SMART CITY PHASE - III is a plotted development in Maheshwaram, Maheshwaram mandal, Ranga Reddy district. The registered promoter is SMART CITY INFRA DEVELOPERS. The project covers 58,980.29 sq.m and has plots numbered 01 to 142; no towers, blocks, floors, or plot-size range are stated. It offers residential plots and is registered under TG-RERA registration P02400004169, with proposed completion stated as 10th JANUARY 2025.

More from Smart City Infra Developers · 2 projects →

01What we found

Period endedTG-RERA registration ran to 10 Jan 2025 - check its extension on TG-RERA
19documents on file - each fact links to its page
0court cases on this project's land in the court records searched
10items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

10 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered project nameSMART CITY PHASE - III RERA record
Project typePlotted development; the HMDA plan describes a proposed residential open layout. RERA record
Phase / registered portionPhase III; registered land is identified in Survey Nos. 323/P, 324/P and 326/P. RERA record
TG-RERA registrationP02400004169
Registration validity25/02/2022 to 10/01/2025, as stated on the registration certificate; no extension is recorded in the supplied registration data.
Registered promoterSMART CITY INFRA DEVELOPERS RERA record
RERA statusThe supplied certificate records registration under section 5. Its stated validity ended on 10/01/2025; current registration status is not established by the supplied record.

Land and geographic identity

FieldRecord
Locality / revenue villageMaheshwaram (also written “Maheswaram” in project documents); revenue village: Maheshwaram. RERA record
MandalMaheshwaram RERA record
DistrictRanga Reddy RERA record
PIN501359 RERA record
Project survey numbers323/P, 324/P and 326/P RERA record Land records
Registered site extent58,980.29 sq.m RERA record
Net / total area58,980.29 sq.m total site area and 58,980.29 sq.m net site area in the HMDA-filed material.
BoundariesNorth: Smart City HMDA Layout; South: owners’ land in Sy. No. 319 and part of Sy. No. 323; East: owners’ land in Sy. No. 326; West: owners’ land, part of Sy. No. 323, and neighbouring land. Land records

Development identity

FieldRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Principal layout approvalLayout Permit No. 000010/LO/Plg/HMDA/2022, dated 10-01-2022; the RERA-filed drawing describes a proposed residential draft layout. Approvals record
Approved built-up areaNot disclosed in the supplied layout evidence; this is a plotted layout, not a building plan. Approvals record
Plot countThe HMDA-filed drawing states plots numbered 01 to 142.
Buildings / floorsNot applicable to the supplied plotted-layout approval; no building count or floor configuration is established.
ParkingNo sanctioned parking count, parking levels or plot-wise parking allocation is identified in the supplied evidence.

Offering and status

FieldRecord
Offered unit typeResidential plots. A RERA configuration count and plot-size range are not available in the supplied RERA data. RERA record
Booked / availableNot disclosed in the supplied evidence. RERA record
Declared completionThe promoter’s Form B undertaking stated 10th JANUARY 2025 as the completion period.
Construction / development stageA RERA filing records 70% completeness, but the supplied material does not identify a verification date or independently verified site progress. RERA record
Completion / occupancy certificateNo project-specific occupancy or completion certificate for the plotted layout is established in the supplied evidence. The file includes an architect’s completion certificate with the same registration number but identifying SMART CITY PHASE-II; its scope does not establish completion certification for Phase III.

2. The project story

SMART CITY PHASE - III is registered as a residential plotted development in Maheshwaram village, Maheshwaram mandal, Ranga Reddy district. The registered land comprises 58,980.29 sq.m in Survey Nos. 323/P, 324/P and 326/P. The HMDA-filed plan presents an open layout with plots numbered 01 to 142, rather than a multi-storey apartment or villa scheme. RERA record Land records

The registration records a proposed completion date of 10 January 2025 and a 70% completeness figure, but the supplied evidence does not describe the basis or as-of date for that progress figure. It should be read as a filed status, not independent confirmation of completed works. The supplied record does not establish a Phase III completion or occupancy certificate. RERA record

3. Master plan, architecture & building design

The HMDA-filed drawing describes a residential open layout on a 58,980.29 sq.m site. It allocates 34,382.60 sq.m to plotted area, 18,235.13 sq.m to layout roads, 4,884.97 sq.m to park/organised open space, and 1,477.62 sq.m to social infrastructure. It also identifies plots numbered 01 to 142. These are figures stated in the drawing; they are not software-measured plot areas.

The drawing identifies multiple road widths, including 12.00, 12.19, 7.62m, 9.14, 15.24 and 18.29, and widths stated as 30', 40' and 100'. The supplied material does not provide a verified plot-by-plot schedule or a complete readable plot-size range. No building footprint, floors, towers or building-level area figures are applicable or established by this layout evidence.

The layout plan lists utility and facility labels including S.T.P, O.H.T, utility area, park area, existing layout park area, cycling track and dustbin. The HMDA draft-layout material also lists internal water-supply lines, street lights, transformer, rainwater-harvesting pits, sewerage disposal, park development, avenue plantation and solid-waste facilities. These are plan or approval-document references; the supplied evidence does not establish their present installation or completion.

4. Homes, configurations & floor plans

The RERA-filed offering is a plotted layout. No RERA unit-type schedule with plot counts, booked or available inventory, plot dimensions, or saleable-area figures is supplied, so a configuration table cannot be completed without inventing figures. RERA record RERA unit table

The HMDA-filed drawing states 142 numbered plots and 34,382.60 sq.m of plotted area, but does not provide a verified plot-by-plot size schedule in the supplied evidence. The floor-plan input contains two layout sheets and no flat plans; no software-measured carpet areas are available. Floor plans

5. Parking & vehicle circulation

The HMDA drawing shows a road network and lists road widths, but the supplied evidence does not establish a sanctioned parking-space count, visitor or accessible parking, parking levels, EV charging, or plot-specific parking allocations. A layout road or drawn area should not be treated as an individual buyer’s parking entitlement.

The draft-layout conditions require roads to be opened for neighbouring-site accessibility. No detailed vehicle-entry, exit, ramp or pedestrian-separation plan is available in the supplied materials.

6. Amenities, recreation & open spaces

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Park / organised open space4,884.97 sq.mHMDA-filed drawing and draft-layout materialShown in the layout; current development or handover is not established.
Social infrastructure1,477.62 sq.mHMDA-filed drawing and draft-layout materialAllocated in the layout; current development or handover is not established.
Cycling trackNo size suppliedHMDA-filed drawing label and draft-layout facility listListed in plan material; completion is not independently verified.
Utility areaNo size supplied in the facility labelHMDA-filed drawingLabelled in the drawing; current status is not established.

The plan and approval material also refer to park development, avenue plantation and dustbins. No clubhouse, community building or other indoor recreation facility is established in the supplied evidence.

7. Utilities, building services & safety

The HMDA draft-layout material lists protected water supply, internal water-supply pipelines, an overhead tank and sumps; common septic tank/STP and independent sewerage disposal; storm-water drains and rainwater-harvesting pits; electrical supply lines, street lights and a transformer; and solid-waste and bio-compost facilities. These are listed as planned or required layout infrastructure, not verified evidence of installation, operating capacity or completion.

The supplied amenity-status data marks water supply, sewerage, storm-water drains, street lighting, water conservation/rainwater harvesting, and an electrical meter room/sub-station/receiving station as available at 100%. This is a filed status; the supporting evidence does not independently confirm on-site completion. The same data marks treatment and disposal of sewage and sullage water, solid-waste management and disposal, energy management, and fire-protection requirements at 0%. RERA amenities

No capacities are supplied for water storage, treatment, electrical backup, STP, or waste systems. Building lifts, fire escapes, building-level fire systems and accessibility features are not established for this plotted development by the supplied record. RERA amenities

8. Location, access & connectivity

The registered location is Maheshwaram village, Maheshwaram mandal, Ranga Reddy district, Telangana, PIN 501359. The supplied location record places the project geocode at 17.1350798, 78.4338212. RERA record Location record

The nearest sampled Outer Ring Road interchange is recorded as approximately 10.6 km away. The supplied evidence does not identify the interchange or provide verified road routes or public-transport distances. Location record

9. Developer & development status

The registered promoter is SMART CITY INFRA DEVELOPERS, recorded as a partnership. Its supplied GSTIN is 36ACYFS8736P1ZU. The registration certificate gives the promoter office as Village: PUNJAGUTTA, Mandal: KHAIRTABAD, District: Hyderabad, Pin: 500082. Corporate record

The project filing identifies Rallabandi Balachary as authorized signatory and Swarna Latha Rallabandi as a partner. The promoter’s Form B is dated 7 FEB 2022 and undertakes completion by 10th JANUARY 2025; it also declares the project land free from encumbrances. These are promoter declarations, not independent verification of title, works or present progress. Parties record

The registration record lists 70% completeness, without a supplied as-of date or independent site-verification evidence. The registration certificate’s stated validity and the promoter’s completion undertaking are separate records; the supplied material does not establish a Phase III occupancy or completion certificate. RERA record

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400004169; issued 25/02/2022; valid to 10/01/2025
What the supplied document establishesForm C records registration of SMART CITY PHASE - III under section 5 and gives the stated registration-validity period.
HMDA layout plan / permit
Identifier / date000010/LO/Plg/HMDA/2022; 10-01-2022
What the supplied document establishesRERA-filed drawing for a proposed residential draft layout in Survey Nos. 323/P, 324/P and 326/P, with layout area and land-use details.
HMDA draft-layout letter
Identifier / date000010/LO/Plg/HMDA/2022; dated 10 January, 2022
What the supplied document establishesDraft open-plot layout letter with infrastructure, road/open-space and mortgage-related conditions.
Gram Panchayat Maheshwaram letter
Identifier / dateLr No:GPM/02/LAVOUT/2022; 05-02-2022
What the supplied document establishesLetter concerning public-purpose land, park and roads and stating they are to be gifted to the Gram Panchayat before final layout release.
Promoter declaration
Identifier / dateForm B; dated 7 FEB 2022
What the supplied document establishesPromoter-filed declarations regarding land, project funds, approvals and proposed completion.
Architect’s completion certificate in file
Identifier / dateHMDA Final Layout Permit No. 000010/LO/Plg/HMDA/2022; printed date 01/10/2024
What the supplied document establishesThe certificate is identified as concerning SMART CITY PHASE-II; it does not establish Phase III completion or occupancy.
Approved-layout portal lookup
Identifier / dateHMDA DPMS HMDA
What the supplied document establishesThe supplied record says the public lookup was unavailable; this is not evidence of approval refusal.

The supplied evidence does not include a Phase III final-layout release, a project-specific completion/occupancy certificate, or an accessible HMDA DPMS verification record. The documents listed above are the available project-file evidence; the full conditions are recorded in the underlying approval documents. HMDA

Other registrations of Smart City

Frequently asked questions

Is SMART CITY PHASE - III registered with Telangana RERA?

Yes. SMART CITY PHASE - III is registered with the Telangana Real Estate Regulatory Authority as P02400004169; the registration status is New Project.

Who is the developer of SMART CITY PHASE - III?

The promoter named in the RERA registration is SMART CITY INFRA DEVELOPERS.

Where is SMART CITY PHASE - III located?

SMART CITY PHASE - III is in Maheshwaram, Rangareddy, Telangana (501359).

When will SMART CITY PHASE - III be completed?

The promoter's proposed date of completion filed with RERA is 10/01/2025. This is the promoter's declaration, not a guarantee.