JAIN PRAMUKH SAMRIDDHI TOWERS is a residential apartment project in Satamrai, Shamshabad, Ranga Reddy. The registered promoter is Jain Construction, partnership. The project has a land area of 22252.56 sqmts and 370 apartments across three residential blocks, with 3BHK, 4BHK and 5BHK configurations; the residential blocks are described as having 27 upper floors. Its TG-RERA registration number is P02400008724, and the project header records proposed completion as 22/10/2029.

01What we found

RegisteredTG-RERA - valid till 22 Jun 2029
70documents on file - each fact links to its page
0court cases on this project's land in the court records searched
10items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

10 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Developer renderDeveloper renderDeveloper renderProject photo
▦ View all 10 photos
Satamrai, Shamshabad, Ranga Reddy · geocoded — approximate.

1. Project at a glance

Project identity

ItemProject record
Registered project nameJAIN PRAMUKH SAMRIDDHI TOWERS RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionThe registration record identifies the project as a whole; a separate phase designation is not disclosed. RERA record
TG-RERA registrationP02400008724 RERA record
Registration validityForm C states validity from 30/08/2024 to 22/06/2029, unless extended by the Authority. This is the registration-validity period, not an occupancy certificate.
Registered promoterJain Construction, partnership. RERA record RERA filing Corporate record
RERA status in supplied recordListed as New Project; registration certificate supplied. The record gives 80% completeness for the evidence set, not a construction-progress percentage. RERA record

Land and geographic identity

ItemProject record
LocalitySatamrai RERA record RERA filing
Revenue villageSatamrai Vill. in the registration certificate; the filed land and approval records also identify Satamrai Village (one approval OCR renders it “Satamrsl”). Land records
Mandal / district / PINShamshabad / Ranga Reddy / 501218 RERA record
Project survey referenceSurvey No. 36 Part, also rendered in filed documents as Sy.No.36/Part, 36/Part or 36 PART. RERA record Land records
Registered site extentNot stated in the registration certificate extraction. The building-permit extraction states 22,252,56 Sq. Mt.; the RERA land-details field records total area and net area as 22252.56 sqmts. RERA filing
Total / net land areaBoth filed RERA land fields state 22252.56 sqmts; affected road-widening/FTL/Nala-widening area is recorded as 0. RERA filing
Boundaries (RERA land filing)East: NH-44 Old-7 Hyderabad to Banglore; West: Road and Land in Sy No 656 of Shamshabad Village; North: Neighbours Land in Gaganpahad Village; South: Part of the Land in Sy No 36. RERA filing

Development identity

ItemProject record
Principal building permissionBuilding permit order dated 22 June, 2024, approval reference OO7saO/BPlHltlDAl L641lsNlDl2023 as OCR-extracted; the RERA filing identifies plan approval no. 007580/BP/HMDA/1641/SMD/2023. RERA record
Authority shown on filed permitShamshabad Municipal Corporation; the permit references HMDA proceedings. Approvals record
Approved built-up areaPermit extraction lists 225019.56 as an approved built-up-area figure. It separately lists total built-up area 223,495.75 and proposed built-up area total 156,5O1.O5; these are distinct figures as transcribed in the document extraction. RERA filing
Buildings / blocksThree residential blocks (A, B, C) and a separate amenity/club-house building are described in the permit and fire-service records. The building-permit extraction’s “Number of the Block 4” is consistent with four listed building components.
Sanctioned floor configuration in permit extractionBlock A: 1 Stilt + 27 upper floors; Block B: 1 Stilt + 27 upper floors; Block C: 3 Cellar + I Stilt + 27 upper floors; A (Amenities): 1 Ground + 6 upper floors.
Fire-service building particularsProvisional fire NOCs describe residential Blocks A, B and C as 3 Cellars, 1 Stilt, 27 Floors and 92.90 metres high. The club-house NOC describes 1 Ground, 7 Floors, 30.00 metres high, Assembly D-3 occupancy.
Unit countsRERA land details state 3 total building units and 3 proposed building units; the unit inventory records 370 apartments across three residential blocks/towers. RERA filing RERA unit table

Offering and status

ItemProject record
RERA-filed configurations3BHK, 4BHK and 5BHK RERA unit table RERA unit details
RERA-filed saleable areas3BHK: 355.41 sq.m; 4BHK: 436.0–517.0 sq.m; 5BHK: 609.0 sq.m RERA unit table
Booked / available3BHK: 29 / 71; 4BHK: 35 / 208; 5BHK: 4 / 23. Portal counts have no supplied as-of date and are indicative. RERA unit table
Construction stageNo project construction-progress percentage or independently verified site-progress record is supplied. RERA amenity records list facilities but show 0 in the progress field. RERA amenities
Completion datesPromoter Form B undertaking states 22.06.2029. The project header records proposed completion 22/10/2029. The supplied material does not identify an approved extension or otherwise resolve these as completion dates. RERA record
Occupancy-certificate statusNo occupancy certificate is supplied for the project or any identified block. The fire-service documents are provisional NOCs and require further occupancy-stage steps; they are not OCs. Document index

2. The project story

JAIN PRAMUKH SAMRIDDHI TOWERS is registered as a residential apartment project on Survey No. 36 Part in Satamrai Village, Shamshabad Mandal, Ranga Reddy District. Its RERA inventory describes 370 apartments—3BHK, 4BHK and 5BHK—organized across three residential blocks/towers. The filed building-permit extraction also identifies an amenity building, while a provisional fire NOC describes the club house as a separate Assembly D-3 building. RERA record RERA filing RERA unit table

The permit extraction describes residential blocks with 27 upper floors; Block C additionally has three cellar levels. Fire-service NOCs describe all three residential blocks as having three cellars, a stilt and 27 floors, and the club house as one ground plus seven floors. These are proposed/sanction-document descriptions, not evidence that the buildings have been completed. No independently verified construction stage or occupancy certificate is included in the supplied record.

3. Master plan, architecture & building design

The RERA land details give a total and net site area of 22252.56 sqmts, with no affected area recorded for road widening, tank FTL or nala widening. The permit extraction records 225019.56 as an approved built-up-area figure and separately transcribes total built-up area as 223,495.75 and proposed built-up area total as 156,5O1.O5. These are reported as separate document fields; no area-category reconciliation is supplied. RERA filing RERA filing

The permit describes Blocks A and B as one stilt plus 27 upper floors, Block C as three cellars, one stilt and 27 upper floors, and an amenities component as one ground plus six upper floors. The fire-service records give residential-block heights of 92.90 metres and a club-house height of 30.00 metres. They also specify fire-access and egress details, including 6.00-metre proposed entry and exit gate widths in the extracted block records, 1.50-metre staircases in residential-block records, and vehicle ramps between cellar levels and stilt. These are document-stated design particulars, not confirmation of completed construction.

Two floor-plan drawings are listed, but both are scans pending measurement; no drawing-derived flat layouts, room dimensions, flats-per-floor counts, lift counts, or building-footprint measurements are available. The approved-plan record supplies no verified FSI-counted area, carpet area or floor-by-floor unit arrangement. Floor plans

4. Homes, configurations & floor plans

RERA records three apartment configurations. Saleable area is the filed area figure; it is not a measured carpet area. The drawing-measurement record reports zero plans measured and two scans pending, so no software-measured carpet area or loading figure can be quoted. RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK1002971355.41 sq.mNot measuredNot supplied
4BHK24335208436.0–517.0 sq.mNot measuredNot supplied
5BHK27423609.0 sq.mNot measuredNot supplied

The RERA portal booking counts have no supplied as-of date and should be treated as indicative. The two floor-plan scans have not been measured; room arrangements, dimensions, balcony/utility areas and typical floor layouts therefore cannot be described from the available drawing data. RERA unit table RERA unit details Floor plans

5. Parking & vehicle circulation

The permit extraction describes cellar parking in the building specifications only through the separate vendor-provided material; the supplied sanctioned-plan extraction does not state a project-wide number of car or two-wheeler spaces, visitor spaces, accessible spaces, or a verified allocation schedule. The vendor describes cellar parking, parking signage, car-wash provision and allotment at booking, and claims a configuration-based number of car parks per flat; these are promoter/marketing statements, not a verified sanctioned count or a legally documented allocation for a particular unit. Promoter website

Fire-service records describe vehicle ramps in the residential blocks: three 6.00 m ramps from Cellar-3 to Cellar-1 and two 6.00 m ramps from Cellar-1 to Stilt in the extracted Block A and C particulars. Block B’s fire NOC also lists three cellars, a stilt and 27 floors, but no separate ramp figures are supplied in that extraction. The record does not establish pedestrian-vehicle separation or completed EV charging installation. Promoter website

6. Amenities, recreation & open spaces

The RERA filing lists 14 site-level amenity/infrastructure categories. Each is marked “YES,” while the supplied progress field is 0; this indicates listed provision, not verified completion. The permit and fire-service records additionally describe an amenities/club-house building. No facility sizes or independently verified completion status are supplied for the RERA-listed amenities. RERA amenities

Community buildings
Description / sizeListed as “YES”; the permit and fire-service documents identify an amenities/club-house building.
Evidence sourceRERA amenities
Declared progress / verified statusRERA progress field: 0; no completion verification supplied.
Green strip / tot lot / park
Description / sizeListed as “YES”; no area or capacity supplied.
Evidence sourceRERA amenities
Declared progress / verified statusRERA progress field: 0; no completion verification supplied.
Aggregate recreational open space
Description / sizeListed as “YES”; no area supplied.
Evidence sourceRERA amenities
Declared progress / verified statusRERA progress field: 0; no completion verification supplied.
Indoor / outdoor recreation, clubhouse and other lifestyle features
Description / sizePromoter/marketing material lists a range of features, including a pool, sports and indoor-game facilities, gym, guest rooms, lawns and places of worship; sizes and quantities are not supplied in that material.
Evidence sourcePromoter website
Declared progress / verified statusMarketing statements; no project-filed progress or independent completion verification supplied.

7. Utilities, building services & safety

The RERA amenity list marks water supply, sewerage/STP, storm-water drains, solid-waste management, rainwater harvesting, energy management, fire protection and electrical meter/substation/receiving-station provision as “YES.” The progress field is 0, so the list does not establish that these services are complete or operational. RERA amenities

The building permit requires an STP and states that an occupancy certificate is compulsory before occupation; it also requires the indicated approach road to be developed and maintained as a black-topped road before release of the occupancy certificate. The provisional fire NOCs set out fire-system and access requirements, including sprinklers, alarms, hydrants, fire pumps, water storage, protected egress, and unobstructed fire-appliance access. These documents describe requirements/proposed provisions; they do not establish final fire clearance or occupancy.

Promoter/marketing specifications additionally describe treated water tanks, STP-water reuse, rainwater harvesting, storm-water drainage, lifts, backup power, electrical car-charging points, CCTV and security arrangements. These are promoter statements, not independently verified installed services; capacities and completed status are not supplied. Promoter website

8. Location, access & connectivity

The registered location is Satamrai Vill., Shamshabad, Ranga Reddy, 501218, with the project land identified as Survey No. 36 Part. The RERA-filed boundary description identifies NH-44 on the east and a road and land in Sy No 656 of Shamshabad Village on the west. RERA filing

The building-permit extraction identifies approach-road widths of 4.5mts., 3.0mts. and 1.smts.; the residential-block fire records refer to an 11.00 mtrs clear driveway and a 14.00 mtrs turning radius. A project-location record gives the Rajiv Gandhi International Airport at 5.1 km. Location record

9. Developer & development status

The registered promoter is Jain Construction, identified as a partnership, with GSTIN 36AASFJ5733B1ZA. The registration certificate gives the promoter’s registered-office location as Satamrai Vill., Shamshabad, Ranga Reddy, PIN 501218. The RERA record names Ankur Agarwal as authorized signatory; the listed partners include Ankur Agarwal, Anuj Jain, Praveen Kumar Jain and Suresh Jain. Corporate record RERA filing Parties record

The Form B affidavit is a promoter declaration. It states a completion undertaking of 22.06.2029 and undertakings concerning approvals, project funds and accounts. The project header separately lists proposed completion as 22/10/2029; the supplied evidence does not establish an extension or resolve these dates. No construction-progress percentage or block-specific completion status is supplied. RERA record

10. Approvals, official records & documents

RecordSupplied project evidence
TG-RERA registrationForm C certificate for JAIN PRAMUKH SAMRIDDHI TOWERS, registration P02400008724; validity stated as 30/08/2024–22/06/2029, unless extended.
Principal building permissionBuilding permit order dated 22 June, 2024, RERA-filed plan approval 007580/BP/HMDA/1641/SMD/2023; permit OCR also records a differently rendered reference. The permit is attributed to Shamshabad Municipal Corporation and refers to HMDA proceedings. RERA record
Environmental clearanceSEIAA Telangana EC EC22B038TG154886, file SIA/TG/MIS/276249/2022, dated 20/07/2022, for “Jains Pramukh”; the supplied extraction does not include site or survey particulars.
Height clearanceAirports Authority of India height NOC HIAL/SOUTH/B/091421/575218, dated 29-09-2021, for Survey No. 36 PART; restricted permissible top elevation 663.00 M, stated validity through 28-09-2029.
Fire-service recordsProvisional fire NOCs dated 13/03/2023 are supplied for Blocks A, B and C and the club house. They are not occupancy certificates; the records require further occupancy-stage fire clearance.
Other filed recordsForm B affidavit dated 24ft day ofJune2024; title-search report; environmental clearance and building-permit records; and project-specific encumbrance statements are listed in the supplied filing.

The supplied material does not include an occupancy/completion certificate or a measured floor-plan set. The two floor-plan drawings remain scans pending measurement. Document index Floor plans

Frequently asked questions

Is JAIN PRAMUKH SAMRIDDHI TOWERS registered with Telangana RERA?

Yes. JAIN PRAMUKH SAMRIDDHI TOWERS is registered with the Telangana Real Estate Regulatory Authority as P02400008724; the registration status is New Project.

Who is the developer of JAIN PRAMUKH SAMRIDDHI TOWERS?

The promoter named in the RERA registration is Jain Construction.

Where is JAIN PRAMUKH SAMRIDDHI TOWERS located?

JAIN PRAMUKH SAMRIDDHI TOWERS is in Satamrai, Satamrai Vill., Shamshabad, Rangareddy, Telangana (501218).

When will JAIN PRAMUKH SAMRIDDHI TOWERS be completed?

The promoter's proposed date of completion filed with RERA is 22/10/2029. This is the promoter's declaration, not a guarantee.