Gautham Sai Infrastructures

M/S GOWTHAM SAI INFRASTRUCTURES · Medchal-Malkajgiri · RERA P02200001103

GAUTHAM SAI INFRASTRUCTURES is a residential apartment project located at Gajula Ramaram-1, Qutballapur Mandal, Medchal-Malkajgiri District. It is being developed by the registered promoter M/S Gowtham Sai Infrastructures, a partnership. The project occupies 633.92 m² and comprises one building with 1 Stilt + 5 upper floors and 15 apartments: 10 2BHK and 5 3BHK. It is registered with TG-RERA under P02200001103, with proposed completion on 26/03/2025.

More from Gowtham Sai Infrastructures · 2 projects →

01What we found

Period endedTG-RERA registration ran to 26 Mar 2025 - check its extension on TG-RERA
10documents on file - each fact links to its page
1court case on this project's land (survey 307, Gajula Ramaram-1)
8items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldProject record
Registered project nameGAUTHAM SAI INFRASTRUCTURES RERA record
Project typeResidential apartment project RERA record
Phase / registered portionPhase is not separately identified in the supplied record; the registration identifies Plots 53 & 54 and the project site.
TG-RERA registrationP02200001103; granted under section 5, issued 05/08/2019.
Registration validityCertificate states 05/08/2019 to 26/03/2025; no extension is recorded in the supplied certificate. Registration validity is distinct from the completion undertaking and from occupancy certification.
Registered promoterM/S Gowtham Sai Infrastructures, a partnership. RERA record Corporate record
RERA status in supplied recordThe project is registered; the certificate’s stated validity has ended, and the supplied record does not show an extension.

Land and geographic identity

FieldProject record
Locality / revenue villageGajula Ramaram-1; the building permit names Gajularamaram. RERA record RERA filing
Mandal / district / PINQutballapur / Medchal-Malkajgiri / 500055. RERA record
Project survey numbers307/2/7, 14, 16 & 26 are stated in the RERA registration certificate. The building permit also names 307/2/6, 7, 14, 16 & 26.
Site extent633.92 m²; the RERA land details report total area and net area as 633.92 m², with affected area 0. RERA filing
Plots identifiedPlots 53 & 54. RERA filing
Boundaries in RERA filingEast: ROAD WIDTH 12; West: PLOT NO 63 AND 64; North: PLO NO 55; South: NEIGHBOURS LAND. RERA filing
Project survey subdivisionsNo subdivision beyond the survey-number forms above is specified in the registration certificate or building permit.

Development identity

FieldProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC).
Principal building approvalApproval No. 2/C26/04975/2019, dated 26 March, 2019; permit file No. 2/C26/01637/2019. Approvals record
Approved building use and formResidential building, 1 Stilt + 5 upper floors, stated height 14.99 m.
Approved built-up area1,811.01 m² as reported in the RERA filing. RERA filing
Building / tower countThe RERA filing reports one building unit; one block/tower is reflected in the unit summary. RERA filing RERA unit table
Parking / other area figures in permitPermit extraction lists Cellar 1,478.25, Stilt 319.88, RM 99.56, 30 Trees, TOTAL: 646,619.00, and 148.09; the supplied extraction does not label all these figures sufficiently to interpret them as parking counts or areas.
Approved versus RERA-declared unitsThe RERA filing reports 1 total building unit and 1 proposed building unit; the unit inventory separately records 15 apartments: 10 two-bedroom and 5 three-bedroom. RERA filing RERA unit table

Offering and status

FieldProject record
Unit types2BHK and 3BHK apartments. RERA unit table RERA unit details
RERA-filed saleable areas2BHK: 46.84 m²; 3BHK: 102.43 m². RERA unit table RERA unit table
Booked / availableRERA portal-derived inventory records 0 booked and 10 available 2BHK units, and 0 booked and 5 available 3BHK units. The portal record has no stated as-of date; figures are indicative. RERA unit table RERA unit table
Construction stageNo independently verified site progress or construction-stage report is supplied. RERA-filed progress entries report water supply at 50% and most other listed infrastructure items at 0%; these are filing figures, not a site inspection. RERA amenities
Completion datesForm B declares completion by 17/01/2025. The RERA project record states proposed completion 26/03/2025. These are separate recorded dates. RERA record
Occupancy / completion certificateNo occupancy certificate or completion certificate is included in the supplied project documents. The building permit states an occupancy certificate is compulsory before occupation. Document index

2. The project story

This is a residential apartment project registered with TG-RERA as GAUTHAM SAI INFRASTRUCTURES, on a 633.92 m² site identified with Plots 53 and 54 at Gajula Ramaram-1, Qutballapur Mandal, Medchal-Malkajgiri District. The filing identifies survey numbers 307/2/7, 14, 16 and 26; GHMC’s building permit also names survey 307/2/6. RERA record RERA filing

The GHMC permit describes one residential building of one stilt level and five upper floors, with a stated height of 14.99 m. The RERA inventory lists 15 apartments—10 2BHK and 5 3BHK. The material supplied does not establish the number of apartments on each floor, the present construction stage through independent inspection, or whether any portion is complete or occupied. RERA unit table RERA unit details

The RERA filing reports water supply at 50% and the other listed infrastructure entries predominantly at 0%. This is reported project information, not independently verified construction progress. No occupancy or completion certificate is supplied. RERA amenities Document index

3. Master plan, architecture & building design

The supplied GHMC building permit is for a residential building on a 633.92 m² site, with 1 Stilt + 5 upper floors and a stated height of 14.99 m. The RERA filing reports approved built-up area of 1,811.01 m². These figures are reported separately; the supplied material does not provide a verified breakdown of floor area, building footprint, floor-by-floor layout, or FSI-counted area. RERA filing

The permit extraction lists cellar and stilt figures, but does not establish a count of parking bays or a complete, interpretable area schedule. It also lists a tot-lot, 30 trees, transformer space, a garbage house, a rainwater-harvesting structure (percolation pit), and an ETP. The permit requires greenery on the site periphery and fencing and maintenance of the tot-lot as greenery before an occupancy certificate is issued.

The supplied floor-plan records contain two drawings, but no measured drawings or extracted flat layouts are available. Consequently, the evidence does not establish flats per floor, internal circulation, lifts, stairs, entrances, exits, or a detailed residential/common-area distribution. Floor plans

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK1001046.84 m²Not availableNot supplied
3BHK505102.43 m²Not availableNot supplied

Unit counts, booking figures and saleable areas are from the RERA inventory; the booking record has no stated as-of date and should be treated as indicative. The supplied floor-plan review reports two drawings but no measured flats, so no drawing-based carpet-area or room-dimension figures are available. RERA unit table RERA unit details Floor plans

The RERA-filed saleable area is not a measured carpet-area figure. The evidence supplied does not quantify carpet area, balcony or utility areas, or common-area loading for either configuration. RERA unit details Floor plans

5. Parking & vehicle circulation

The GHMC permit extraction lists a cellar and stilt level and states that cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not partitioned or converted to other uses. The RERA filing reports a mortgage area of 148.09 m², but the supplied record does not establish a sanctioned parking-space count, resident or visitor allocation, accessible spaces, bay ownership, or parking allocation to particular apartments. RERA filing

The permit extraction’s cellar and stilt figures are not sufficiently labelled to treat them as parking counts. No ramp, driveway, vehicle-entry arrangement, pedestrian separation, mechanical-parking system, or EV-charging provision is evidenced in the supplied material.

6. Amenities, recreation & open spaces

Tot-lot / greenery
Description / sizeTot-lot is listed; size is not stated. Permit requires it to be fenced and maintained as greenery before occupancy certification.
Evidence sourceGHMC permit
Declared progress / verified statusPermit condition; completion not verified
Trees
Description / size30 Trees listed.
Evidence sourceGHMC permit
Declared progress / verified statusListed in permit; planting status not verified
Rainwater harvesting
Description / sizeRain Water Harvesting Structure (percolation pit); size not supplied.
Evidence sourceGHMC permit; RERA filing RERA amenities
Declared progress / verified statusRERA filing marks water conservation/rainwater harvesting “YES” and 0%; completion not verified
Community buildings
Description / sizeRERA filing lists community buildings.
Evidence sourceRERA amenities
Declared progress / verified status0% reported; not independently verified
Clubhouse, swimming pool, gym, children’s play area
Description / sizeListed in vendor material, without sizes or capacities.
Evidence sourcePromoter website
Declared progress / verified statusPromoter/vendor material only; not established as sanctioned or delivered in the supplied record
Covered car parking
Description / sizeListed in vendor material; count and allocation not supplied.
Evidence sourcePromoter website
Declared progress / verified statusPromoter/vendor material only; no delivery or unit allocation verified

7. Utilities, building services & safety

Water supply
Evidence in supplied recordRERA filing marks water supply “YES” and reports 50%. RERA amenities
Status / limitationFiling-reported progress; source, storage capacity and treatment are not specified or independently verified.
Sewerage and sewage treatment
Evidence in supplied recordRERA filing lists sewerage and treatment/disposal of sewage and sullage water, both at 0%. The GHMC permit lists an ETP. RERA amenities
Status / limitationNo capacity, design details or completion evidence supplied.
Storm-water drainage
Evidence in supplied recordListed in the RERA filing at 0%. RERA amenities
Status / limitationNo system details or completed status supplied.
Rainwater harvesting
Evidence in supplied recordRERA filing marks the item “YES” at 0%; permit lists a percolation pit. RERA amenities
Status / limitationDeclared/listed provision; completion not verified.
Electrical services
Evidence in supplied recordPermit requires space for a transformer; RERA filing lists electrical meter room/sub-station/receiving station at 0%. RERA amenities
Status / limitationNo capacity, supply arrangement, backup or completed status supplied.
Fire and life safety
Evidence in supplied recordListed in the RERA filing at 0%. RERA amenities
Status / limitationSpecific equipment, escape arrangements and clearances are not established by the supplied records.
Waste
Evidence in supplied recordPermit lists a garbage house; RERA filing lists solid-waste management and disposal at 0%. RERA amenities
Status / limitationNo segregation or operating details supplied.
Lifts, accessibility and security
Evidence in supplied recordNo lift or service-lift details, accessibility features, CCTV or access-control system are evidenced in the supplied material.
Status / limitationNot disclosed in the supplied records.

8. Location, access & connectivity

The official project location is recorded as Gajula Ramaram-1, Qutballapur Mandal, Medchal-Malkajgiri District, PIN 500055. The GHMC permit names Gajularamaram and identifies MITHILANAGAR ROAD in its location extraction. The supplied location record describes its coordinates as a cadastral parcel centroid, not as a separately surveyed entrance point. RERA record Location record

The location dataset lists the following distances: New Era The Lead School 0.2 km; an unnamed park 0.5 km; Store World 1.1 km; Usha Mullapudi Cardiac Centre 1.2 km; Union Bank of India 1.6 km; Auto Stand 2.0 km; Sri Chaitanya Junior College 2.9 km; and KPHB Colony Metro 4.5 km. These are the supplied location-record measurements; no travel times are provided. Location record

9. Developer & development status

The registered promoter is M/S Gowtham Sai Infrastructures, identified in the RERA filing as a partnership. The supplied partnership information names Srinivasa Rao Kandula as an authorized signatory and Suneetha Kandula as a partner. The promoter address in the RERA filing is HOME, SUMITHRA NAGAR, GAJULA RAMARAM, Qutballapur, Medchal-Malkajgiri, 500055. The RERA certificate separately records a promoter office in Kukatpally, Qutballapur, Medchal-Malkajgiri, PIN 500072. No official contact number, email or promoter website is established in the supplied RERA information. Corporate record Parties record RERA record

The project’s Form B affidavit, dated 25/05/2019, declares completion by 17/01/2025. The project record gives a proposed completion date of 26/03/2025, while the registration certificate states validity through 26/03/2025 and records no extension. These are distinct completion and registration records; the supplied evidence does not confirm actual completion or occupancy certification. RERA record Document index

10. Approvals, official records & documents

TG-RERA registration certificate
DetailsForm C; registration P02200001103, granted under section 5; issued 05/08/2019; certificate states validity through 26/03/2025 and no extension.
GHMC building permit
DetailsApproval 2/C26/04975/2019, dated 26 March, 2019; file 2/C26/01637/2019; residential building permit for 1 Stilt + 5 upper floors.
RERA Form B
DetailsPromoter affidavit dated 25/05/2019, including a declared title and encumbrance statement and completion undertaking.
Layout plan
DetailsA layout-plan document is listed in the RERA record, but its supplied extraction is not readable.
Occupancy / completion certificate
DetailsNo such certificate is present in the supplied document list.
EvidenceDocument index

The project approval record lists the technical persons as architect KANCHERLA PRASANNA KUMARI (license No. ca/2015/69457) and structural engineer T CHAKRAPANI (license No. 84/STRL/ENGG/TP-10/GHMC/12).

Frequently asked questions

Is GAUTHAM SAI INFRASTRUCTURES registered with Telangana RERA?

Yes. GAUTHAM SAI INFRASTRUCTURES is registered with the Telangana Real Estate Regulatory Authority as P02200001103; the registration status is New Project.

Who is the developer of GAUTHAM SAI INFRASTRUCTURES?

The promoter named in the RERA registration is M/S GOWTHAM SAI INFRASTRUCTURES.

Where is GAUTHAM SAI INFRASTRUCTURES located?

GAUTHAM SAI INFRASTRUCTURES is in GAJULA RAMARAM, Gajula Ramaram-1, Qutballapur, Medchal-Malkajgiri, Telangana (500055).

When will GAUTHAM SAI INFRASTRUCTURES be completed?

The promoter's proposed date of completion filed with RERA is 26/03/2025. This is the promoter's declaration, not a guarantee.

More projects in Gajula Ramaram 1