Maram R P Homes
MARAM INFRA PROJECTS PRIVATE LIMITED · Hyderabad · RERA P02500000056
MARAM R P HOMES is a residential apartment project in Hayathnagar, Saroor Nagar Mandal, Hyderabad district. It is being developed by the registered promoter MARAM INFRA PROJECTS PRIVATE LIMITED on a 4149.23 m² site, with one building, Building A, comprising Cellar + Stilt + 5 floors. The project has 117 2BHK units. It is registered under TG-RERA registration number P02500000056, with proposed completion on 28/12/2019.
More from Maram Infra Projects Pvt Ltd · 7 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
12 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | MARAM R P HOMES |
| Project type | Residential apartment project RERA filing |
| Phase / registered portion | Phase not separately identified in the supplied record; registration refers to the project. |
| TG-RERA registration | P02500000056 |
| Registration validity | 30/11/2018–28/12/2019; no extension is recorded in the supplied certificate data. This is the registration period, not the occupancy-certificate status. |
| Registered promoter | MARAM INFRA PROJECTS PRIVATE LIMITED |
| RERA status | The project evidence labels it “On-Going Project”; the supplied registration certificate records the validity dates above. RERA record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality | Hayathnagar RERA filing |
| Revenue village | Hayathnagar; the building-permit extraction also describes the locality as Hayathnagar. Land records |
| Mandal | Saroor Nagar Mandal in the GHMC building-permit extraction; the supplied registration certificate separately gives Saidabad. Mandal identity should be checked against the project’s revenue records. |
| District / PIN | Hyderabad / 501505 RERA record |
| Project survey number(s) | Survey No. 219; no subdivision is supplied. Land records |
| Site extent | 4149.23 m² site area; 4149.23 m² net area; road-affected area recorded as 0 in the building-permit extraction. |
| Boundaries | North: neighbours’ land; South: 40 ft wide road; East: neighbours’ land; West: 30 ft wide road. RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Principal building approval | 1/C3/06363/2017, dated 13 July 2017; file no. 1/C3/05120/2017 Approvals record |
| Approved building | Building A, residential; Cellar + Stilt + 5 floors |
| Approved built-up area | 10,697.40 m² recorded as residential in the permit extraction; the RERA filing also records approved built-up area of 10,697.4 m². RERA filing |
| Building count | One building / one block in the supplied project and unit records. RERA unit table |
| Approved versus RERA-declared units | The permit extraction does not state a unit count. TG-RERA unit data records 117 units. RERA unit table |
Offering and status
| Field | Project record |
|---|---|
| RERA-filed configuration | 2BHK; 117 units RERA unit table |
| RERA-filed saleable area | 43.52 m² per unit RERA unit table |
| Booked / available | 0 booked / 117 available in the portal data; no as-of date is supplied, so counts are indicative rather than a current inventory confirmation. RERA unit table |
| Completion dates | Original and revised proposed completion: 28/12/2019 RERA filing |
| Occupancy certificate | The supplied RERA-filed architect certificate identifies GHMC OC 0008/GHMC/CBN/2021-OC, dated 25/06/2021, for the building. |
| Construction stage | A Form–1A architect certificate dated 28/04/2025 certifies project completion; this is a filed professional certificate, not an independent site inspection in the supplied evidence. |
2. The project story
MARAM R P HOMES is a residential apartment development on Survey No. 219 in Hayathnagar, Hyderabad. The GHMC building-permit record describes one residential building, Building A, with a cellar, stilt and five floors, on a 4149.23 m² site. Land records
The RERA-filed offer is 117 two-bedroom apartments. The portal records all 117 as available and none as booked, but supplies no date for that inventory snapshot. RERA unit table A Form–1A architect certificate dated 28/04/2025 certifies overall completion and cites the building’s GHMC occupancy certificate dated 25/06/2021. These are filed records; no independent site-progress verification is supplied here.
3. Master plan, architecture & building design
The GHMC permit records a 4149.23 m² site and net area, with 10,697.40 m² shown as residential and the building configuration recorded as Cellar + Stilt + 5 floors. It also lists a 366.92 m² “Tot-lot,” 2,758.24 m² cellar area and 2,218.20 m² stilt area. These are the permit extraction’s separate area labels; they should not be treated as interchangeable area measures.
The permit requires construction to follow the sanctioned plan and identifies a 14.5 m height in the extracted parameters. The supplied drawing records do not provide usable measured floor-plan geometry: five drawings are listed, with none measured and no flats extracted from them. Details such as flats per floor, building footprint, internal circulation, lifts, stairs, orientation and room layout therefore cannot be described from the available drawing-derived data. Floor plans
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 117 | 0 | 117 | 43.52 m² | Not available | Not supplied |
The 43.52 m² figure is the RERA-filed saleable area, not a measured carpet-area figure. No software-measured carpet area or room dimensions are available: the supplied floor-plan record reports five drawings, none measured. RERA unit table Floor plans
5. Parking & vehicle circulation
The supplied evidence does not establish sanctioned parking counts, parking allocation by apartment, visitor or accessible parking, parking-bay locations, ramps, or vehicle circulation arrangements. The permit identifies cellar and stilt levels but does not, in the provided extraction, specify their parking use or capacity. A parking entitlement for an individual unit cannot be confirmed from these records. Document index
6. Amenities, recreation & open spaces
TG-RERA amenity data marks the following items as available in the filing; the percentages are the reported progress values in that data, not independently verified completion:
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Community buildings | Size and facility details not supplied | RERA amenities | 30% recorded; not independently verified |
| Water supply | Source, storage and treatment details not supplied | RERA amenities | 20% recorded; not independently verified |
| Sewerage (chamber, lines, septic tank, STP) | Specific system and capacity not supplied | RERA amenities | 20% recorded; not independently verified |
| Internal roads and footpaths | Dimensions and materials not supplied | RERA amenities | 0% recorded; not independently verified |
| Green strip / tot-lot / park | GHMC permit lists a 366.92 m² “Tot-lot” and requires it to be fenced and maintained as greenery before OC; the amenity record gives no area for the green space. | RERA amenities | Amenity progress 0%; completion not independently verified |
| Storm-water drains | Details not supplied | RERA amenities | 0% recorded; not independently verified |
| Street lighting | Details not supplied | RERA amenities | 0% recorded; not independently verified |
| Sewage and sullage treatment/disposal | Facility details not supplied | RERA amenities | 0% recorded; not independently verified |
| Solid-waste management and disposal | Facility details not supplied | RERA amenities | 0% recorded; not independently verified |
| Water conservation / rainwater harvesting | GHMC permit requires a rainwater-harvesting percolation pit. | Amenity progress 0%; completion not independently verified | |
| Energy management | Details not supplied | RERA amenities | 0% recorded; not independently verified |
| Fire protection and fire safety | Systems and details not supplied | RERA amenities | 0% recorded; not independently verified |
| Electrical meter room / sub-station / receiving station | GHMC permit requires space for a transformer; further details are not supplied. | RERA amenities | 20% recorded; not independently verified |
| Recreational open space | Aggregate area not supplied | RERA amenities | 0% recorded; not independently verified |
7. Utilities, building services & safety
The RERA amenity filing lists water supply, sewerage, storm-water drains, sewage and sullage treatment/disposal, solid-waste management, rainwater harvesting, energy management, electrical facilities and fire protection. It does not provide the water source, storage or treatment capacity, STP capacity, reuse arrangements, electrical supply or backup capacity, lift details, or fire-system specifications. RERA amenities
The GHMC permit requires a garbage house within the premises and says an occupancy certificate is required before occupation. These are recorded permit conditions; the supplied material does not independently verify the installation or operation of these facilities.
8. Location, access & connectivity
The registered project location is Hayathnagar, Hyderabad, PIN 501505, on Survey No. 219. The permit records adjoining land to the north and east, a 40 ft wide road to the south and a 30 ft wide road to the west. RERA record RERA filing
Supplied location data gives these distances from the project’s cadastral parcel centroid; the method and source do not establish travel times or road-route distances:
| Nearby place | Recorded distance |
|---|---|
| Financial District (Nanakramguda) | 1.2 km |
| IndusInd Bank | 0.4 km |
| Unnamed bus station | 2.2 km |
| Manuu Polytechnic Hyderabad | 1.6 km |
| Sankaraya Eye Hospital | 1.6 km |
| ADP | 0.0 km |
| South India Shopping Mall | 2.6 km |
| Unnamed park | 1.2 km |
| Nanakramguda Govt primary school | 0.5 km |
Location record
9. Developer & development status
The registered promoter is MARAM INFRA PROJECTS PRIVATE LIMITED, identified as a company. The corporate identifier supplied is GSTIN 36AAHCM7638L1ZV. The promoter address in the project record is Vaishnavi Nest, beside Ikon Hospital, Information Colony, Hayathnagar, Hyderabad 501505. Corporate record Parties record
The TG-RERA record names Satish Kumar Maram as Managing Director and authorised signatory. The project’s Form-B affidavit is a promoter declaration that gives a completion undertaking of 28.12.2019 and other undertakings; it is not a completion certificate. Parties record
10. Approvals, official records & documents
| Identifier / date | P02500000056; issued 30/11/2018; valid through 28/12/2019 |
|---|---|
| What the supplied record establishes | Registration of MARAM R P HOMES and the stated validity period. |
| Identifier / date | Approval 1/C3/06363/2017; file 1/C3/05120/2017; 13 July 2017 |
|---|---|
| What the supplied record establishes | Permit extraction records Building A, residential, Cellar + Stilt + 5 floors, on Survey No. 219. |
| Identifier / date | 0008/GHMC/CBN/2021-OC; 25/06/2021 |
|---|---|
| What the supplied record establishes | Identified by the filed architect certificate as the building’s OC. |
| Identifier / date | 28/04/2025 |
|---|---|
| What the supplied record establishes | Certifies completion of the project in all aspects as described in the certificate. |
| Identifier / date | Completion undertaking: 28.12.2019 |
|---|---|
| What the supplied record establishes | Promoter-filed declaration and undertakings, including the stated completion date. |
| Identifier / date | Title report 3959; development agreement/GPA 3960 |
|---|---|
| What the supplied record establishes | Title investigation report and development-rights instrument are included in the supplied document record. |
| Identifier / date | 3955 |
|---|---|
| What the supplied record establishes | The supplied extraction contains no identifiable property schedule, search period or transaction rows; it does not establish a specific encumbrance result. |
1. Project at a glance
Project identity
Registered project name: MARAM R P HOMES
Project type: Residential apartment project
Phase / registered portion: Phase not separately identified in the supplied record; registration refers to the project.
TG-RERA registration: P02500000056
Registration validity: 30/11/2018–28/12/2019; no extension is recorded in the supplied certificate data. This is the registration period, not the occupancy-certificate status.
Registered promoter: MARAM INFRA PROJECTS PRIVATE LIMITED
RERA status: The project evidence labels it “On-Going Project”; the supplied registration certificate records the validity dates above.
Land and geographic identity
Locality: Hayathnagar
Revenue village: Hayathnagar; the building-permit extraction also describes the locality as Hayathnagar.
Mandal: Saroor Nagar Mandal in the GHMC building-permit extraction; the supplied registration certificate separately gives Saidabad. Mandal identity should be checked against the project’s revenue records.
District / PIN: Hyderabad / 501505
Project survey number(s): Survey No. 219; no subdivision is supplied.
Site extent: 4149.23 m² site area; 4149.23 m² net area; road-affected area recorded as 0 in the building-permit extraction.
Boundaries: North: neighbours’ land; South: 40 ft wide road; East: neighbours’ land; West: 30 ft wide road.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building approval: 1/C3/06363/2017, dated 13 July 2017; file no. 1/C3/05120/2017
Approved building: Building A, residential; Cellar + Stilt + 5 floors
Approved built-up area: 10,697.40 m² recorded as residential in the permit extraction; the RERA filing also records approved built-up area of 10,697.4 m².
Building count: One building / one block in the supplied project and unit records.
Approved versus RERA-declared units: The permit extraction does not state a unit count. TG-RERA unit data records 117 units.
Offering and status
RERA-filed configuration: 2BHK; 117 units
RERA-filed saleable area: 43.52 m² per unit
Booked / available: 0 booked / 117 available in the portal data; no as-of date is supplied, so counts are indicative rather than a current inventory confirmation.
Completion dates: Original and revised proposed completion: 28/12/2019
Occupancy certificate: The supplied RERA-filed architect certificate identifies GHMC OC 0008/GHMC/CBN/2021-OC, dated 25/06/2021, for the building.
Construction stage: A Form–1A architect certificate dated 28/04/2025 certifies project completion; this is a filed professional certificate, not an independent site inspection in the supplied evidence.
2. The project story
MARAM R P HOMES is a residential apartment development on Survey No. 219 in Hayathnagar, Hyderabad. The GHMC building-permit record describes one residential building, Building A, with a cellar, stilt and five floors, on a 4149.23 m² site.
The RERA-filed offer is 117 two-bedroom apartments. The portal records all 117 as available and none as booked, but supplies no date for that inventory snapshot. A Form–1A architect certificate dated 28/04/2025 certifies overall completion and cites the building’s GHMC occupancy certificate dated 25/06/2021. These are filed records; no independent site-progress verification is supplied here.
3. Master plan, architecture & building design
The GHMC permit records a 4149.23 m² site and net area, with 10,697.40 m² shown as residential and the building configuration recorded as Cellar + Stilt + 5 floors. It also lists a 366.92 m² “Tot-lot,” 2,758.24 m² cellar area and 2,218.20 m² stilt area. These are the permit extraction’s separate area labels; they should not be treated as interchangeable area measures.
The permit requires construction to follow the sanctioned plan and identifies a 14.5 m height in the extracted parameters. The supplied drawing records do not provide usable measured floor-plan geometry: five drawings are listed, with none measured and no flats extracted from them. Details such as flats per floor, building footprint, internal circulation, lifts, stairs, orientation and room layout therefore cannot be described from the available drawing-derived data.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 117 | 0 | 117 | 43.52 m² | Not available | Not supplied |
The 43.52 m² figure is the RERA-filed saleable area, not a measured carpet-area figure. No software-measured carpet area or room dimensions are available: the supplied floor-plan record reports five drawings, none measured.
5. Parking & vehicle circulation
The supplied evidence does not establish sanctioned parking counts, parking allocation by apartment, visitor or accessible parking, parking-bay locations, ramps, or vehicle circulation arrangements. The permit identifies cellar and stilt levels but does not, in the provided extraction, specify their parking use or capacity. A parking entitlement for an individual unit cannot be confirmed from these records.
6. Amenities, recreation & open spaces
TG-RERA amenity data marks the following items as available in the filing; the percentages are the reported progress values in that data, not independently verified completion:
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Community buildings | Size and facility details not supplied | 30% recorded; not independently verified | |
| Water supply | Source, storage and treatment details not supplied | 20% recorded; not independently verified | |
| Sewerage (chamber, lines, septic tank, STP) | Specific system and capacity not supplied | 20% recorded; not independently verified | |
| Internal roads and footpaths | Dimensions and materials not supplied | 0% recorded; not independently verified | |
| Green strip / tot-lot / park | GHMC permit lists a 366.92 m² “Tot-lot” and requires it to be fenced and maintained as greenery before OC; the amenity record gives no area for the green space. | Amenity progress 0%; completion not independently verified | |
| Storm-water drains | Details not supplied | 0% recorded; not independently verified | |
| Street lighting | Details not supplied | 0% recorded; not independently verified | |
| Sewage and sullage treatment/disposal | Facility details not supplied | 0% recorded; not independently verified | |
| Solid-waste management and disposal | Facility details not supplied | 0% recorded; not independently verified | |
| Water conservation / rainwater harvesting | GHMC permit requires a rainwater-harvesting percolation pit. | Amenity progress 0%; completion not independently verified | |
| Energy management | Details not supplied | 0% recorded; not independently verified | |
| Fire protection and fire safety | Systems and details not supplied | 0% recorded; not independently verified | |
| Electrical meter room / sub-station / receiving station | GHMC permit requires space for a transformer; further details are not supplied. | 20% recorded; not independently verified | |
| Recreational open space | Aggregate area not supplied | 0% recorded; not independently verified |
7. Utilities, building services & safety
The RERA amenity filing lists water supply, sewerage, storm-water drains, sewage and sullage treatment/disposal, solid-waste management, rainwater harvesting, energy management, electrical facilities and fire protection. It does not provide the water source, storage or treatment capacity, STP capacity, reuse arrangements, electrical supply or backup capacity, lift details, or fire-system specifications.
The GHMC permit requires a garbage house within the premises and says an occupancy certificate is required before occupation. These are recorded permit conditions; the supplied material does not independently verify the installation or operation of these facilities.
8. Location, access & connectivity
The registered project location is Hayathnagar, Hyderabad, PIN 501505, on Survey No. 219. The permit records adjoining land to the north and east, a 40 ft wide road to the south and a 30 ft wide road to the west.
Supplied location data gives these distances from the project’s cadastral parcel centroid; the method and source do not establish travel times or road-route distances:
Financial District (Nanakramguda): 1.2 km
IndusInd Bank: 0.4 km
Unnamed bus station: 2.2 km
Manuu Polytechnic Hyderabad: 1.6 km
Sankaraya Eye Hospital: 1.6 km
ADP: 0.0 km
South India Shopping Mall: 2.6 km
Unnamed park: 1.2 km
Nanakramguda Govt primary school: 0.5 km
9. Developer & development status
The registered promoter is MARAM INFRA PROJECTS PRIVATE LIMITED, identified as a company. The corporate identifier supplied is GSTIN 36AAHCM7638L1ZV. The promoter address in the project record is Vaishnavi Nest, beside Ikon Hospital, Information Colony, Hayathnagar, Hyderabad 501505.
The TG-RERA record names Satish Kumar Maram as Managing Director and authorised signatory. The project’s Form-B affidavit is a promoter declaration that gives a completion undertaking of 28.12.2019 and other undertakings; it is not a completion certificate.
10. Approvals, official records & documents
| Identifier / date | P02500000056; issued 30/11/2018; valid through 28/12/2019 |
|---|---|
| What the supplied record establishes | Registration of MARAM R P HOMES and the stated validity period. |
| Identifier / date | Approval 1/C3/06363/2017; file 1/C3/05120/2017; 13 July 2017 |
|---|---|
| What the supplied record establishes | Permit extraction records Building A, residential, Cellar + Stilt + 5 floors, on Survey No. 219. |
| Identifier / date | 0008/GHMC/CBN/2021-OC; 25/06/2021 |
|---|---|
| What the supplied record establishes | Identified by the filed architect certificate as the building’s OC. |
| Identifier / date | 28/04/2025 |
|---|---|
| What the supplied record establishes | Certifies completion of the project in all aspects as described in the certificate. |
| Identifier / date | Completion undertaking: 28.12.2019 |
|---|---|
| What the supplied record establishes | Promoter-filed declaration and undertakings, including the stated completion date. |
| Identifier / date | Title report 3959; development agreement/GPA 3960 |
|---|---|
| What the supplied record establishes | Title investigation report and development-rights instrument are included in the supplied document record. |
| Identifier / date | 3955 |
|---|---|
| What the supplied record establishes | The supplied extraction contains no identifiable property schedule, search period or transaction rows; it does not establish a specific encumbrance result. |
Frequently asked questions
Is MARAM R P HOMES registered with Telangana RERA?
Yes. MARAM R P HOMES is registered with the Telangana Real Estate Regulatory Authority as P02500000056; the registration status is On-Going Project.
Who is the developer of MARAM R P HOMES?
The promoter named in the RERA registration is MARAM INFRA PROJECTS PRIVATE LIMITED.
Where is MARAM R P HOMES located?
MARAM R P HOMES is in HAYATHNAGAR, Hyderabad, Telangana (501505).
When will MARAM R P HOMES be completed?
The promoter's proposed date of completion filed with RERA is 28/12/2019. This is the promoter's declaration, not a guarantee.