13/MBNR/2020 |
|---|---|
| What the supplied document establishes | Proposed residential apartment plan; the extracted plan itself does not show a completed approval number or approval date. |
| Identifier / date | Form B, dated 15th day of FEB, 2024 |
|---|---|
| What the supplied document establishes | Promoter-authorized signatory declaration including the stated completion date of 26 August 2026. |
| Identifier / date | No project-specific OC established |
|---|---|
| What the supplied document establishes | The extracted Form–1A record for VKR RESIDENCY contains only “NA.” The other supplied OC, document 652242, identifies a different owner, developer, location and RERA registration and is not an OC for this project. |
1. Project at a glance
Project identity
Registered project name: VKR RESIDENCY
Project type / phase: Residential apartment project; a single registered project/building is recorded. A separate phase name or phase number is not disclosed.
TG-RERA registration: P01400007875; registration certificate issued 16/03/2024, valid through 26/08/2026. Registration validity is distinct from the completion date.
Registered promoter: RAJPUROHIT in the project record; the certificate names Mr./Ms. Rajpurohit Shravan. The promoter’s entity type is not disclosed in the supplied record.
RERA record status: New Project; registration is recorded. The supplied record does not establish a later extension.
Land and geographic identity
Locality / address: Near Erra Satyam Junction Road, Ward No. 1; Station Road is also recorded as the street/locality.
Revenue village: Not disclosed in the project land record. The approval document names Mahaboobnagar, but the supplied evidence does not establish a revenue-village name for the project parcel.
Mandal / district / PIN: Mahabubnagar Urban / Mahabubnagar / 509001.
Plot identifiers: House Nos. 1-6-61 and 1-6-61/A.
Survey numbers / subdivisions: Not disclosed in the project land record.
Site extent: Total site area 1693.84 sq.m; road-affected area 174.42 sq.m; net area 1519.42 sq.m.
Boundaries: East: houses of others; West: 12-00 feet wide road; North: road; South: 40-00 feet road.
Additional plan area entry: The plan records 793.11 as “vacant plot area”; its measurement unit is not stated in the extracted field.
Development identity
Sanctioning authority: Mahaboobnagar Municipality/Municipal Corporation.
Principal building approval: Approval No. 0054/BP/3063/2023, dated 26 August 2023.
Other approval references: File No. 008444/BP/DTCP/3063/0071/2023; application No. TS/049836/2023. These are approval-document references, not separate building counts.
Building / floors: One residential building, Building - A (SHRAVAN DEVELOPER); 1 stilt + 5 upper floors. The approval lists residential upper-floor area 3,299.44 m² and stilt area 700.24 m².
Approved built-up area: 4025.54 m² is recorded in the RERA project fields as approved built-up area. The plan separately labels 3,299.44 as proposed built-up area excluding parking and 4,025.54 including parking.
Unit count: 25 units in the plan; RERA unit record also lists 25: 10 two-bedroom and 15 three-bedroom units.
Parking: The plan records parking area proposed as 726.10 and visitor parking as 69.54; the extracted entries do not give a reliable count of parking spaces. The approval requires stilt/cellar parking shown in the plan to be used for vehicle parking.
Offering and status
Configurations: 2BHK (10 units) and 3BHK (15 units).
RERA saleable area: 2BHK: 122.17 sq.m each; 3BHK: 156.08 sq.m each.
Booking / availability: Portal-derived counts show 0 booked and 10 available 2BHK units, and 0 booked and 15 available 3BHK units. The portal record has no as-of date, so counts are indicative.
Completion deadline: Promoter’s Form B declares completion by 26th AUG, 2026; the project record gives 26/08/2026. This is the declared project completion date, not the registration-validity statement or an OC.
Construction stage: Not established by the supplied evidence. The amenity record shows 0% for the listed progress fields; this does not independently establish the physical construction stage.
Occupancy certificate: No occupancy certificate for VKR RESIDENCY is established by the supplied project documents. The available OC document concerns a different project and is not evidence for this building.
2. The project story
- VKR RESIDENCY is registered as a residential apartment project at House Nos. 1-6-61 and 1-6-61/A, near Erra Satyam Junction Road, Ward No. 1, on Station Road in Mahabubnagar. Its filed land area is 1693.84 sq.m, including a recorded road-affected portion of 174.42 sq.m and a net area of 1519.42 sq.m. The project record does not disclose the revenue village or survey/subdivision numbers.
- The approval record describes one apartment building, Building - A, with a stilt level and five upper floors. The RERA unit schedule lists 25 homes: 10 two-bedroom and 15 three-bedroom units. The project completion date is declared as 26 August 2026. The supplied materials do not establish construction progress through an independent site inspection, or show an occupancy certificate for this project.
3. Master plan, architecture & building design
- The building-permission document records one residential apartment building with 1 stilt + 5 upper floors. Its area entries identify a 700.24 m² stilt and 3,299.44 m² of residential upper-floor area; the RERA fields list approved built-up area as 4025.54 m². The plan also gives 3,299.44 as proposed built-up area excluding parking and 4,025.54 including parking. These are the figures and labels in the supplied approval/filing record; no separate FSI-counted area or carpet area for the building is provided.
- The plan identifies 174.42 sq.m as road-affected area and 1519.42 sq.m as net plot area. It records a front setback of 4.00 and rear and side setbacks of 5.00 each; the extracted entries do not state units for those setback figures. The plan also lists road widths of 3.66 M, 9.14 M, 9.14 MT, 15.24 MT, and 4.5 M. It does not provide enough verified drawing-derived information here to describe the building footprint, lifts, stairs, entrances, or floor-by-floor circulation.
4. Homes, configurations & floor plans
The RERA filing lists 10 two-bedroom and 15 three-bedroom apartments. The saleable areas below are RERA-filed. Carpet-area figures are software measurements from the filed plan drawing (document 396650), not RERA disclosures; the measurement record says the drawing measurements require review. Saleable area and carpet area are different measures, and the supplied evidence does not establish that the filed saleable areas are carpet areas.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 122.17 sq.m | 78.6–83.3 sq.m; median 81.2 sq.m | 34% |
| 3BHK | 15 | 0 | 15 | 156.08 sq.m | 88.9–116.1 sq.m; median 107.3 sq.m | 31% |
The drawing’s typical-floor panel identifies hall, living/dining, kitchen, bedrooms, toilets, wash areas and balconies across the measured layouts. For example, a measured 2BHK layout includes a hall labelled 4.26 × 4.87 m, two bedrooms, dining/kitchen and two balconies; a measured 3BHK layout includes living/dining labelled 7.82 × 4.86 m, three bedrooms, kitchen/pooja, toilets, wash area and a balcony. These are drawing-based measurements, not RERA-filed room specifications.
5. Parking & vehicle circulation
- The building plan records proposed parking area of 726.10 and visitor parking of 69.54; the extracted area entries do not specify their measurement units or give a dependable total space count. The approval identifies stilt parking and requires cellar/stilt areas approved for parking to be used exclusively for vehicle parking, without partition walls or rolling shutters. The supplied record does not establish individual apartment parking allocations, accessible spaces, two-wheeler counts, or a verified spaces-per-home ratio.
- The building-permission conditions state that parking places are to be provided with electric-vehicle charging infrastructure. This is an approval condition, not evidence that charging equipment has been installed or is operational.
6. Amenities, recreation & open spaces
The RERA amenity schedule marks several facilities “YES” but records 0% in its progress fields. The building approval also identifies a tot-lot, greenery and rainwater-harvesting-related requirements. Neither the schedule nor the approval extract establishes that these facilities are complete or independently verified.
| Description / size | No project-specific clubhouse or indoor recreation facility is established in the supplied RERA amenity schedule. |
|---|---|
| Declared progress / verified status | Not established. |
| Description / size | Green Strip/TOT LOT/Park is marked “YES”; the approval refers to a tot-lot. No size or capacity is supplied. |
|---|---|
| Declared progress / verified status | Amenity progress field: 0%; completion not independently verified. |
| Description / size | Green Strip/TOT LOT/Park is marked “YES”; the plan lists Green Belt and Green Strip. No area for aggregate recreational open space is supplied. |
|---|---|
| Declared progress / verified status | Amenity progress field: 0%; completion not independently verified. |
| Description / size | Community Buildings and Street Lighting appear in the schedule, without an indicated “YES” or supplied description/size. |
|---|---|
| Declared progress / verified status | Not established. |
7. Utilities, building services & safety
- The RERA amenity schedule marks Water Supply, Sewerage, Storm Water Drains, Water Conservation/Rain Water Harvesting, Energy management, and Electrical Meter Room/Sub-Station/Receiving Station as “YES”; each listed progress field is 0%. It gives no source, capacity, treatment specifications, storage volumes or completion evidence.
- The building approval requires construction of a rainwater-harvesting structure/percolation pit, a transformer space and a garbage house. It also states requirements concerning fire safety, plumbing, electrical installations and lifts, but the supplied record does not establish the installed systems, capacities, lift count, emergency-stair arrangement, or completed safety clearances. These are approval conditions, not proof of delivery.
- The approval document includes an electric-vehicle charging-infrastructure condition and a condition that an Occupancy Certificate is to be granted only after the prescribed CTI requirements are in place. The supplied evidence does not confirm installation or commissioning of either system.
8. Location, access & connectivity
- The registered project location is near Erra Satyam Junction Road, Ward No. 1, on Station Road, Mahabubnagar, Mahabubnagar Urban, PIN 509001. The stated plot boundaries include a road on the north, a 40-00 feet road on the south, a 12-00 feet wide road on the west, and houses of others to the east. The supplied location record does not provide verified public-transport information or measured distances to nearby landmarks.
- The evidence does not establish a revenue-village name or survey number for the project parcel. The supplied cadastral coordinate entry is labelled as a parcel centroid, but no independently verified connectivity assessment is provided.
9. Developer & development status
- The project record identifies the registered promoter as RAJPUROHIT and the registration certificate names Mr./Ms. Rajpurohit Shravan. The project documents identify Shravan Rajpurohit as the developer and as the person signing the Form B declaration on behalf of the promoter. The promoter’s legal entity type, corporate registration identifiers, registered office and official contact details are not established in the supplied project record.
- Form B declares completion by 26th AUG, 2026. That is a promoter declaration; the supplied evidence does not provide independently verified construction progress or an OC for VKR RESIDENCY. The registration certificate states validity through 26/08/2026; registration validity and the declared completion deadline are separate dates, even though the dates shown here coincide.
10. Approvals, official records & documents
| Identifier / date | P01400007875, issued 16/03/2024; valid to 26/08/2026 |
|---|---|
| What the supplied document establishes | FORM C registration certificate for VKR RESIDENCY. |
| Identifier / date | 0054/BP/3063/2023, 26 August 2023 |
|---|---|
| What the supplied document establishes | Mahaboobnagar Municipality/Municipal Corporation approval for Building - A, a residential building with 1 stilt + 5 upper floors. |
| Identifier / date | 008444/BP/DTCP/3063/0071/2023 |
|---|---|
| What the supplied document establishes | File reference shown in the building-approval record. |
| Identifier / date | TS/049836/2023, dated 24 July 2023 |
|---|---|
| What the supplied document establishes | Application reference shown in the proposed building-plan document. |
| Identifier / date | File No. G1/STR-ENG/13/MBNR/2020 |
|---|---|
| What the supplied document establishes | Proposed residential apartment plan; the extracted plan itself does not show a completed approval number or approval date. |
| Identifier / date | Form B, dated 15th day of FEB, 2024 |
|---|---|
| What the supplied document establishes | Promoter-authorized signatory declaration including the stated completion date of 26 August 2026. |
| Identifier / date | No project-specific OC established |
|---|---|
| What the supplied document establishes | The extracted Form–1A record for VKR RESIDENCY contains only “NA.” The other supplied OC, document 652242, identifies a different owner, developer, location and RERA registration and is not an OC for this project. |
Frequently asked questions
Is VKR RESIDENCY registered with Telangana RERA?
Yes. VKR RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P01400007875; the registration status is New Project.
Who is the developer of VKR RESIDENCY?
The promoter named in the RERA registration is RAJPUROHIT.
Where is VKR RESIDENCY located?
VKR RESIDENCY is in NEAR ERRA SATYAM Jn ROAD,WARD NO 1, Mahabubnagar Urban, Mahabubnagar, Telangana (509001).
When will VKR RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 26/08/2026. This is the promoter's declaration, not a guarantee.
More projects in Mahabubnagar Urban