CITIZEN PARK SQUARE is a residential apartment project in Banjara Hills, KHAIRTABAD mandal, Hyderabad district. The registered promoter developing it is WM CITIZEN INFRA PROJECTS, a partnership. The project is on a 1,401.30 sq m site and has one building with Cellar + Ground + 4 upper floors and 20 3BHK units, with a RERA-filed saleable area of 191.46 sq m. It is registered with TG-RERA under P02500002713, with proposed completion on 24/01/2026.

01What we found

Period endedTG-RERA registration ran to 24 Jan 2026 - check its extension on TG-RERA
18documents on file - each fact links to its page
0court cases on this project's land in the court records searched
7items to check - 4 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

7 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Project at a glance

Project identity

FieldRecord
Registered projectCITIZEN PARK SQUARE RERA record
Project type / phaseResidential apartment project; phase or separately described registered portion: not disclosed. The RERA record describes one building. RERA record RERA filing RERA unit table
TG-RERA registrationP02500002713
Registration validity30/03/2021 to 24/01/2026; certificate states four years and no extension is recorded in the supplied data. This is registration validity, not the building’s occupancy status.
Registered promoterWM CITIZEN INFRA PROJECTS, a partnership. RERA filing Corporate record
RERA-recorded status“New Project.” The registration certificate confirms registration under section 5. RERA filing

Land and geographic identity

FieldRecord
Locality / revenue villageBanjara Hills is the registered locality and the village stated in the project identity. The building-permit extraction labels the village BANJARAHILLS -19. The occupancy-certificate extraction labels it Shaikpet; the RERA certificate lists mandal KHAIRTABAD. Revenue-village identity therefore is not consistently established by the supplied records. RERA record Land records
Mandal / district / PINMandal: RERA certificate states KHAIRTABAD; building-permit extraction does not supply a mandal. District: Hyderabad. PIN: 500034 in the RERA certificate and project identity. RERA record
Survey numbers and subdivisionsRERA land details do not disclose survey numbers. The occupancy-certificate extraction identifies 164/74; the supplied title materials also refer to Survey No. 151/8 and Survey No. 92/A, but the evidence provided does not establish these as the complete project survey identity. The registered plot description is 8-2-120/77/4 & 8-2-120/77/5, ON PLOT NO 4 & 5. Land records
Site area1,401.30 sq m total and net site area in the RERA land details and building-permit extraction; road-affected area is recorded as 0. Land records
BoundariesEast: 40 FEET WIDE ROAD; West: JAPANESE GARDEN AND NEIGHBORS HOUSE; North: HOUSE OF Mr SHIVA NAG - 227; South: HOUSE ON PLOT NO 92 By A PART. RERA filing

Development identity

FieldRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC). Approvals record
Principal building approvalBuilding Permit Order 1/C18/00925/2020, approved 24 January, 2020; file no. 1/C18/19521/2019. Approvals record
Approved built-up area3,224.49 sq m in the RERA project record and as sanctioned in the occupancy-certificate extraction. That certificate separately records 3,235.95 sq m as the site-building-plan floor area. RERA filing
Building count and configurationOne building is recorded. The sanctioned configuration is Cellar + Ground + 4 upper floors; the occupancy certificate describes 2 Cellar + Ground + 4 Upper Floors. Land records
ParkingThe permit identifies cellar and ground/upper-floor parking areas, including 1,780.19 for cellar parking and 69.76 for G/U floors parking. The occupancy certificate records parking area of 1,849.95 m2. A sanctioned space count is not supplied.
Units20 units in the RERA unit record; the building-permit extraction does not supply a numerical sanctioned unit count. RERA unit table RERA unit table

Offering and status

FieldRecord
Filed configuration and area3BHK, RERA-filed saleable area 191.46 sq m. RERA unit table RERA unit table
Bookings / availability3 booked; 17 available, as last read from the TG-RERA portal; no as-of date is supplied, so these counts are indicative rather than current-confirmed. RERA unit table
RERA completion commitment24/01/2026 in the registration record; the promoter’s Form B declaration also undertakes completion by 24th JANUARY 2026. RERA record
Construction stageThe supplied evidence includes a GHMC occupancy certificate identifying the residential building as fit for occupation; it does not provide a separately dated, current site-progress assessment.
Occupancy certificateGHMC 1068/GHMC/KHB/2025-OC, dated 22 May, 2025; the certificate covers the residential building described as 2 Cellar + Ground + 4 Upper Floors. Approvals record

The project story

CITIZEN PARK SQUARE is a single-building residential apartment project registered with TG-RERA in Banjara Hills, Hyderabad. The RERA record describes one building on a 1,401.30 sq m site, with 20 filed 3BHK units. The building permit describes a residential building with cellar parking, a ground floor and four upper floors. RERA record Land records RERA unit table

The registration certificate and promoter’s Form B set a completion date of 24/01/2026. Separately, the supplied GHMC occupancy certificate records that the building was inspected and declared fit for occupation, with completion dated 21 March, 2025 and the certificate dated 22 May, 2025. The certificate is for the building described in that document; the supplied record does not provide a separate phase-wise or unit-wise OC breakdown.

TG-RERA’s latest supplied unit read shows 3 booked and 17 available, but is undated. It should be treated as an indicative portal snapshot, not a current availability confirmation. RERA unit table

Master plan, architecture & building design

The GHMC building permit sanctions one residential building, Building - A-1 (PROPOSD), described as Cellar + Ground + 4 upper floors and 14.99 m high. The occupancy-certificate extraction describes 2 Cellar + Ground + 4 Upper Floors. The supplied documents do not provide a verified floor-by-floor apartment schedule, lift and stair details, building footprint, or a complete circulation plan.

The RERA record gives approved built-up area as 3,224.49 sq m. The occupancy-certificate extraction records the same figure as floor area “As per Sanctioned Plan,” and separately records 3,235.95 sq m “As per Site Building Plan.” These are document-labelled area figures; no FSI-counted area or carpet-area total for the whole project is supplied. RERA filing

The permit specifies 75.76 m² for a tot-lot and records 70 Trees, 4 RWHPs, a transformer space and a garbage house. The permit also requires the cellar and stilt areas approved for parking to be used exclusively for vehicle parking.

Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK20317191.46 sq m119.0–135.1 sq m; median 132.5 sq m31%

The unit count, booking count, availability and saleable area are from the TG-RERA filing; booking figures have no supplied as-of date. Carpet measurements are software-measured from approved floor-plan drawings and are not RERA-filed measurements; the drawing extraction notes that review is needed. RERA unit table RERA unit table Floor plans RERA unit details

The drawing-based 3BHK measurement covers eight flat designs. A representative second-floor plan labels bedrooms, toilets, dining, drawing room, kitchen and utility areas; the two labelled utility areas are excluded from the measured carpet area. Carpet area, utility space and saleable area are distinct measures: the RERA saleable figure is not a carpet-area figure. RERA unit details Floor plans

Parking & vehicle circulation

The GHMC permit allocates 1,780.19 to cellar parking and 69.76 to G/U floors parking; it also states that the cellar and stilt areas approved for parking are to be used exclusively for parking. The occupancy-certificate extraction records 1,849.95 m2 as parking area. These records do not establish a car- or two-wheeler-space count, visitor or accessible parking provision, EV charging, parking allocation to individual units, or whether any bay is for exclusive use.

The supplied evidence does not describe vehicle ramps, internal driveways, pedestrian separation or a parking-allotment arrangement. A parking area shown or recorded in a sanction does not by itself establish exclusive ownership of a parking space.

Amenities, recreation & open spaces

Tot-lot / green area
Description / size75.76 m²
Evidence sourceGHMC building permit; occupancy-certificate extraction
Declared progress / verified statusIncluded in the permit; OC extraction also records the tot-lot area.
Common Garden; security; CCTV; waste management; fire safety; lift; power backup; sewage treatment plant; swimming pool; gym; children’s play area; clubhouse; covered car parking
Description / sizeNo sizes or detailed specifications supplied
Evidence sourceThird-party vendor listing Promoter website
Declared progress / verified statusListing claims only; not established by the supplied sanctioned or RERA amenity documents.

The RERA amenity schedule marks water supply, sewerage, storm-water drains, green strip/tot-lot/park, sewage and sullage treatment, solid-waste management, rainwater harvesting, and an electrical meter room/sub-station/receiving station as available at 100%. It records 0% for internal roads and footpaths, street lighting, community buildings, energy management, fire protection and fire-safety requirements, and aggregate recreational open space. These are the filed progress entries; they are not independent site verification. RERA amenities

The building permit requires the tot-lot to be fenced and maintained as greenery before OC. The occupancy-certificate extraction records a tot-lot area of 75.76 m².

Utilities, building services & safety

The RERA amenity schedule marks water supply, sewerage, storm-water drains, sewage and sullage treatment, solid-waste management, rainwater harvesting, and an electrical meter room/sub-station/receiving station as available at 100%. It does not supply capacities, system specifications, water source or storage details, sewerage-treatment capacity, power-backup details, lift capacity or fire-system specifications. RERA amenities

The GHMC permit requires a rainwater-harvesting percolation pit, transformer space, and a garbage house. It also requires an occupancy Fire NOC from the Director (EV&DM) before issue of an occupancy certificate. The supplied occupancy certificate states that the building was declared fit for occupation; the extracts do not include the Fire NOC itself or a detailed fire-system schedule.

No supplied project record details accessible routes, ramps, CCTV or access-control systems, EV charging, or the specific water, drainage and electrical capacities. The permit requires parking areas to be used for parking and states that a safe separation distance from high- and low-tension electrical lines is to be maintained.

Location, access & connectivity

The registered location is Banjara Hills, Hyderabad, Telangana, PIN 500034. The project record describes the eastern boundary as a 40 FEET WIDE ROAD. A cadastral-parcel-centroid location is supplied at 17.41528, 78.35459; this is a mapped parcel-centroid coordinate, not a surveyed entrance point. RERA record RERA filing Location record

The supplied location data identifies Financial District (Nanakramguda) at 1.2 km as an anchor. No measured distances to public-transport stops or other landmarks, or verified travel times, are supplied. Location record

Developer & development status

The TG-RERA registered promoter is WM CITIZEN INFRA PROJECTS, recorded as a partnership. The RERA record identifies WALI MOHAMMED as authorized signatory and lists FAROOQ WALI MOHAMMED, TAREEQ WALI MOHAMMED, SHAREEQ WALI MOHAMMED and GOUSIA BEGUM as partners. Its recorded office address is KAPUR TOWERS, DWARAKAPURI COLONY, BANJARA HILLS, BANJARA HILLS, Hyderabad, 500034. RERA filing Parties record

The GHMC building-permit extraction names CITIZEN BUILDERS AND DEVELOPERS as builder; the supplied records do not establish it as the TG-RERA registered promoter. The Form B affidavit is a promoter declaration that the project would be completed by 24th JANUARY 2026. The supplied GHMC occupancy certificate records the building as fit for occupation.

Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02500002713; issued 30/03/2021, valid to 24/01/2026
Scope and evidenceForm C certificate for CITIZEN PARK SQUARE; includes a separate-account condition.
GHMC building permit order
Identifier / date1/C18/00925/2020; 24 January, 2020; file no. 1/C18/19521/2019
Scope and evidenceBuilding permit for the residential building; includes stated conditions.
GHMC occupancy certificate
Identifier / date1068/GHMC/KHB/2025-OC; 22 May, 2025; application 003514/GHMC/1529/KHB1/2025-OC
Scope and evidenceOccupancy certificate for the residential building identified in the document as 2 Cellar + Ground + 4 Upper Floors. It records completion dated 21 March, 2025 and says the building is fit for occupation.
Architect’s title opinion / title materials
Identifier / dateTitle opinion dated 09.12.2020; cited deed references include Development Agreement cum GPA 6452/2019
Scope and evidenceTitle opinion and supporting title-document extracts are available in the RERA-filed document set.
Form B promoter declaration
Identifier / date30thday of December 2020
Scope and evidencePromoter declaration concerning title basis, encumbrance status, project funds and completion undertaking.
Approved layout / drawing record
Identifier / datePlan approval number 1/C18/00925/2020; drawing text layer dated 29-01-2020
Scope and evidenceA layout-plan document is listed in the RERA filing, but its supplied extraction is incomplete. Approvals record

Frequently asked questions

Is CITIZEN PARK SQUARE registered with Telangana RERA?

Yes. CITIZEN PARK SQUARE is registered with the Telangana Real Estate Regulatory Authority as P02500002713; the registration status is New Project.

Who is the developer of CITIZEN PARK SQUARE?

The promoter named in the RERA registration is WM CITIZEN INFRA PROJECTS.

Where is CITIZEN PARK SQUARE located?

CITIZEN PARK SQUARE is in BANJARA HILLS, Hyderabad, Telangana (500034).

When will CITIZEN PARK SQUARE be completed?

The promoter's proposed date of completion filed with RERA is 24/01/2026. This is the promoter's declaration, not a guarantee.