Sign in

Sai Swara By Suvela Projects

SUVELA PROJECTS · Rangareddy · RERA P02400011097

SAI SWARA BY SUVELA PROJECTS is a residential apartment project at Plot No. 30, Gopanpally, Serilingampally mandal, Ranga Reddy district, developed by the registered promoter SUVELA PROJECTS. The registered site area is 418.06 sq. m, with one residential building, Building A (B L NAGESWARI), comprising 1 Stilt + 5 upper floors and 10 homes. The homes are 3BHK, with a RERA-filed saleable area of 135.27 sq. m per unit. The project is registered under TG-RERA **P02400011097**, and the declared completion date is 24.08.2027.

More from Suvela Projects · 3 projects →

01What we found

RegisteredTG-RERA - valid till 24 Aug 2027
19documents on file - each fact links to its page
15court cases on this project's land (survey 231, 316, Gopanpally)
13items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

13 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Photo from housing.com

1. Project at a glance

Project identity

FieldProject record
Registered nameSAI SWARA BY SUVELA PROJECTS RERA record
Project typeResidential apartment project RERA record
Phase / registered portionOne residential building, Building A (B L NAGESWARI), on Plot No. 30; no separate phase name is stated
TG-RERA registrationP02400011097
Registration validity24/08/2024 to 24/08/2027, unless extended by the Authority
Registered promoterSUVELA PROJECTS; the RERA filing identifies it as a partnership RERA filing Corporate record
RERA statusThe supplied record identifies this as a “New Project”; the registration certificate is available. The registration end date is not the project-completion deadline RERA record

Land and geographic identity

FieldProject record
Locality / sitePlot No. 30, Gopanpally RERA record
Revenue villageGopanpally (also printed as GOPANPALLY / GOPANPALLE in filed approval records) RERA record
MandalSerilingampally RERA record
DistrictRanga Reddy RERA record
PIN500019 RERA record
Project survey numbersSurvey No. 231 part and Survey No. 316 part RERA record
Registered site extent418.06 sq. m; the registration certificate identifies the site as Plot No. 30
Net / total areaApproved plot area 418.06 sq. m; net plot area 418.06 sq. m. Filed land details also report total and net area of 418.06 sq. m RERA filing
BoundariesFiled boundaries are recorded as “OTHERS LAND” on the east, west, north and south; specific adjoining parcel identities are not supplied RERA filing

Development identity

FieldProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC)
Principal building permitPermit No. 2541/GHMC/SLP/2024-BP, dated 24 August 2024; file No. 003971/GHMC/1929/SLP2/2024-BP
Approved built-up areaThe approval extraction reports upper-floor residential area of 1,100.95 sq. m, stilt area of 194.93 sq. m and total parking area of 156 (unit not stated in that extracted field). A separate drawing extraction reports proposed built-up area excluding parking of 1,100.95 sq. m, including parking of 1,316.95 sq. m, and “TOTAL BUA” of 1,328.28
Building count and configurationOne residential building, Building A (B L NAGESWARI), sanctioned as 1 Stilt + 5 upper floors
HeightBuilding height is recorded as 14.95 m in the permit extraction; another drawing-extracted field records total height as 20.44 m
ParkingThe plan extraction records 216.00 sq. m parking area. The permit extraction separately records “Total Parking Area 156” without an associated unit in that field. The filed material does not establish a verified count of parking spaces
Units10 units in the GHMC plan extraction and 10 units in the RERA filing RERA unit table

Offering and status

FieldProject record
RERA-filed configuration3BHK; 10 units RERA unit table RERA unit details
RERA-filed saleable area135.27 sq. m per unit RERA unit table RERA unit details
Booking / availabilityPortal-derived count: 0 booked and 10 available; the portal record has no as-of date, so these figures are indicative RERA unit table
Construction stageNo independently verified site-progress record or current construction stage is supplied. The RERA project status is “New Project” RERA record RERA amenities
Completion dateThe Form-B declaration states completion by 24.08.2027; the building permit states construction to be completed before 24 August, 2027
Occupancy certificate (OC)No OC is supplied. The permit makes an OC compulsory before occupation and states that an occupancy fire NOC is to be obtained before issue of the OC

2. The project story

Sai Swara by Suvela Projects is registered as a residential apartment project on Plot No. 30 at Gopanpally, in Survey No. 231 part and Survey No. 316 part. The filed site extent is 418.06 sq. m. The GHMC permit describes a single building, Building A (B L Nageswari), with a stilt and five upper floors; the RERA unit record lists ten 3BHK apartments. RERA record RERA unit table

The supplied record establishes the sanctioned building form and the promoter’s declared completion date, but does not establish how much construction has been completed on site. The amenity progress entries show 0% for the listed facilities, but do not independently verify physical site progress. No occupancy certificate is included; under the permit conditions, an OC is required before occupation. RERA amenities

3. Master plan, architecture & building design

The GHMC-filed plan is for one residential building on a 418.06 sq. m plot, with 1,100.95 sq. m recorded as proposed built-up area excluding parking and 216.00 sq. m recorded as parking area. The approval extraction also lists 1,316.95 sq. m as proposed built-up area including parking and “TOTAL BUA” as 1,328.28; those extracted fields are preserved as recorded and are not treated as interchangeable area measures.

The building is sanctioned as 1 Stilt + 5 upper floors. The permit records a 14.95 m building height and 194.93 sq. m stilt area; the drawing extraction separately records a total height of 20.44 m. No supplied material details flats per floor, lift or stair counts, floor-by-floor layouts, building footprint, internal circulation, or a quantified open-space allocation.

The approval conditions call for a fenced tot-lot maintained as greenery, peripheral tree planting and a strip of greenery around the site. These are approval conditions, not evidence that the works have been completed. The approval also identifies rainwater-harvesting pits, a transformer space and an on-site garbage house; details are summarised under utilities and services.

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK10010135.27 sq. mSoftware-measured median 86.9 sq. m; range 79.8–87.0 sq. m36%

The RERA filing identifies ten 3BHK units and records a saleable area of 135.27 sq. m per unit. The booking figures are portal-derived and have no stated as-of date. RERA unit details RERA unit table

The carpet-area figures are software measurements from the approved floor-plan drawing, not RERA-filed carpet-area disclosures; six flat designs were measured and the supplied measurement record says they need review. The measured sample floor plan identifies bedrooms, living/dining, kitchen, toilets and utility areas. For example, the fifth-floor FF-501 drawing labels a living/dining area of 3.69 m × 5.97 m, a kitchen of 2.85 m × 2.3 m, bedrooms of 4.86 m × 3.43 m and 4.05 m × 3.0 m, and two utility areas. Floor plans RERA unit details

Carpet area describes usable interior floor area under the statutory definition; the drawing-based measurement excludes the labelled utility areas. Saleable area is the RERA-filed figure and is not the same measure as drawing-measured carpet area. The supplied record does not provide a RERA-filed balcony-area breakdown or a unit-specific common-area allocation. Floor plans RERA unit details § Act s.2

5. Parking & vehicle circulation

The approved plan extraction records a parking area of 216.00 sq. m, while the permit extraction records a total parking area of 156 without specifying a unit in that field. The permit sanctions a stilt and requires the stilt/parking area to be used exclusively for vehicle parking; the supplied records do not establish the number of car or two-wheeler spaces, visitor or accessible parking, mechanical parking, ramp arrangement, or unit-by-unit allocations.

The filed approval conditions require parking places in buildings to provide electric-vehicle charging infrastructure in accordance with the cited technical requirements and guidelines. This is an approval condition; the supplied material does not confirm installation or operation. A parking space shown in a plan does not by itself establish exclusive ownership or allocation to a particular apartment.

6. Amenities, recreation & open spaces

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
LiftListed as a project utility; no count, capacity or specification suppliedNot verified as installed; no progress percentage supplied for the lift
Tot-lot / green stripApproval condition: fence and maintain the tot-lot as greenery; peripheral planting and greenery strip also requiredApproval condition; amenities record lists green strip/tot-lot/park at 0%
Community buildingsListed in the RERA amenities schedule; no size or facility detail suppliedRERA amenities0%; completion not independently verified
Aggregate recreational open spaceListed in the RERA amenities schedule; no area suppliedRERA amenities0%; completion not independently verified
Internal roads and footpathsListed in the RERA amenities schedule; no dimensions suppliedRERA amenities0%; completion not independently verified
Street lightingListed in the RERA amenities scheduleRERA amenities0%; completion not independently verified

The RERA amenities schedule lists 14 infrastructure and amenity categories, with 0% progress recorded for the items shown except that water supply and rainwater harvesting are marked “YES”; those entries do not establish that the facilities are complete or independently verified. RERA amenities

7. Utilities, building services & safety

  • Water and conservation: The RERA amenities schedule marks water supply and water conservation/rainwater harvesting “YES.” The approval identifies four rainwater-harvesting pits and requires a rainwater-harvesting structure. A WTP and percolating well also appear in the plan extraction, but no capacity, source, treatment performance or completion status is supplied. RERA amenities
  • Sewerage, drainage and waste: Sewerage, storm-water drains, and treatment/disposal of sewage and sullage water are listed in the RERA amenities schedule, each at 0%. The plan extraction lists an STP and requires an on-site garbage house; no capacity or commissioning evidence is supplied. RERA amenities
  • Electrical services: The plan extraction lists an electrical transformer and requires space for a transformer. The supplied material does not state supply capacity, backup arrangements or installation status.
  • Fire and life safety: The permit requires an occupancy fire NOC from the Director (EV&DM) before issue of the occupancy certificate and makes structural and fire safety the responsibility of the owner, builder/developer and project professionals. No fire NOC or OC is supplied.
  • Construction and digital infrastructure: The permit includes conditions on construction-worker safety, C&D waste disposal and demarcation of building/rooftop space for broadband and digital-connectivity infrastructure. These are conditions, not confirmation of completed facilities.
  • Accessibility and lifts: The plan extraction lists a lift but provides no number or capacity. No project-specific accessible route, ramp or accessibility-feature detail is supplied.

8. Location, access & connectivity

The registered project location is Plot No. 30, Gopanpally village, Serilingampally mandal, Ranga Reddy district, Telangana, PIN 500019; the project land is identified as Survey No. 231 part and Survey No. 316 part. RERA record

The GHMC plan extraction refers to 12.00 m and 18 m roads. A location-data record gives the nearest sampled Outer Ring Road interchange as approximately 6.9 km; this is a supplied mapped-distance estimate, not a measured route or travel time. No public-transport details or verified distances to other landmarks are supplied. Location record

9. Developer & development status

The registered promoter is SUVELA PROJECTS, identified in the RERA filing as a partnership. The filing provides GSTIN 36AECFS5629B1Z6. Named project representatives include SANIKOMMU RAJA SEKHAR as authorized signatory and SANIKOMMU PUSHPA SEKHAR as partner. The supplied record does not establish an official website or project contact details. Corporate record Parties record

The project’s Form-B affidavit, signed by S. Raja Sekhar for Suvela Projects, declares a completion date of 24.08.2027 and sets out the promoter’s project-fund, audit and pending-approval undertakings. This is a promoter declaration; the supplied material does not independently verify construction progress or completion.

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02400011097; valid 24/08/2024–24/08/2027
What the supplied record establishesForm C registration for Sai Swara by Suvela Projects and the stated Gopanpally project land
GHMC building permit
Identifier / date2541/GHMC/SLP/2024-BP; 24 August 2024
What the supplied record establishesPermit for Building A, 1 Stilt + 5 upper floors, on a 418.06 sq. m plot; includes conditions for OC and occupancy fire NOC
GHMC file / plan reference
Identifier / date003971/GHMC/1929/SLP2/2024-BP
What the supplied record establishesFiled building-plan reference; the extracted plan identifies Survey Nos. 231 part and 316 part, Plot No. 30, and ten units
Layout reference recorded in permit
Identifier / date3593/MP2/Plg/HUDA/2001
What the supplied record establishesReference recorded in the building-permit extraction; a separate approved-layout drawing or independently verified layout record is not supplied here
Form-B affidavit-cum-declaration
Identifier / date24 March 2026
What the supplied record establishesPromoter’s declaration of land title, encumbrance position, fund arrangements and completion by 24.08.2027
Filed floor-plan / approval drawing
Identifier / dateDocument 679530
What the supplied record establishesPlan-extracted building configuration, areas, parking and conditions; drawing-derived carpet measurements are software-measured, not RERA-filed Floor plans

Frequently asked questions

Is SAI SWARA BY SUVELA PROJECTS registered with Telangana RERA?

Yes. SAI SWARA BY SUVELA PROJECTS is registered with the Telangana Real Estate Regulatory Authority as P02400011097; the registration status is New Project.

Who is the developer of SAI SWARA BY SUVELA PROJECTS?

The promoter named in the RERA registration is SUVELA PROJECTS.

Where is SAI SWARA BY SUVELA PROJECTS located?

SAI SWARA BY SUVELA PROJECTS is in GOPANPALLY, Serilingampally, Rangareddy, Telangana (500019).

When will SAI SWARA BY SUVELA PROJECTS be completed?

The promoter's proposed date of completion filed with RERA is 24/12/2027. This is the promoter's declaration, not a guarantee.

More projects in Gopanpally