Highland

BOTCHA SANDEEP AND OTHERS · Rangareddy · RERA P02400010142

Highland is a new plotted/open-layout residential development in Maheshwaram, Maheshwaram Mandal, Ranga Reddy District. It is being developed by BOTCHA SANDEEP AND OTHERS on a total site area of 35,754.95 sq.m. The RERA-filed layout records 20,123.54 sq.m of plotted area; the supplied record does not state a plot count, plot-size configurations, or buildings and floors. Highland is registered with TG-RERA under P02400010142, with a proposed completion date of 04/11/2028.

01What we found

RegisteredTG-RERA - valid till 4 Jul 2028
32documents on file - each fact links to its page
0court cases on this project's land in the court records searched
8items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

ItemProject record
Registered project nameHighland RERA record
Project typeNew plotted/open-layout residential development RERA record
Phase / registered portionNo phase designation is identified in the supplied record; the registration is for the listed layout and land RERA record
TG-RERA registrationP02400010142 RERA record
Registration validity04/07/2025 to 04/07/2028 (three years, unless extended by the Authority) RERA record
Registered promoterBOTCHA SANDEEP AND OTHERS RERA record
RERA statusRegistered; the supplied record does not identify a later extension, lapse or revocation RERA record Approvals record

Land and geographic identity

ItemProject record
Locality / revenue villageMaheshwaram / Maheshwaram Revenue Village RERA record
MandalMaheshwaram RERA record
DistrictRanga Reddy RERA record
PIN501359 RERA record
Project survey numbers and subdivisions470/1/1/3, 471/1/1/3, 472/2, 472/1, 473/1/2, 479, 473/1/1, 480/-/2, 473, 471/1/1/2, 470/1/1/2, 471/2, 470/2, 470/1/2 and 471/1/2. The registration certificate and drawing/OCR also render the 480 subdivision as “480-/2” or “480/?/2”; verify the exact survey notation against the registered land schedule. RERA record
Total site area35,754.95 sq.m Land records
Road-affected area668.87 sq.m Land records
Net site area32,224.93 sq.m in the HMDA draft layout record
BoundariesEast: Check Dam; West: Others Land; North: Others Land; South: Road RERA filing

Development identity

ItemProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Principal layout approvalHMDA Draft Layout Letter / Layout Permit 000047/LO/Plg/HMDA/2025, dated 04 July 2025 Approvals record
Filed plan type“Plan Showing the Proposed Residential Draft Layout”; open-layout/plotted residential use
Approved built-up area20,123.54 sq.m is recorded as “Approved Built up Area” in the RERA filing; it is identified in the layout land-use statement as plotted area, not as apartment-building floor area. RERA filing Layout record
Buildings / floorsNot disclosed as buildings or floor configurations; this is a plotted layout, not a multi-storey building scheme. RERA record
ParkingNo project-wide parking-space count or parking-level plan is established in the supplied RERA layout records. RERA amenities
Layout land useRERA-filed drawing states: Plotted Area 20,123.54 sq.m; Road Area 8,453.15 sq.m; “Organized open space/park Area/Utility Area” 2,829.18 sq.m; Social Infrastructure Area 819.18 sq.m; Amenity Area Total 3,530.02 sq.m; Buffer Zone Area 2,861.15 sq.m.

Offering and status

ItemProject record
OfferingResidential plots; plot count, plot-size schedule and plot-by-plot availability are not established by the supplied RERA data. RERA record Layout record
RERA booked / available countsNot disclosed in the supplied evidence. RERA record RERA amenities
Construction / development stageHMDA draft layout permission is recorded, followed by a Gram Panchayath Maheshwaram releasing order dated 25/08/2025. No independently verified on-site completion percentage is supplied.
Completion datesForm B promoter declaration: 03-Jul-2028; RERA header proposed completion: 04/11/2028. These are separately recorded dates; this overview does not resolve the difference. RERA record
Registration validity versus completionRegistration validity runs to 04/07/2028 unless extended; this is distinct from the two completion dates recorded above. RERA record
Occupancy / completion certificateNo occupancy or completion certificate is supplied. The record concerns a plotted layout; the supplied documents do not establish a certificate for the layout or any building. Document index

The project story

Highland is registered with TG-RERA as a new residential plotted development at Maheshwaram, Maheshwaram Mandal, Ranga Reddy District. Its registered land identity comprises the survey numbers and subdivisions listed above, and the RERA record describes a total site area of 35,754.95 sq.m, including a road-affected area of 668.87 sq.m. The HMDA drawing identifies a net site area of 32,224.93 sq.m. RERA record Land records

The approval record is for an open-plot layout, not apartments or villas. It shows residential plots, internal roads and land designated for open space/park, social infrastructure, utilities and amenities. The promoter’s Form B affidavit declares completion by 03-Jul-2028; the RERA header separately records a proposed completion date of 04/11/2028. No site-verified progress measurement is provided, so the approval and declarations should not be read as proof that layout works are complete. RERA record

Master plan, architecture & building design

The project is organized as a plotted layout. The RERA-filed layout drawing identifies 32,224.93 sq.m as net area and 20,123.54 sq.m as plotted area. It also records 8,453.15 sq.m of layout roads, 2,829.18 sq.m under the combined “Organized open space/park Area/Utility Area” line, and 819.18 sq.m of social infrastructure area. The same drawing separately lists 3,530.02 sq.m as total amenity area and 2,861.15 sq.m as buffer-zone area.

The drawing labels the land use as residential and the development as an open layout. It shows road-width entries of 12.00 and 7.62m; the HMDA draft-layout extraction separately records an abutting road width of 12.00 and refers to roads “18 mts and above.” No building count, floor configuration, building footprint, apartment arrangement or tower design is established for this plotted project.

Homes, configurations & floor plans

The RERA record describes a plotted residential offering. The supplied evidence does not provide a complete RERA unit/plot inventory, plot-size range, booked-versus-available counts, or plot-specific saleable areas. The available drawing is a layout sheet, not a unit floor plan; no measured carpet-area or room-configuration data applies to the plots. RERA record Layout record Floor plans

A third-party vendor record contains apartment-style configurations and amenity claims, but those are not used here to describe the TG-RERA-registered plotted offering. Promoter website

Parking & vehicle circulation

The layout drawing identifies roads and road widths, but the supplied RERA evidence does not establish a total parking count, dedicated visitor or accessible parking, parking allocation to individual plots, or parking facilities by type. No car-park level, ramp, EV-charging provision or exclusive parking right is documented in the supplied project records. RERA amenities

Amenities, recreation & open spaces

The RERA-filed layout drawing identifies the following facilities and land-use provisions. The “available” entries in the RERA amenities register are recorded as project provisions; each listed progress value is 0%. The evidence supplied does not independently verify completed facilities. RERA amenities

Park / green open space
Description / sizePark area 2,829.18 sq.m in the HMDA layout land-use statement; the drawing also groups organized open space/park/utility area as 2,829.18 sq.m.
Evidence sourceHMDA draft layout and RERA amenities register RERA amenities
Declared progress / verified statusPark/green-strip provision marked available; 0% progress in the RERA amenities register; not independently verified complete.
Social infrastructure
Description / size819.18 sq.m in the HMDA land-use statement.
Evidence sourceHMDA draft layout
Declared progress / verified statusLand provision shown; community-building progress is 0% in the RERA amenities register.
Utility area
Description / sizeShown as a layout land-use provision; no standalone area is reliably established by the combined open-space/park/utility line.
Evidence sourceHMDA draft layout
Declared progress / verified statusProvision shown; completion not independently verified.
Amenity area
Description / sizeDrawing states 3,530.02 sq.m total amenity area.
Evidence sourceRERA-filed layout drawing
Declared progress / verified statusThe HMDA draft layout extraction separately records amenities area as 0; delivery/status is not established here.
Internal roads and footpaths
Description / sizeLayout roads 8,453.15 sq.m in the HMDA land-use statement.
Evidence sourceHMDA draft layout and RERA amenities register RERA amenities
Declared progress / verified statusMarked available; 0% progress in the RERA amenities register; not independently verified complete.
Water supply
Description / sizeLayout drawing labels internal water-supply pipelines and an overhead water tank; the amenities register marks water supply available.
Evidence sourceRERA-filed layout drawing and amenities register RERA amenities
Declared progress / verified statusMarked available; 0% progress; not independently verified complete.
Sewerage / septic system
Description / sizeLayout drawing specifies a common septic tank; HMDA conditions refer to underground drainage and a common septic tank / STP.
Evidence sourceRERA-filed layout drawing and HMDA draft-layout conditions
Declared progress / verified statusProvision specified; no completion verification supplied.
Garbage pit / solid-waste provision
Description / size“Garbage Pit” appears in the layout drawing; the amenities register includes solid waste management and disposal. RERA amenities
Evidence sourceRERA-filed layout drawing and amenities register RERA amenities
Declared progress / verified statusNo completed-status evidence; amenities-register progress 0%.
Rainwater harvesting
Description / sizeRainwater-harvesting pits are specified in the HMDA draft-layout conditions; the amenities register lists water conservation/rainwater harvesting. RERA amenities
Evidence sourceHMDA draft layout and RERA amenities register RERA amenities
Declared progress / verified statusNo completed-status evidence; amenities-register progress 0%.
Electrical distribution
Description / sizeDistribution transformer is shown in the layout drawing; the RERA amenities register marks an electrical meter room/sub-station/receiving station available. RERA amenities
Evidence sourceRERA-filed layout drawing and amenities register RERA amenities
Declared progress / verified statusMarked available in the register; 0% progress; not independently verified complete.
Street lighting / avenue planting
Description / sizeHMDA conditions specify street lights and avenue plantation.
Evidence sourceHMDA draft-layout conditions
Declared progress / verified statusRequired development works; completion not independently verified.

Utilities, building services & safety

The layout drawing and HMDA draft-layout conditions specify internal water-supply pipelines, an overhead water tank, an assured water-supply source, underground drainage lines, a common septic tank / STP, storm-water drains, rainwater-harvesting pits, electrical supply lines, street lights and a transformer. These are recorded as layout provisions or required development works; the supplied evidence does not establish their completed status, capacities, or operating performance.

Fire protection and fire-safety requirements appear in the RERA amenities register, but progress is recorded as 0% and no project-specific fire clearance or completed fire-safety installation is supplied. The record does not establish building lifts, accessibility features, CCTV, security arrangements, backup power, or other building services for the plotted layout. RERA amenities Document index

Location, access & connectivity

The registered location is Maheshwaram Revenue Village, Maheshwaram Mandal, Ranga Reddy District, Telangana, PIN 501359. The supplied project boundaries identify a road to the south, a check dam to the east, and other land to the north and west. The HMDA drawing identifies a 12.00 abutting-road-width entry and internal road-width entries of 12.00 and 7.62m. RERA record RERA filing

The location record provides one measured connectivity reference: the nearest sampled Outer Ring Road interchange is approximately 10.8 km away. The supplied RERA project record does not provide travel times or a broader public-transport or landmark-distance schedule. Location record

Developer & development status

The registered promoter is BOTCHA SANDEEP AND OTHERS, with organization type recorded as “Others”; the legal entity type is not further established in the supplied records. Botcha Sandeep is identified as an authorized signatory in the promoter’s Form B affidavit, dated 25-August-2025. RERA record Corporate record

The promoter declares that the project will be completed by 03-Jul-2028 and that project funds will be handled under the separate-account arrangements described in the affidavit. The RERA header records 04/11/2028 as the proposed completion date. No construction-progress certificate, site inspection result, or independently verified completion status is supplied. The RERA certificate’s registration validity is separately stated as ending 04/07/2028, unless extended. RERA record

Approvals, official records & documents

TG-RERA Form C registration certificate
Identifier / dateP02400010142; validity 04/07/2025–04/07/2028
What it establishesRegistration of Highland under the named promoter, with project location and land identity.
HMDA draft layout letter / layout plan
Identifier / datePermit 000047/LO/Plg/HMDA/2025, approved 04 July 2025; application 056744/SMD/LT/U6/HMDA/13092022
What it establishesDraft open-layout permission and stated land-use, mortgage and layout-development conditions. The drawing is dated 04-07-2025.
Gram Panchayath Maheshwaram releasing order
Identifier / dateGPM/LAYOUT/2025, dated 25/08/2025; proceedings number recorded as 000047/LO/PIg/HMDA/2025
What it establishesLocal-body releasing order for the stated layout area, directing compliance with HMDA’s draft proceedings and conditions.
Promoter Form B affidavit
Identifier / dateDated 25-August-2025
What it establishesPromoter declaration on title, encumbrances, funds, approvals and a completion undertaking of 03-Jul-2028.
Layout plan / drawing
Identifier / dateOne sheet, scale 1:600, sheet 01/01
What it establishesRERA-filed layout drawing, land-use schedule, layout features and recorded plot mortgages.
HMDA mortgage deeds
Identifier / dateDocuments 10090/2025 and 10089/2025, dated 09/06/2025
What it establishesHMDA security over specified plots for layout-development obligations.
Public-purpose gift deed recorded in HMDA draft letter
Identifier / dateDocument 10088/2025, dated 09.06.2025
What it establishesGift-deed reference for roads, park, social infrastructure, utility and road-widening areas to the local body.
Gram Panchayath gift-deed reference
Identifier / dateDocument 10321 / 2025
What it establishesThe releasing-order record cites a gift deed for land areas in favour of Gram Panchayath Maheshwaram.
Commencement / occupancy / completion certificates
Identifier / dateNot supplied as a distinct project certificate in the evidence reviewed Document index
What it establishesNo building commencement certificate, occupancy certificate or completion certificate is established by the supplied record.

The HMDA document is expressly described as a draft layout and records development conditions, including completing specified layout works within three years. The Gram Panchayath order is recorded as a releasing order subject to HMDA’s terms. The supplied documents do not establish that the required layout works have been completed or that a final occupancy/completion certificate has been issued.

Frequently asked questions

Is Highland registered with Telangana RERA?

Yes. Highland is registered with the Telangana Real Estate Regulatory Authority as P02400010142; the registration status is New Project.

Who is the developer of Highland?

The promoter named in the RERA registration is BOTCHA SANDEEP AND OTHERS.

Where is Highland located?

Highland is in MAHESWARAM, Maheshwaram, Rangareddy, Telangana (501359).

When will Highland be completed?

The promoter's proposed date of completion filed with RERA is 04/11/2028. This is the promoter's declaration, not a guarantee.