Aashritha Pride
TANMAY CONSTRUCTIONS · Hyderabad · RERA P02500002013
AASHRITHA PRIDE is a residential apartment project in Gayatri Nagar, Quthbullapur, Hyderabad. It is being developed by registered promoter TANMAY CONSTRUCTIONS on a site of 589.63 sq. m., with one building and 1 Stilt + 5 upper floors. The RERA-listed offering comprises 15 apartments: 10 2BHK and five 3BHK. Its TG-RERA registration is P02500002013, and its proposed completion date is 03/04/2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
7 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Record |
|---|---|
| Registered project name | AASHRITHA PRIDE RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | Phase not separately identified in the supplied record. The registration is for the project; the building permit identifies Building A. RERA record |
| TG-RERA registration | P02500002013 RERA record |
| Registration validity | 06/07/2020 to 03/04/2025; the supplied certificate states four years and is not marked extended. This is registration validity, not an occupancy certificate or a completion confirmation. RERA record |
| Registered promoter | TANMAY CONSTRUCTIONS, partnership RERA record RERA filing |
| RERA status | Listed as On-Going Project in the project information. The record gives a proposed/revised completion date of 03/04/2025; it does not establish current construction status. RERA filing RERA record |
Land and geographic identity
| Item | Record |
|---|---|
| Locality | Gayatri Nagar RERA record |
| Revenue village | Jeedimetla is stated in the building permit and title documents; the RERA identity fields separately state Gayatri Nagar as the village. The supplied information does not resolve whether these labels refer to the same revenue-village identity. Land records |
| Mandal | Quthbullapur in the building permit; not disclosed in the project’s land identity fields. Land records |
| District | Hyderabad in the RERA project identity; Medchal-Malkajgiri in the building permit. RERA record |
| PIN | 500097 RERA record |
| Survey number(s) | Survey No. 123; no subdivision is supplied. RERA record Land records |
| Registered site extent | 589.63 sq. m. RERA filing |
| Total / net area | Total area 589.63 sq. m.; net area 589.63 sq. m. RERA filing |
| Recorded road-affected / nala area | Project fields record 0 sq. m. affected in road widening/FTL/nala widening; the permit records road-affected area 0 sq. m. and nala-affected area 0 sq. m. RERA filing |
| Boundaries | East: “ROAD WIDTH 12”; west, north and south: “NEIGHBOURS LAND.” RERA filing |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) Approvals record |
| Principal approval | Building Permit Order 2/C23/05551/2019, approved 03 April 2019. The permit also records file no. 2/KP/17905/2018. Approvals record |
| Approved built-up area | The RERA project fields state approved built-up area 1,611.33 sq. m. The permit separately lists residential upper-floors area 1,342.75 m² and stilt area 256.72 m²; these are distinct figures as recorded. RERA filing |
| Building count | One building; the permit names Building A (Residential Flats). RERA filing |
| Sanctioned floor configuration | 1 Stilt + 5 upper floors; permit-stated height 14.99 m. No basement or podium is recorded. |
| Parking levels | The permit says the approved cellar and stilts are for vehicle parking, but the extracted floor configuration records one stilt and does not establish a parking-space count or a cellar level. |
| Unit count | GHMC permit: sanctioned unit total not stated in the supplied extraction. RERA project fields: one “building unit” and one “proposed building unit” (these fields do not give the apartment count). The RERA unit record lists 15 apartments. RERA filing RERA unit table |
Offering and status
| Item | Record |
|---|---|
| RERA-listed configurations | 2BHK: 10 units; 3BHK: 5 units. RERA unit table |
| RERA-filed saleable area | 2BHK: 86.44–86.48 sq. m.; 3BHK: 95.77 sq. m. RERA unit table |
| Booked / available | Portal-derived unit record shows 0 booked and 15 available (2BHK: 0/10 booked, 10 available; 3BHK: 0/5 booked, 5 available). The record has no as-of date, so treat these counts as indicative. RERA unit table |
| Construction stage | No verified current stage or site-progress measurement is supplied. The permit is an approval record; it does not establish construction completion. RERA amenities |
| Completion dates | Project fields show proposed and revised proposed completion as 03/04/2025. Form B separately records the promoter’s completion undertaking as 04/03/2025. RERA filing |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents. The permit requires a completion notice and occupancy certificate before occupation. |
2. The project story
- AASHRITHA PRIDE is recorded with TG-RERA as a residential apartment project in Gayatri Nagar, Hyderabad, on Survey No. 123. Its RERA-listed offering comprises 15 apartments—10 two-bedroom units and five three-bedroom units—in a single building. The GHMC building-permit extraction identifies that building as Building A, with one stilt and five upper floors. RERA record Land records RERA unit table
- The project record does not establish how much construction has been completed, whether any apartments have been handed over, or whether the building has an occupancy certificate. The portal-derived booking figures show all 15 units as available and none as booked, but they have no as-of date and should be treated as indicative rather than a current sales statement. RERA unit table Document index
- The permit contains design and site conditions, including rainwater-harvesting structures, transformer space, a garbage house and an ETP. These are approval requirements or recorded provisions, not evidence that the facilities have been installed or commissioned.
3. Master plan, architecture & building design
- The project’s RERA land record identifies a single site of 589.63 sq. m. in Survey No. 123, with recorded net area also 589.63 sq. m. The GHMC permit extraction identifies one residential building, Building A, with 1 stilt + 5 upper floors and a stated height of 14.99 m. No basement, podium, multi-building arrangement or separate phase organization is established in the supplied material. RERA filing
- The RERA fields state an approved built-up area of 1,611.33 sq. m. The permit’s extracted parameters separately report 1,342.75 m² for residential upper floors and 256.72 m² for the stilt. These figures are presented as recorded; the available extraction does not provide a drawing-based area schedule explaining their relationship. RERA filing
- The permit records 10 rainwater-harvesting structures and 25 trees, and requires a periphery strip of greenery. The supplied drawing and permit extracts do not establish flats per floor, lift or stair configuration, entrances, exits, internal circulation, open-space dimensions, or the residential/common-area distribution.
4. Homes, configurations & floor plans
- The RERA unit record lists 10 2BHK apartments and five 3BHK apartments. It reports saleable areas separately from drawing-measured carpet areas. The carpet figures below are software measurements from the approved floor-plan drawing record, not RERA-filed area disclosures; they need drawing review. Saleable area includes the home’s share of common areas, while carpet area is a different measurement. RERA unit table RERA unit details Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 86.44–86.48 sq. m. | 58.1–68.0 sq. m.; median 63.1 sq. m. (software-measured) | 27% |
| 3BHK | 5 | 0 | 5 | 95.77 sq. m. | Not supplied for this RERA-listed configuration | Not supplied |
- For one measured 2BHK drawing, the room schedule identifies a living room, dining area, kitchen, two bedrooms and a toilet, as well as two balconies. The drawing extraction gives dimensions for the listed enclosed rooms; balconies are excluded from the measured carpet area. These room details describe one measured drawing, not every unit. RERA unit details
- The drawing-measurement data also contains a 6BHK configuration, but the RERA unit record does not list it as a project offering; it is therefore not included as a purchasable RERA-listed configuration here. RERA unit details Floor plans
5. Parking & vehicle circulation
- The GHMC permit states that the cellar and stilt approved for parking are to be used exclusively for vehicle parking, without partition walls or rolling shutters. The extracted building configuration identifies one stilt; it does not establish a cellar level, the number or type of parking spaces, visitor or accessible spaces, parking allocation to individual units, or EV provision.
- Although the permit describes parking use, the supplied records do not establish actual construction or a buyer’s exclusive entitlement to a particular bay. Obtain the sanctioned parking plan and the relevant sale/allotment documents to confirm any unit-specific arrangement. Document index
6. Amenities, recreation & open spaces
- The RERA amenities record names project infrastructure and safety-related items, with recorded progress percentages. A percentage of 0 or 30 is a portal entry, not independent confirmation of construction or operation. The GHMC permit records certain site provisions and requirements; neither source establishes independently verified completion. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads and footpaths | No size stated | RERA amenities record | Listed “YES”; 0%. Not independently verified. RERA amenities |
| Green strip / tot-lot / park | No area stated; the permit also requires a periphery greenery strip | RERA amenities record; GHMC permit | Listed “YES”; 0%. Not independently verified. RERA amenities |
| Community buildings | No description or size stated | RERA amenities record | Progress 0%; not independently verified. RERA amenities |
| Street lighting | No quantity stated | RERA amenities record | Listed “YES”; 0%. Not independently verified. RERA amenities |
- The promoter-vendor material mentions facilities such as a swimming pool, clubhouse, gym, landscaped gardens and indoor play areas, but these are not established in the supplied RERA amenity record or permit extraction as sanctioned or delivered project facilities. They are not treated here as confirmed project provisions. Promoter website RERA amenities
7. Utilities, building services & safety
- The RERA amenities record lists water supply, sewerage, storm-water drains, sewage and sullage treatment/disposal, solid-waste management, rainwater harvesting, energy management, fire protection and safety, and electrical meter room/substation/receiving station. It records water supply at 30% and the other listed service-progress entries at 0%; these are declared portal figures, not independent verification of works or operational service. RERA amenities
- The GHMC permit records 10 rainwater-harvesting structures, space for a transformer, a garbage house and an ETP. It also requires sanitation, plumbing, fire-safety requirements, lifts and electrical installations to be executed under qualified technical supervision. The supplied extracts do not state water source or storage capacity, treatment capacity, backup-power provision, lift count or capacity, detailed fire systems, CCTV, access control, or accessibility arrangements.
- The permit requires an occupancy certificate before occupation and requires a completion notice after construction. No occupancy/completion certificate is supplied in the reviewed project documents; no completed or commissioned status is established here. Document index
8. Location, access & connectivity
- The registered project location is Gayatri Nagar, Hyderabad, Telangana 500097. The permit describes the site as being in Jeedimetla, Quthbullapur, Medchal-Malkajgiri, at Survey No. 123; the project fields separately state village Gayatri Nagar and district Hyderabad. These are the location identifiers provided in the records. RERA record Land records
- The RERA land record lists the eastern boundary as “ROAD WIDTH 12,” with neighbouring land to the north, south and west. The GHMC permit also references an 18-metre road condition. The supplied extracts do not identify a named approach road, public-transport service, or measured distances to local landmarks. RERA filing
9. Developer & development status
- The registered legal promoter is TANMAY CONSTRUCTIONS, recorded as a partnership. The project record lists Chennupati Sarath Kumar, Gantu Srinivasa Rao and Punukollu Jaya Chandra as partners, and Mynani Ravi Kumar as authorized signatory. The supplied records do not provide a verified promoter registration number or official website/contact details. RERA filing Parties record
- The Form B affidavit-cum-declaration was signed by Mynani Ravi Kumar as authorized signatory and dated 18/2/2020. It contains the promoter’s statements about title and encumbrances, the RERA separate-account arrangements and an undertaking to complete by 04/03/2025; these are promoter declarations, not independent verification of present title, account operation or construction status.
- The RERA project fields show 03/04/2025 as both the proposed and revised proposed completion date, while the registration certificate states validity through 03/04/2025. The supplied record does not establish a subsequent extension, current construction progress or an occupancy certificate. RERA filing Document index
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form C certificate for AASHRITHA PRIDE, registration P02500002013, issued 06/07/2020; stated validity 06/07/2020–03/04/2025. The certificate is not marked extended. |
| Principal building approval | GHMC Building Permit Order 2/C23/05551/2019, approved 03 April 2019; file no. 2/KP/17905/2018. The extraction identifies Building A, residential flats, at Survey No. 123. Approvals record |
| Building and commencement record | The RERA document register includes “Commencement Certificates for each building in each phase”; the supplied extracted document is a GHMC Building Permit Order. No separate commencement notice or certificate is identified in the supplied material. Document index |
| Approved-plan evidence | A layout-plan item is listed in the RERA document register, but its contents were not extracted. The permit extraction supplies selected building and site parameters. Document index |
| Completion / occupancy evidence | No completion or occupancy certificate is included in the supplied project documents. Document index |
| Promoter declaration | Form B affidavit-cum-declaration by TANMAY CONSTRUCTIONS’ authorized signatory, dated 18/2/2020. |
| Title / development records in project file | The RERA document list includes a title search report and title documents, including a 2018 sale deed and a 2019 development agreement-cum-GPA. Their detailed title implications are addressed in the Land & Title section. Document index |
- The available plan item is not extractable in the supplied record, and the reviewed material does not include a completion/occupancy certificate or a current site-progress verification. Those limits mean the overview can describe the registered offering and permit-recorded design, but cannot confirm present construction or facility completion. Document index
1. Project at a glance
Project identity
Registered project name: AASHRITHA PRIDE
Project type: Residential apartment project
Phase / registered portion: Phase not separately identified in the supplied record. The registration is for the project; the building permit identifies Building A.
TG-RERA registration: P02500002013
Registration validity: 06/07/2020 to 03/04/2025; the supplied certificate states four years and is not marked extended. This is registration validity, not an occupancy certificate or a completion confirmation.
Registered promoter: TANMAY CONSTRUCTIONS, partnership
RERA status: Listed as On-Going Project in the project information. The record gives a proposed/revised completion date of 03/04/2025; it does not establish current construction status.
Land and geographic identity
Locality: Gayatri Nagar
Revenue village: Jeedimetla is stated in the building permit and title documents; the RERA identity fields separately state Gayatri Nagar as the village. The supplied information does not resolve whether these labels refer to the same revenue-village identity.
Mandal: Quthbullapur in the building permit; not disclosed in the project’s land identity fields.
District: Hyderabad in the RERA project identity; Medchal-Malkajgiri in the building permit.
PIN: 500097
Survey number(s): Survey No. 123; no subdivision is supplied.
Registered site extent: 589.63 sq. m.
Total / net area: Total area 589.63 sq. m.; net area 589.63 sq. m.
Recorded road-affected / nala area: Project fields record 0 sq. m. affected in road widening/FTL/nala widening; the permit records road-affected area 0 sq. m. and nala-affected area 0 sq. m.
Boundaries: East: “ROAD WIDTH 12”; west, north and south: “NEIGHBOURS LAND.”
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal approval: Building Permit Order 2/C23/05551/2019, approved 03 April 2019. The permit also records file no. 2/KP/17905/2018.
Approved built-up area: The RERA project fields state approved built-up area 1,611.33 sq. m. The permit separately lists residential upper-floors area 1,342.75 m² and stilt area 256.72 m²; these are distinct figures as recorded.
Building count: One building; the permit names Building A (Residential Flats).
Sanctioned floor configuration: 1 Stilt + 5 upper floors; permit-stated height 14.99 m. No basement or podium is recorded.
Parking levels: The permit says the approved cellar and stilts are for vehicle parking, but the extracted floor configuration records one stilt and does not establish a parking-space count or a cellar level.
Unit count: GHMC permit: sanctioned unit total not stated in the supplied extraction. RERA project fields: one “building unit” and one “proposed building unit” (these fields do not give the apartment count). The RERA unit record lists 15 apartments.
Offering and status
RERA-listed configurations: 2BHK: 10 units; 3BHK: 5 units.
RERA-filed saleable area: 2BHK: 86.44–86.48 sq. m.; 3BHK: 95.77 sq. m.
Booked / available: Portal-derived unit record shows 0 booked and 15 available (2BHK: 0/10 booked, 10 available; 3BHK: 0/5 booked, 5 available). The record has no as-of date, so treat these counts as indicative.
Construction stage: No verified current stage or site-progress measurement is supplied. The permit is an approval record; it does not establish construction completion.
Completion dates: Project fields show proposed and revised proposed completion as 03/04/2025. Form B separately records the promoter’s completion undertaking as 04/03/2025.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents. The permit requires a completion notice and occupancy certificate before occupation.
2. The project story
- AASHRITHA PRIDE is recorded with TG-RERA as a residential apartment project in Gayatri Nagar, Hyderabad, on Survey No. 123. Its RERA-listed offering comprises 15 apartments—10 two-bedroom units and five three-bedroom units—in a single building. The GHMC building-permit extraction identifies that building as Building A, with one stilt and five upper floors.
- The project record does not establish how much construction has been completed, whether any apartments have been handed over, or whether the building has an occupancy certificate. The portal-derived booking figures show all 15 units as available and none as booked, but they have no as-of date and should be treated as indicative rather than a current sales statement.
- The permit contains design and site conditions, including rainwater-harvesting structures, transformer space, a garbage house and an ETP. These are approval requirements or recorded provisions, not evidence that the facilities have been installed or commissioned.
3. Master plan, architecture & building design
- The project’s RERA land record identifies a single site of 589.63 sq. m. in Survey No. 123, with recorded net area also 589.63 sq. m. The GHMC permit extraction identifies one residential building, Building A, with 1 stilt + 5 upper floors and a stated height of 14.99 m. No basement, podium, multi-building arrangement or separate phase organization is established in the supplied material.
- The RERA fields state an approved built-up area of 1,611.33 sq. m. The permit’s extracted parameters separately report 1,342.75 m² for residential upper floors and 256.72 m² for the stilt. These figures are presented as recorded; the available extraction does not provide a drawing-based area schedule explaining their relationship.
- The permit records 10 rainwater-harvesting structures and 25 trees, and requires a periphery strip of greenery. The supplied drawing and permit extracts do not establish flats per floor, lift or stair configuration, entrances, exits, internal circulation, open-space dimensions, or the residential/common-area distribution.
4. Homes, configurations & floor plans
- The RERA unit record lists 10 2BHK apartments and five 3BHK apartments. It reports saleable areas separately from drawing-measured carpet areas. The carpet figures below are software measurements from the approved floor-plan drawing record, not RERA-filed area disclosures; they need drawing review. Saleable area includes the home’s share of common areas, while carpet area is a different measurement.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 10 | 0 | 10 | 86.44–86.48 sq. m. | 58.1–68.0 sq. m.; median 63.1 sq. m. (software-measured) | 27% |
| 3BHK | 5 | 0 | 5 | 95.77 sq. m. | Not supplied for this RERA-listed configuration | Not supplied |
- For one measured 2BHK drawing, the room schedule identifies a living room, dining area, kitchen, two bedrooms and a toilet, as well as two balconies. The drawing extraction gives dimensions for the listed enclosed rooms; balconies are excluded from the measured carpet area. These room details describe one measured drawing, not every unit.
- The drawing-measurement data also contains a 6BHK configuration, but the RERA unit record does not list it as a project offering; it is therefore not included as a purchasable RERA-listed configuration here.
5. Parking & vehicle circulation
- The GHMC permit states that the cellar and stilt approved for parking are to be used exclusively for vehicle parking, without partition walls or rolling shutters. The extracted building configuration identifies one stilt; it does not establish a cellar level, the number or type of parking spaces, visitor or accessible spaces, parking allocation to individual units, or EV provision.
- Although the permit describes parking use, the supplied records do not establish actual construction or a buyer’s exclusive entitlement to a particular bay. Obtain the sanctioned parking plan and the relevant sale/allotment documents to confirm any unit-specific arrangement.
6. Amenities, recreation & open spaces
- The RERA amenities record names project infrastructure and safety-related items, with recorded progress percentages. A percentage of 0 or 30 is a portal entry, not independent confirmation of construction or operation. The GHMC permit records certain site provisions and requirements; neither source establishes independently verified completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Internal roads and footpaths | No size stated | RERA amenities record | Listed “YES”; 0%. Not independently verified. |
| Green strip / tot-lot / park | No area stated; the permit also requires a periphery greenery strip | RERA amenities record; GHMC permit | Listed “YES”; 0%. Not independently verified. |
| Community buildings | No description or size stated | RERA amenities record | Progress 0%; not independently verified. |
| Street lighting | No quantity stated | RERA amenities record | Listed “YES”; 0%. Not independently verified. |
- The promoter-vendor material mentions facilities such as a swimming pool, clubhouse, gym, landscaped gardens and indoor play areas, but these are not established in the supplied RERA amenity record or permit extraction as sanctioned or delivered project facilities. They are not treated here as confirmed project provisions.
7. Utilities, building services & safety
- The RERA amenities record lists water supply, sewerage, storm-water drains, sewage and sullage treatment/disposal, solid-waste management, rainwater harvesting, energy management, fire protection and safety, and electrical meter room/substation/receiving station. It records water supply at 30% and the other listed service-progress entries at 0%; these are declared portal figures, not independent verification of works or operational service.
- The GHMC permit records 10 rainwater-harvesting structures, space for a transformer, a garbage house and an ETP. It also requires sanitation, plumbing, fire-safety requirements, lifts and electrical installations to be executed under qualified technical supervision. The supplied extracts do not state water source or storage capacity, treatment capacity, backup-power provision, lift count or capacity, detailed fire systems, CCTV, access control, or accessibility arrangements.
- The permit requires an occupancy certificate before occupation and requires a completion notice after construction. No occupancy/completion certificate is supplied in the reviewed project documents; no completed or commissioned status is established here.
8. Location, access & connectivity
- The registered project location is Gayatri Nagar, Hyderabad, Telangana 500097. The permit describes the site as being in Jeedimetla, Quthbullapur, Medchal-Malkajgiri, at Survey No. 123; the project fields separately state village Gayatri Nagar and district Hyderabad. These are the location identifiers provided in the records.
- The RERA land record lists the eastern boundary as “ROAD WIDTH 12,” with neighbouring land to the north, south and west. The GHMC permit also references an 18-metre road condition. The supplied extracts do not identify a named approach road, public-transport service, or measured distances to local landmarks.
9. Developer & development status
- The registered legal promoter is TANMAY CONSTRUCTIONS, recorded as a partnership. The project record lists Chennupati Sarath Kumar, Gantu Srinivasa Rao and Punukollu Jaya Chandra as partners, and Mynani Ravi Kumar as authorized signatory. The supplied records do not provide a verified promoter registration number or official website/contact details.
- The Form B affidavit-cum-declaration was signed by Mynani Ravi Kumar as authorized signatory and dated 18/2/2020. It contains the promoter’s statements about title and encumbrances, the RERA separate-account arrangements and an undertaking to complete by 04/03/2025; these are promoter declarations, not independent verification of present title, account operation or construction status.
- The RERA project fields show 03/04/2025 as both the proposed and revised proposed completion date, while the registration certificate states validity through 03/04/2025. The supplied record does not establish a subsequent extension, current construction progress or an occupancy certificate.
10. Approvals, official records & documents
TG-RERA registration: Form C certificate for AASHRITHA PRIDE, registration P02500002013, issued 06/07/2020; stated validity 06/07/2020–03/04/2025. The certificate is not marked extended.
Principal building approval: GHMC Building Permit Order 2/C23/05551/2019, approved 03 April 2019; file no. 2/KP/17905/2018. The extraction identifies Building A, residential flats, at Survey No. 123.
Building and commencement record: The RERA document register includes “Commencement Certificates for each building in each phase”; the supplied extracted document is a GHMC Building Permit Order. No separate commencement notice or certificate is identified in the supplied material.
Approved-plan evidence: A layout-plan item is listed in the RERA document register, but its contents were not extracted. The permit extraction supplies selected building and site parameters.
Completion / occupancy evidence: No completion or occupancy certificate is included in the supplied project documents.
Promoter declaration: Form B affidavit-cum-declaration by TANMAY CONSTRUCTIONS’ authorized signatory, dated 18/2/2020.
Title / development records in project file: The RERA document list includes a title search report and title documents, including a 2018 sale deed and a 2019 development agreement-cum-GPA. Their detailed title implications are addressed in the Land & Title section.
- The available plan item is not extractable in the supplied record, and the reviewed material does not include a completion/occupancy certificate or a current site-progress verification. Those limits mean the overview can describe the registered offering and permit-recorded design, but cannot confirm present construction or facility completion.
Frequently asked questions
Is AASHRITHA PRIDE registered with Telangana RERA?
Yes. AASHRITHA PRIDE is registered with the Telangana Real Estate Regulatory Authority as P02500002013; the registration status is On-Going Project.
Who is the developer of AASHRITHA PRIDE?
The promoter named in the RERA registration is TANMAY CONSTRUCTIONS.
Where is AASHRITHA PRIDE located?
AASHRITHA PRIDE is in GAYATRI NAGAR, Hyderabad, Telangana (500097).
When will AASHRITHA PRIDE be completed?
The promoter's proposed date of completion filed with RERA is 03/04/2025. This is the promoter's declaration, not a guarantee.
More projects in Hyderabad