Platinum Township
BOMMANA TULASI DAS REDDY AND OTHERS · Rangareddy · RERA P02400010851
PLATINUM TOWNSHIP is a plotted residential development in Kulkulepally Village, Madgul Mandal, Ranga Reddy District, developed by registered promoter BOMMANA TULASI DAS REDDY AND OTHERS. The registered land area is 39,780.60 sq. m, and the DTCP draft-layout approval records 137 residential plots; tower or block and floor counts are not stated. TG-RERA registration number P02400010851 is stated as valid from 06/05/2023 to 06/05/2027, and the project header records proposed and revised completion as 06/09/2027.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | PLATINUM TOWNSHIP RERA record |
| Project type | Plotted development / residential layout RERA record |
| Phase or registered portion | Not separately identified in the supplied record; registration is for the project on Survey Nos. 42/P, 43/P and 44/P |
| TG-RERA registration | P02400010851, granted under section 5; registration certificate states validity from 06/05/2023 to 06/05/2027 |
| Registered promoter | BOMMANA TULASI DAS REDDY AND OTHERS RERA record |
| RERA status | On-Going Project RERA record |
| Registration validity | 06/05/2023–06/05/2027, as stated in the certificate; this is separate from the completion date |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / village names appearing in project records | Kulkulepally Village; the registration certificate also states Kolukulapally. The layout approval identifies Kulkulepally Gram Panchayat RERA record |
| Mandal | Madgul RERA record |
| District | Ranga Reddy / Rangareddy; the certificate states Ranga Reddy RERA record |
| PIN | 509327 RERA record |
| Survey numbers | 42/P, 43/P and 44/P RERA record |
| Registered site extent | The registration data records total and net land area as 39,780.60 sq. m RERA filing |
| Layout approval extent | The DTCP draft-layout document states Ac. 9-32.5 Guntas or Ac.9.83 Cents; 47,577.20 Sq. Yds |
| Boundaries in RERA filing | East: others’ land; West: 100 FEET WIDE ROAD; North: others’ land; South: others’ land RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Director of Town and Country Planning (DTCP); the draft-layout approval records delegation to Kulkulepally Gram Panchayat |
| Principal layout approval | Draft - TLP.No. 100/2023/H, dated 06-05-2023 Approvals record |
| Subsequent layout record | Grampanchayat Kulkulepally document GPA/ 01/2026, dated 04/05/2026, described as releasing DTCP draft-layout approvals Approvals record |
| Approved built-up area | The RERA land-details filing lists 23,305.85 sq. m as “Approved Built up Area”; the supplied material does not clarify the measurement basis for this plotted layout RERA filing |
| Plot count | 137 plots in the DTCP draft-layout approval |
| Buildings / floors | Not disclosed in the supplied project approval and RERA layout records. A plotted layout is recorded; no sanctioned building-floor configuration is supplied |
| Parking | The supplied approval extraction and RERA fields do not establish a sanctioned parking count or parking arrangement RERA filing |
Offering and status
| Field | Project record |
|---|---|
| Unit type | Residential plots; the DTCP draft-layout approval records a 137-plot residential layout |
| Plot sizes / RERA saleable area | Plot-by-plot sizes and RERA-filed saleable-area schedule are not included in the supplied structured data |
| Booked / available counts | Not supplied |
| Construction stage | RERA status is “On-Going Project”; independently verified site progress is not supplied RERA record |
| Completion date | The project header records proposed and revised completion as 06/09/2027 RERA record. A Form-B declaration dated 28th January, 2026 states completion by 06th May, 2027 |
| Occupancy / completion certificate | No occupancy certificate or completion certificate is included in the supplied material. The project is a plotted layout; the supplied record does not establish a phase- or plot-specific OC status Document index |
2. The project story
- PLATINUM TOWNSHIP is registered as a plotted residential development in Survey Nos. 42/P, 43/P and 44/P, at Kulkulepally Village, Madgul Mandal, Ranga Reddy District, PIN 509327. The registration certificate identifies the project as PLATINUM TOWNSHIP, registration P02400010851, and the project header records its status as ongoing. RERA record
- The DTCP document is titled Draft Technical Layout Pattern - Approved and records a residential layout of 137 plots. It allocates land to plots, roads and open space, and specifies development works including roads, drains, greenery, rainwater-harvesting pits, street lighting, electricity, sewerage disposal and protected water supply. These are approval requirements or listed works; the supplied evidence does not establish their completion.
- A later Grampanchayat Kulkulepally record dated 04/05/2026 is described as releasing the DTCP draft-layout approvals and records the mortgage and gift-settlement documents. This documents a layout-release record, not independently verified progress on the ground. No site inspection, construction-progress certificate, or completed-works evidence is supplied here.
3. Master plan, architecture & building design
The project’s supplied design evidence concerns a plotted layout rather than apartment or tower plans. The DTCP draft-layout approval describes 137 plots across Ac. 9-32.5 Guntas or Ac.9.83 Cents; 47,577.20 Sq. Yds, with the following land-use allocation:
| Layout component | Approved figure in DTCP draft-layout record |
|---|---|
| Layout area | Ac. 9.83 Cents; 47,577.20 Sq. Yds |
| Plotted area | 58.59%; Ac. 5.759 Cents; 27,873.56 Sq. Yds |
| Road area | 31.41%; Ac. 3.088 Cents; 14,945.92 Sq. Yds |
| Open space | 10.00%; Ac. 0.983 Cents; 4,757.72 Sq. Yds |
| Mortgage area | 15.40%; Ac. 0.887 Cents; 4,293.08 Sq. Yds |
The approval identifies the layout as residential and states that only detached dwelling houses designed for one family may be built on a site; it also says shops, business premises and industrial units are not allowed except at sites specially reserved for them in the draft layout. The supplied extraction does not identify any specially reserved commercial sites or provide a plot-by-plot plan.
The registration filing lists 23,305.85 sq. m as approved built-up area, but the supplied materials do not define its measurement basis or provide building drawings to explain it. No building count, building footprints, floor configuration, tower heights, internal plot-size schedule, or phase-wise layout plan is available in the supplied data. The two drawing records listed for floor-plan review are scans pending measurement, so no software-measured carpet areas or drawing-derived dimensions are available. RERA filing Floor plans
4. Homes, configurations & floor plans
This is a plotted project, not an apartment configuration schedule. The DTCP draft-layout approval records 137 residential plots, but the supplied RERA data does not provide plot-wise sizes, booked or available counts, or a RERA-filed saleable-area schedule.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | 137 in the DTCP draft-layout approval | Not supplied | Not supplied | Plot-wise schedule not supplied | Not applicable / not supplied | Not supplied |
The plot-size descriptions appearing in the third-party vendor record are not used to establish the RERA-filed offering. The supplied drawing review reports 2 drawings, with 0 measured and 2 scans pending; therefore no drawing-based plot or room measurements are available. Promoter website Floor plans
5. Parking & vehicle circulation
No parking-space count, visitor or accessible parking provision, parking layout, or plot-specific parking allocation is established by the supplied RERA filing or approval extraction. The DTCP draft-layout approval refers to roads and requires roads to be opened for access to neighbouring sites, but the supplied material does not describe a separate vehicle-circulation plan or pedestrian separation. RERA filing
The approval identifies plots 67 to 87 as the plots to be mortgaged to the Gram Panchayat, measuring Ac.0.887 cents or 4293.08 Sq. Yards. This is a layout-development security requirement, not evidence of parking allocation.
6. Amenities, recreation & open spaces
The following records describe facilities as approval requirements or RERA-filed amenity entries. The supplied data does not establish that they are completed or independently verified.
| Description / size | 10.00%; Ac. 0.983 Cents; 4,757.72 Sq. Yds in the DTCP draft-layout record |
|---|---|
| Declared progress / verified status | Layout allocation recorded; completion or handover status not independently verified |
| Description / size | Listed as available in the RERA amenities data; approval also specifies road works and access to neighbouring sites |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity entry; progress field is 0; completion not verified |
| Description / size | Listed in RERA amenities; approval calls for greenery including avenue plantation and fencing of open spaces |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity entry; progress field is 0; completion not verified |
| Description / size | Listed in RERA amenities; also specified in the layout approval |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress field is 0; completion not verified |
| Description / size | Listed in RERA amenities |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress field is 0; no description, size or completion evidence supplied |
| Description / size | RERA amenity entry; approval specifies rainwater-harvesting pits |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | Progress field is 0; completion not verified |
No clubhouse, indoor recreation facility, sports facility, or facility capacity is established in the supplied project records.
7. Utilities, building services & safety
The layout approval lists infrastructure works including sub-surface, curbstones, metalling of the carriage-way, side drains, construction of drains and channelization of nalas, rainwater-harvesting pits, street lighting and electricity facilities, a sewerage-disposal system, and protected water supply. These are listed works in the approval; the supplied material does not verify installation, capacity, or completion.
RERA amenity entries also list water supply; sewerage (chambers, lines, septic tank, STP); storm-water drains; treatment and disposal of sewage and sullage water; solid-waste management and disposal; energy management; fire protection and fire-safety requirements; and an electrical meter room, sub-station and receiving station. The amenity progress fields are 0 where provided, and no system capacities, fire-clearance documents, or completed-service evidence are supplied. RERA amenities
No project-specific evidence is supplied for water storage or treatment capacity, sewerage-treatment capacity or reuse, electrical backup, EV charging, access control, CCTV, accessible circulation or fire-system installation. The supplied vendor record lists several services, but it is not a RERA project document and does not establish their approval or delivery. Promoter website
8. Location, access & connectivity
The registered project location is Kulkulepally Village / Kolukulapally, Madgul Mandal, Ranga Reddy District, Telangana, PIN 509327, on Survey Nos. 42/P, 43/P and 44/P. The RERA filing records a 100 FEET WIDE ROAD on the western boundary; the DTCP draft-layout approval also requires layout roads to be opened for access to neighbouring sites. RERA record RERA filing
The supplied location record gives a geocoded point in Madgul and reports the nearest sampled Outer Ring Road interchange at approximately 45.8 km. This is a recorded sampled distance; no further public-transport, landmark, route or travel-time information is supplied. Location record
9. Developer & development status
- The registered promoter is BOMMANA TULASI DAS REDDY AND OTHERS. The RERA filing identifies the organization type as “Others” and describes it as “Partners”; a more specific registered legal-entity type, corporate registration number, official project contact details, or official website is not established in the supplied data. RERA record RERA filing Corporate record
- A Form-B affidavit dated 28th January, 2026, made through authorized signatory Bommana Tulasi Das Reddy for Sri. BOMMANA TULASI DAS REDDY AND 5 OTHERS, declares a completion date of 06th May, 2027 and includes undertakings concerning project funds, audits and pending approvals. The project header separately records proposed and revised completion as 06/09/2027. These are the completion dates stated in their respective RERA records; neither is the registration-validity period. RERA record
- The RERA status is “On-Going Project,” but no independently verified construction-progress figure or site-stage report is supplied. No occupancy or completion certificate is included in the supplied documents. RERA record Document index
10. Approvals, official records & documents
| Identifier / date | P02400010851; valid 06/05/2023–06/05/2027; issued 16/05/2026 |
|---|---|
| What the supplied record establishes | Form C certificate for PLATINUM TOWNSHIP, registered under section 5; covers Survey Nos. 42/P, 43/P and 44/P |
| Identifier / date | Draft - TLP.No. 100/2023/H; 06-05-2023; file Lr.Roc.No.12705/1801/2023/H/e-Panchayat |
|---|---|
| What the supplied record establishes | Draft Technical Layout Pattern approval for a 137-plot residential layout; includes land-use allocation and layout-development conditions |
| Identifier / date | 100/2023/H |
|---|---|
| What the supplied record establishes | Supplied OCR fragment identifies the Gram Panchayat, Madgul Mandal and R.R. District but does not establish readable approval terms |
| Identifier / date | GPA/ 01/2026; 04/05/2026 |
|---|---|
| What the supplied record establishes | Described as releasing DTCP draft-layout approvals; records the open-space and road gift settlement and mortgage documents |
| Identifier / date | Dated 28th January, 2026 |
|---|---|
| What the supplied record establishes | Promoter declaration on title basis, completion undertaking and project-related undertakings; the printed encumbrance alternative does not contain filled-in details |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No such certificate is established by the materials reviewed Document index |
The supplied approval material includes the DTCP draft-layout conditions, while the later Gram Panchayat record identifies registered mortgage document 14568/2025 and gift-settlement document 14567/2025. No building-specific commencement certificate, plot-wise plan schedule, or occupancy/completion certificate is included in the supplied overview evidence. Document index
1. Project at a glance
Project identity
Registered project name: PLATINUM TOWNSHIP
Project type: Plotted development / residential layout
Phase or registered portion: Not separately identified in the supplied record; registration is for the project on Survey Nos. 42/P, 43/P and 44/P
TG-RERA registration: P02400010851, granted under section 5; registration certificate states validity from 06/05/2023 to 06/05/2027
Registered promoter: BOMMANA TULASI DAS REDDY AND OTHERS
RERA status: On-Going Project
Registration validity: 06/05/2023–06/05/2027, as stated in the certificate; this is separate from the completion date
Land and geographic identity
Locality / village names appearing in project records: Kulkulepally Village; the registration certificate also states Kolukulapally. The layout approval identifies Kulkulepally Gram Panchayat
Mandal: Madgul
District: Ranga Reddy / Rangareddy; the certificate states Ranga Reddy
PIN: 509327
Survey numbers: 42/P, 43/P and 44/P
Registered site extent: The registration data records total and net land area as 39,780.60 sq. m
Layout approval extent: The DTCP draft-layout document states Ac. 9-32.5 Guntas or Ac.9.83 Cents; 47,577.20 Sq. Yds
Boundaries in RERA filing: East: others’ land; West: 100 FEET WIDE ROAD; North: others’ land; South: others’ land
Development identity
Sanctioning authority: Director of Town and Country Planning (DTCP); the draft-layout approval records delegation to Kulkulepally Gram Panchayat
Principal layout approval: Draft - TLP.No. 100/2023/H, dated 06-05-2023
Subsequent layout record: Grampanchayat Kulkulepally document GPA/ 01/2026, dated 04/05/2026, described as releasing DTCP draft-layout approvals
Approved built-up area: The RERA land-details filing lists 23,305.85 sq. m as “Approved Built up Area”; the supplied material does not clarify the measurement basis for this plotted layout
Plot count: 137 plots in the DTCP draft-layout approval
Buildings / floors: Not disclosed in the supplied project approval and RERA layout records. A plotted layout is recorded; no sanctioned building-floor configuration is supplied
Parking: The supplied approval extraction and RERA fields do not establish a sanctioned parking count or parking arrangement
Offering and status
Unit type: Residential plots; the DTCP draft-layout approval records a 137-plot residential layout
Plot sizes / RERA saleable area: Plot-by-plot sizes and RERA-filed saleable-area schedule are not included in the supplied structured data
Booked / available counts: Not supplied
Construction stage: RERA status is “On-Going Project”; independently verified site progress is not supplied
Completion date: The project header records proposed and revised completion as 06/09/2027. A Form-B declaration dated 28th January, 2026 states completion by 06th May, 2027
Occupancy / completion certificate: No occupancy certificate or completion certificate is included in the supplied material. The project is a plotted layout; the supplied record does not establish a phase- or plot-specific OC status
2. The project story
- PLATINUM TOWNSHIP is registered as a plotted residential development in Survey Nos. 42/P, 43/P and 44/P, at Kulkulepally Village, Madgul Mandal, Ranga Reddy District, PIN 509327. The registration certificate identifies the project as PLATINUM TOWNSHIP, registration P02400010851, and the project header records its status as ongoing.
- The DTCP document is titled Draft Technical Layout Pattern - Approved and records a residential layout of 137 plots. It allocates land to plots, roads and open space, and specifies development works including roads, drains, greenery, rainwater-harvesting pits, street lighting, electricity, sewerage disposal and protected water supply. These are approval requirements or listed works; the supplied evidence does not establish their completion.
- A later Grampanchayat Kulkulepally record dated 04/05/2026 is described as releasing the DTCP draft-layout approvals and records the mortgage and gift-settlement documents. This documents a layout-release record, not independently verified progress on the ground. No site inspection, construction-progress certificate, or completed-works evidence is supplied here.
3. Master plan, architecture & building design
The project’s supplied design evidence concerns a plotted layout rather than apartment or tower plans. The DTCP draft-layout approval describes 137 plots across Ac. 9-32.5 Guntas or Ac.9.83 Cents; 47,577.20 Sq. Yds, with the following land-use allocation:
Layout area: Ac. 9.83 Cents; 47,577.20 Sq. Yds
Plotted area: 58.59%; Ac. 5.759 Cents; 27,873.56 Sq. Yds
Road area: 31.41%; Ac. 3.088 Cents; 14,945.92 Sq. Yds
Open space: 10.00%; Ac. 0.983 Cents; 4,757.72 Sq. Yds
Mortgage area: 15.40%; Ac. 0.887 Cents; 4,293.08 Sq. Yds
The approval identifies the layout as residential and states that only detached dwelling houses designed for one family may be built on a site; it also says shops, business premises and industrial units are not allowed except at sites specially reserved for them in the draft layout. The supplied extraction does not identify any specially reserved commercial sites or provide a plot-by-plot plan.
The registration filing lists 23,305.85 sq. m as approved built-up area, but the supplied materials do not define its measurement basis or provide building drawings to explain it. No building count, building footprints, floor configuration, tower heights, internal plot-size schedule, or phase-wise layout plan is available in the supplied data. The two drawing records listed for floor-plan review are scans pending measurement, so no software-measured carpet areas or drawing-derived dimensions are available.
4. Homes, configurations & floor plans
This is a plotted project, not an apartment configuration schedule. The DTCP draft-layout approval records 137 residential plots, but the supplied RERA data does not provide plot-wise sizes, booked or available counts, or a RERA-filed saleable-area schedule.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Residential plots | 137 in the DTCP draft-layout approval | Not supplied | Not supplied | Plot-wise schedule not supplied | Not applicable / not supplied | Not supplied |
The plot-size descriptions appearing in the third-party vendor record are not used to establish the RERA-filed offering. The supplied drawing review reports 2 drawings, with 0 measured and 2 scans pending; therefore no drawing-based plot or room measurements are available.
5. Parking & vehicle circulation
No parking-space count, visitor or accessible parking provision, parking layout, or plot-specific parking allocation is established by the supplied RERA filing or approval extraction. The DTCP draft-layout approval refers to roads and requires roads to be opened for access to neighbouring sites, but the supplied material does not describe a separate vehicle-circulation plan or pedestrian separation.
The approval identifies plots 67 to 87 as the plots to be mortgaged to the Gram Panchayat, measuring Ac.0.887 cents or 4293.08 Sq. Yards. This is a layout-development security requirement, not evidence of parking allocation.
6. Amenities, recreation & open spaces
The following records describe facilities as approval requirements or RERA-filed amenity entries. The supplied data does not establish that they are completed or independently verified.
| Description / size | 10.00%; Ac. 0.983 Cents; 4,757.72 Sq. Yds in the DTCP draft-layout record |
|---|---|
| Declared progress / verified status | Layout allocation recorded; completion or handover status not independently verified |
| Description / size | Listed as available in the RERA amenities data; approval also specifies road works and access to neighbouring sites |
|---|---|
| Declared progress / verified status | RERA amenity entry; progress field is 0; completion not verified |
| Description / size | Listed in RERA amenities; approval calls for greenery including avenue plantation and fencing of open spaces |
|---|---|
| Declared progress / verified status | RERA amenity entry; progress field is 0; completion not verified |
| Description / size | Listed in RERA amenities; also specified in the layout approval |
|---|---|
| Declared progress / verified status | Progress field is 0; completion not verified |
| Description / size | Listed in RERA amenities |
|---|---|
| Declared progress / verified status | Progress field is 0; no description, size or completion evidence supplied |
| Description / size | RERA amenity entry; approval specifies rainwater-harvesting pits |
|---|---|
| Declared progress / verified status | Progress field is 0; completion not verified |
No clubhouse, indoor recreation facility, sports facility, or facility capacity is established in the supplied project records.
7. Utilities, building services & safety
The layout approval lists infrastructure works including sub-surface, curbstones, metalling of the carriage-way, side drains, construction of drains and channelization of nalas, rainwater-harvesting pits, street lighting and electricity facilities, a sewerage-disposal system, and protected water supply. These are listed works in the approval; the supplied material does not verify installation, capacity, or completion.
RERA amenity entries also list water supply; sewerage (chambers, lines, septic tank, STP); storm-water drains; treatment and disposal of sewage and sullage water; solid-waste management and disposal; energy management; fire protection and fire-safety requirements; and an electrical meter room, sub-station and receiving station. The amenity progress fields are 0 where provided, and no system capacities, fire-clearance documents, or completed-service evidence are supplied.
No project-specific evidence is supplied for water storage or treatment capacity, sewerage-treatment capacity or reuse, electrical backup, EV charging, access control, CCTV, accessible circulation or fire-system installation. The supplied vendor record lists several services, but it is not a RERA project document and does not establish their approval or delivery.
8. Location, access & connectivity
The registered project location is Kulkulepally Village / Kolukulapally, Madgul Mandal, Ranga Reddy District, Telangana, PIN 509327, on Survey Nos. 42/P, 43/P and 44/P. The RERA filing records a 100 FEET WIDE ROAD on the western boundary; the DTCP draft-layout approval also requires layout roads to be opened for access to neighbouring sites.
The supplied location record gives a geocoded point in Madgul and reports the nearest sampled Outer Ring Road interchange at approximately 45.8 km. This is a recorded sampled distance; no further public-transport, landmark, route or travel-time information is supplied.
9. Developer & development status
- The registered promoter is BOMMANA TULASI DAS REDDY AND OTHERS. The RERA filing identifies the organization type as “Others” and describes it as “Partners”; a more specific registered legal-entity type, corporate registration number, official project contact details, or official website is not established in the supplied data.
- A Form-B affidavit dated 28th January, 2026, made through authorized signatory Bommana Tulasi Das Reddy for Sri. BOMMANA TULASI DAS REDDY AND 5 OTHERS, declares a completion date of 06th May, 2027 and includes undertakings concerning project funds, audits and pending approvals. The project header separately records proposed and revised completion as 06/09/2027. These are the completion dates stated in their respective RERA records; neither is the registration-validity period.
- The RERA status is “On-Going Project,” but no independently verified construction-progress figure or site-stage report is supplied. No occupancy or completion certificate is included in the supplied documents.
10. Approvals, official records & documents
| Identifier / date | P02400010851; valid 06/05/2023–06/05/2027; issued 16/05/2026 |
|---|---|
| What the supplied record establishes | Form C certificate for PLATINUM TOWNSHIP, registered under section 5; covers Survey Nos. 42/P, 43/P and 44/P |
| Identifier / date | Draft - TLP.No. 100/2023/H; 06-05-2023; file Lr.Roc.No.12705/1801/2023/H/e-Panchayat |
|---|---|
| What the supplied record establishes | Draft Technical Layout Pattern approval for a 137-plot residential layout; includes land-use allocation and layout-development conditions |
| Identifier / date | 100/2023/H |
|---|---|
| What the supplied record establishes | Supplied OCR fragment identifies the Gram Panchayat, Madgul Mandal and R.R. District but does not establish readable approval terms |
| Identifier / date | GPA/ 01/2026; 04/05/2026 |
|---|---|
| What the supplied record establishes | Described as releasing DTCP draft-layout approvals; records the open-space and road gift settlement and mortgage documents |
| Identifier / date | Dated 28th January, 2026 |
|---|---|
| What the supplied record establishes | Promoter declaration on title basis, completion undertaking and project-related undertakings; the printed encumbrance alternative does not contain filled-in details |
| Identifier / date | Not supplied |
|---|---|
| What the supplied record establishes | No such certificate is established by the materials reviewed |
The supplied approval material includes the DTCP draft-layout conditions, while the later Gram Panchayat record identifies registered mortgage document 14568/2025 and gift-settlement document 14567/2025. No building-specific commencement certificate, plot-wise plan schedule, or occupancy/completion certificate is included in the supplied overview evidence.
Frequently asked questions
Is PLATINUM TOWNSHIP registered with Telangana RERA?
Yes. PLATINUM TOWNSHIP is registered with the Telangana Real Estate Regulatory Authority as P02400010851; the registration status is On-Going Project.
Who is the developer of PLATINUM TOWNSHIP?
The promoter named in the RERA registration is BOMMANA TULASI DAS REDDY AND OTHERS.
Where is PLATINUM TOWNSHIP located?
PLATINUM TOWNSHIP is in Kulkulepally Village, Kolukulapally, Madgul, Rangareddy, Telangana (509327).
When will PLATINUM TOWNSHIP be completed?
The promoter's proposed date of completion filed with RERA is 06/09/2027. This is the promoter's declaration, not a guarantee.
More projects in Madgul