Gigaciti Phase-6

VERTEX KLR DEVELOPERS LLP · Rangareddy · RERA P02400005103

GIGACITI PHASE-6 is a plotted development in Thukkuguda Municipality, Mankal, Maheshwaram, Ranga Reddy. It is being developed by VERTEX KLR DEVELOPERS LLP on a registered site area of 55200.82 sq.m., with a final layout approval for 84 residential plots; no building or floor configuration is stated. The project is registered under TG-RERA number P02400005103, issued 29/09/2022, and the promoter’s Form B declaration undertakes completion by 24 June 2025.

More from Vertex Klr Developers LLP · 9 projects →

01What we found

Period endedTG-RERA registration ran to 24 Jun 2025 - check its extension on TG-RERA
26documents on file - each fact links to its page
9court cases on this project's land (survey 64, 71, 72, 73, Mankal)
11items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

11 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Mankal, Maheshwaram, Ranga Reddy · geocoded — approximate.

1. Project at a glance

Project identity

ItemProject record
Registered project nameGIGACITI PHASE-6. RERA record
Project typePlotted development / open-plot residential layout. RERA record RERA filing
Phase / registered portionPhase 6; the registered land is stated as 55200.82 sq.m. RERA record
TG-RERA registrationP02400005103, issued 29/09/2022; certificate states validity from 29/09/2022 to 24/06/2025, subject to extension. It records no extension. RERA record
RERA status in supplied recordRegistered certificate supplied; it does not establish a subsequent extension or current registration validity.
Registered promoterVERTEX KLR DEVELOPERS LLP. RERA record Corporate record

Land and geographic identity

ItemProject record
LocalityThukkuguda Municipality. RERA filing
Revenue villageMankal; also written “Mankhal” in the filed approval and title records. RERA record
Mandal / district / PINMaheshwaram / Ranga Reddy / 501359. RERA record
Project survey numbers as filed64/P, 71/P, 72/P and 73/P. RERA record
Registered site extent55200.82 sq.m.
Net site area55200.82 sq.m.
Boundaries in the RERA filingEast: neighbours’ land; West: 100FT ROAD; North: 100FT ROAD; South: neighbours’ land. RERA filing
Additional subdivision detailThe registration and layout documents list the four survey references above but do not specify further subdivisions.

Development identity

ItemProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA); final layout letter is issued through TG-bPASS and delegated to Thukkuguda Municipality/Municipal Corporation.
Principal final layout approval006450/FLT/HMDA/1505/SMD/2024, dated 16 December 2024.
Earlier layout permissionDraft layout letter 000114/LO/Plg/HMDA/2022, dated 24 June 2022.
Approved plotsFinal layout record states 84 plots.
Approved built-up area0, as stated in the final layout area statement; this is a plotted layout, not an apartment building approval.
Buildings / floors / parking levelsNot applicable to the layout approval information supplied; no building count, floor configuration or parking-level schedule is provided.
Site area allocation in final layout recordPlotted area 39068.46 sq.m.; layout road area 9942.05 sq.m.; park 4636.71 sq.m.; social infrastructure 1444.40 sq.m.; utilities area 108.81 sq.m.; amenities area 0.

Offering and status

ItemProject record
Unit typeResidential plots; no apartment or villa configuration is stated in the supplied RERA documents.
Plot countFinal layout approval records 84 plots.
Plot sizesThe supplied software-extracted layout data identifies at least 80 plots with sizes, from 227.6 to 1168.61 sq.m.; the plot list is incomplete and should be checked against the drawing. Layout record
Booked / available countsNot supplied.
Construction stageNo independently verified site progress is supplied. The RERA filing includes infrastructure progress fields, but the available amenity data does not establish completion of the layout works. RERA amenities
Promoter-declared completion dateThe Form B declaration undertakes completion by 24 June 2025.
Registration validityCertificate validity ends 24/06/2025 unless extended; no extension is recorded on the certificate supplied. This is separate from the completion undertaking.
Occupancy / completion certificateNo occupancy certificate is identified in the supplied records. The final layout letter is a layout approval, not an occupancy certificate for buildings.

2. The project story

GIGACITI PHASE-6 is a residential plotted layout in Mankal revenue village, Maheshwaram Mandal, Ranga Reddy District, within Thukkuguda Municipality. Its filed land identity covers Sy. Nos. 64/P, 71/P, 72/P and 73/P, with a recorded site and net area of 55200.82 sq.m. RERA record

The final layout record approves 84 residential plots. It also provides for internal roads, parks/open space, social infrastructure and utility land; the final letter states that roads, open spaces, social infrastructure and utilities were taken over by the local authority by registered gift deed, and that HMDA executed a relinquishment deed concerning the mortgaged plots. The supplied records do not establish plot-by-plot sale availability or independently verified on-site completion. The completion date in the promoter’s Form B declaration and the registration-validity period are recorded separately above.

3. Master plan, architecture & building design

This is a plotted layout, not a multi-storey building scheme in the supplied approval record. The final layout letter records 55200.82 sq.m. total and net site area and 0 total built-up area. It records 84 plots, with 39068.46 sq.m. plotted area, 9942.05 sq.m. layout roads, 4636.71 sq.m. park, 1444.40 sq.m. social infrastructure and 108.81 sq.m. utilities area; amenities area is recorded as 0.

The draft layout letter separately lists 1444.4 sq.m. open space and 4745.53 sq.m. organized open-space/park area, and requires roads, open spaces and social infrastructure to be handed over by registered gift deed before final layout release. The software-extracted drawing data describes at least 80 plots with sizes, but the plot list is incomplete and should be verified against the approved drawing. Layout record

The final approval states that plots are for residential dwelling-house use and that roads are to remain open for public access. It also states a minimum 3 m (10’0”) safety distance, vertically and horizontally, from high-tension electricity lines when residential building permissions are considered. Building-specific plans, elevations, floor configurations and building permissions are not included in the supplied evidence.

4. Homes, configurations & floor plans

The RERA approval is for plots rather than apartments. The final layout letter records 84 plots; the extracted drawing data has sizes for 80 plots and explicitly notes that the plot list is incomplete. These are software-extracted drawing details, not a complete RERA inventory disclosure. Layout record

Plot informationSupplied record
Approved plot count84.
Size range among plots with extracted sizes227.6–1168.61 sq.m. (software-measured; drawing-derived). Layout record
Size bands among plots with extracted sizes250–300 sq.yd.: 1; 300–400 sq.yd.: 41; 400–500 sq.yd.: 18; 500–1000 sq.yd.: 11; 1000+ sq.yd.: 9. Layout record
Booked / available plotsNot disclosed in the supplied data.
Plot-specific saleable / carpet areaNot supplied. Apartment carpet-area and loading concepts are not applicable to this plotted-layout record.
Floor plansThree drawing records are noted: two have no flats and one scan is pending; no apartment configurations or measured carpet areas are available. Floor plans

5. Parking & vehicle circulation

The supplied records do not establish a count or allocation of resident, visitor or accessible parking spaces, nor do they specify parking arrangements for individual plots. A drawing-based bay or area, if any, would not by itself establish exclusive ownership or allotment. The draft layout approval requires roads to be opened for accessibility to neighbouring sites and prohibits a compound wall or fencing around the site.

6. Amenities, recreation & open spaces

The layout approval and RERA amenity data identify proposed or listed infrastructure and facilities. The percentages below are filing-record progress figures, not independent verification of completion. The final layout letter states that roads, open spaces, social infrastructure and utilities were taken over by the local authority through registered gift deeds.

Internal roads and footpaths
Description / sizeRoad area 9942.05 sq.m.; draft approval refers to a 120 ft wide road.
Evidence sourceFinal and draft layout approvals; RERA amenity record. RERA amenities
Declared progress / verified statusRERA amenity record lists the facility; no progress percentage is supplied. Final letter says roads were taken over by the local authority. RERA amenities
Park / organized open space
Description / sizeFinal record: park 4636.71 sq.m.; draft record: organized open space 4745.53 sq.m.
Evidence sourceFinal and draft layout approvals.
Declared progress / verified statusFinal letter says open spaces were taken over by the local authority; independent condition/site verification is not supplied.
Social infrastructure
Description / size1444.40 sq.m.
Evidence sourceFinal and draft layout approvals.
Declared progress / verified statusFinal letter says social infrastructure was taken over by the local authority.
Community buildings
Description / sizeNo size or quantity stated.
Evidence sourceRERA amenity record. RERA amenities
Declared progress / verified statusListed “YES”; no progress percentage or independent completion evidence supplied. RERA amenities
Green strip / tot lot / park
Description / sizeNo separate size stated.
Evidence sourceRERA amenity record. RERA amenities
Declared progress / verified statusListed “YES”; no progress percentage supplied. RERA amenities
Street lighting
Description / sizeNo quantity stated.
Evidence sourceRERA amenity record and final layout letter. RERA amenities
Declared progress / verified statusListed “YES”; final letter includes street lighting among the civic amenities to be maintained. Completion is not independently verified. RERA amenities
Solid-waste management and disposal
Description / sizeNo capacity stated.
Evidence sourceRERA amenity record. RERA amenities
Declared progress / verified statusListed “YES”; no progress percentage supplied. RERA amenities
Water conservation / rainwater harvesting
Description / sizeNo quantity or capacity stated.
Evidence sourceRERA amenity record and final layout letter. RERA amenities
Declared progress / verified statusListed “YES”; no progress percentage supplied. RERA amenities
Treatment and disposal of sewage and sullage water
Description / sizeNo capacity stated.
Evidence sourceRERA amenity record. RERA amenities
Declared progress / verified status50% recorded; not independently verified. RERA amenities

7. Utilities, building services & safety

The draft layout letter lists storm-water drains, underground drainage lines, a common septic tank/STP, internal water-supply pipelines, an overhead tank, electrical supply lines, street lights, a transformer, avenue plantation, park development, rainwater-harvesting pits, solid-waste disposal/dumping space, a bio-compost unit and cycling tracks. These are approval-record project provisions; the supplied evidence does not establish their capacities or independent completion.

The final layout letter lists water supply, sewerage and drainage disposal systems, street lighting and rainwater-harvesting structures among civic amenities and states that roads, open spaces, social infrastructure and utilities were handed over by registered gift deed. It also requires the layout’s civic amenities and greenery to be properly maintained. The RERA amenity record reports sewerage at 90%, storm-water drains at 90%, and sewage/sullage treatment and disposal at 50%; these are declared progress figures, not site-verified completion. RERA amenities

No specific water source, storage capacity, treatment-plant capacity, electrical backup, EV charging, security system, accessible-circulation design or building fire-system details are supplied. The RERA amenity record lists fire protection and fire safety requirements but gives no progress percentage or technical details. RERA amenities

8. Location, access & connectivity

The registered location is Mankal revenue village, Maheshwaram Mandal, Ranga Reddy District, PIN 501359, at Thukkuguda Municipality. The project boundary record identifies 100FT ROAD on the west and north, and neighbouring land on the east and south. RERA record RERA filing

The supplied location data lists the Outer Ring Road nearest sampled interchange at 10.6 km, TGSRTC Bus Station, Maheshwaram at 0.2 km, and Community Health Centre Maheshwaram at 0.2 km. Location record No travel times are supplied as verified measurements.

9. Developer & development status

The registered legal promoter is VERTEX KLR DEVELOPERS LLP, an LLP. Its supplied corporate identifier is GSTIN 36AARFV1740M1ZL. Corporate record RERA record The RERA certificate gives the promoter office as Village: Madhapur, Mandal: Serilingampally, District: Ranga Reddy, PIN: 500081.

The Form B affidavit is attributed to Mr. K. ANUROOP, representing Vertex KLR Developers LLP. It declares the project land free from encumbrances, refers to title authentication and an owner-promoter development agreement, and undertakes completion by 24 June 2025. These are promoter declarations.

The supplied records do not provide an independently verified construction-progress assessment, a current plot booking/availability schedule, or evidence of an extension to the registration certificate. The registration certificate’s validity dates and the promoter’s completion undertaking are distinct records.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400005103; issued 29/09/2022; validity through 24/06/2025 unless extended
What it recordsForm C registration for GIGACITI PHASE-6; no extension is recorded on the supplied certificate.
HMDA draft layout letter
Identifier / date000114/LO/Plg/HMDA/2022; 24 June 2022
What it recordsTechnical approval for a draft open-plot layout over Sy. Nos. 64/P, 71/P, 72/P and 73/P; includes infrastructure and land-handover conditions.
TG-bPASS final layout letter
Identifier / date006450/FLT/HMDA/1505/SMD/2024; 16 December 2024
What it recordsFinal residential layout permission, recording 84 plots and the area statement.
Form B promoter declaration
Identifier / dateSupplied as document 250855
What it recordsPromoter declaration concerning title basis, encumbrances, RERA account obligations and completion undertaking.
HMDA-related gift deeds and relinquishment deed
Identifier / dateGift Deeds 8311/2022 and 8314/2022, dated 16 April 2022; Relinquishment Deed 20141/2024, dated 07 December 2024
What it recordsFinal layout letter states roads, open spaces, social infrastructure and utilities were handed over by registered gift deeds, and HMDA executed relinquishment concerning mortgaged plots.
Layout drawing
Identifier / dateDocument 255313
What it recordsListed as the filed layout plan; the supplied extraction states that plot-size data is incomplete and software-derived. Layout record
Title documents / title opinion
Identifier / dateTitle report 246313; advocate certificate 246314; linked deed records include documents 259703–259720 and 259709–259719
What it recordsTitle-related materials are available in the project file; this overview does not assess the title chain.
Completion / occupancy certificate
Identifier / dateNot identified in the supplied records
What it recordsThe final layout permission is not an occupancy certificate for buildings.

Other registrations of Gigaciti

Frequently asked questions

Is GIGACITI PHASE-6 registered with Telangana RERA?

Yes. GIGACITI PHASE-6 is registered with the Telangana Real Estate Regulatory Authority as P02400005103; the registration status is New Project.

Who is the developer of GIGACITI PHASE-6?

The promoter named in the RERA registration is VERTEX KLR DEVELOPERS LLP.

Where is GIGACITI PHASE-6 located?

GIGACITI PHASE-6 is in THUKKUGUDA MUNCIPALITY, Mankal, Maheshwaram, Rangareddy, Telangana (501359).

When will GIGACITI PHASE-6 be completed?

The promoter's proposed date of completion filed with RERA is 24/06/2025. This is the promoter's declaration, not a guarantee.