Sign in

Vishwak Enclave

DEVASHREE CONSTRUCTIONS · Hanamkonda · RERA P00300003840

VISHWAK ENCLAVE is a residential apartment project in HANAMKONDA, Warangal Urban district; the mandal is not disclosed in the supplied project record. The registered promoter is DEVASHREE CONSTRUCTIONS. The project is on a site of 965.81 m2 and comprises one residential building with 1 Stilt + 5 upper floors and 25 apartments: 1BHK and 2BHK configurations. It is registered under TG-RERA number P00300003840, and the project header records a proposed completion date of 18/06/2027.

01What we found

RegisteredTG-RERA - valid till 18 Feb 2027
17documents on file - each fact links to its page
3court cases on this project's land (survey 196, 197, Hanamkonda)
9items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

9 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered project nameVISHWAK ENCLAVE RERA record
Project typeResidential apartment project RERA record
Phase / registered portionPhase not separately identified in the supplied record; the registration and building permit refer to one residential building RERA record
TG-RERA registrationP00300003840
Registration status and validityRegistered under section 5; certificate states validity from 03/01/2022 to 18/02/2027, unless extended by the Authority. The supplied certificate says it has not been extended.
Registered promoterDEVASHREE CONSTRUCTIONS
RERA completion undertakingThe Form B declaration states a completion undertaking of 18/02/2027.

Land and geographic identity

FieldRecord
LocalityHANAMKONDA RERA record
Revenue villageHanamkonda in the project identity record; the building permit describes the site as Shayampet, Ward 32. RERA record
MandalNot disclosed in the supplied project record. Land records
DistrictWarangal Urban RERA record
PIN506319 RERA record
Project survey numbers189, 196, 197 & 198; no subdivisions are specified in the project identity fields. RERA record
Plot numbers18 & 19
Site extent965.81 m2; the permit records both site area and net area as 965.81 m2, with road-affected area 0. Land records
Boundaries in RERA filingNorth and south: 9M WIDE ROAD; east and west: VACANT LAND. RERA filing

Development identity

FieldRecord
Sanctioning authorityGreater Warangal Municipal Corporation; the project filing also identifies DTCP as the authority. Approvals record
Principal building permit3006/26457/W32/2020, approved 18 February, 2021. Approvals record
Approved built-up area2166.1 sqmts in the project filing; the permit extraction separately lists 2,166.10 for residential upper floors and 477.80 for the stilt. These are the figures as labelled in their respective records. RERA filing
Buildings / blocksOne building is recorded in the project filing; the permit describes one residential building. RERA filing
Sanctioned floor configuration1 Stilt + 5 upper floors; permit extraction records height 14.7 m.
Parking levels / provisionThe permit specifies stilt parking; no parking-space count or separate parking level is provided in the supplied extract.
Units1 proposed building unit is recorded in the project land details; the RERA unit schedule lists 25 apartments. The permit requires prior approval to increase the sanctioned number of units. RERA filing RERA unit table

Offering and status

FieldRecord
RERA-listed configurations1BHK and 2BHK apartments. RERA unit table
RERA-filed saleable areas1BHK: 100.5 sq.m; 2BHK: 70.54 sq.m. RERA unit table
Booked / availablePortal-derived counts last read show 0 booked / 5 available 1BHK and 0 booked / 20 available 2BHK. The record has no as-of date, so these counts are indicative. RERA unit table
Construction stageThe RERA amenity record gives 0% for each listed item; it does not establish an independently inspected site-construction stage. RERA amenities
Completion timelineForm B promoter undertaking: 18/02/2027. The project header separately records a proposed completion date of 18/06/2027; the supplied record does not identify this as a revised date. RERA record
Occupancy / completion certificateThe building-permit extraction says completion is not certified; no occupancy certificate is supplied. This is the permit’s building scope.

2. The project story

VISHWAK ENCLAVE is registered as a residential apartment project in Hanamkonda, Warangal Urban, associated in the filed records with Plot Nos. 18 & 19 and Survey Nos. 189, 196, 197 & 198. The municipal building permit describes one residential building with 1 stilt + 5 upper floors on a site of 965.81 m2. RERA record Land records

The RERA unit schedule lists 25 apartments: five 1BHK and 20 2BHK. The portal-derived booking figures are indicative because no as-of date is supplied. The available evidence does not establish completed or occupancy-certified portions, nor does it independently verify construction progress. The permit extraction states that completion has not been certified and requires an occupancy certificate before occupation. RERA unit table

3. Master plan, architecture & building design

The filed project information records a total and net site area of 965.81 sqmts, with no road-affected area. The building permit extraction describes one residential building and records 1 Stilt + 5 upper floors. It lists 2,166.10 for residential upper floors, 477.80 for the stilt, and 162.34 for a tot-lot; these are permit-extraction component figures and are not interchangeable area measures. RERA filing RERA filing

The project filing states approved built-up area as 2166.1 sqmts. The permit gives setbacks of Front 3 m, Rear 4 m, Side I 4 m, Side II 4 m and records a building height of 14.7 m. The permit also identifies LRS/C3/828/2008 as the Layout / Sub Divn. No. RERA filing

The building-permit extraction identifies a tot-lot and a stilt, but the supplied material does not provide a readable architectural drawing description establishing flat distribution by floor, building footprint, lift or stair arrangement, detailed circulation, or residential/common-area split. The floor-plan file is listed as a layout-plan document but is not extracted as a readable approval plan.

4. Homes, configurations & floor plans

The RERA filing supplies unit counts and saleable areas. Carpet areas below are software measurements from approved floor-plan drawing geometry, not RERA-filed figures; the measurement record says these require review. The 2BHK measurements include two held-back implausible measurements, and the drawing-based measurements should be checked against the drawings. RERA unit table Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
1BHK505100.5 sq.m82.3 sq.m (software-measured)18%
2BHK2002070.54 sq.m63.1–66.9 sq.m (software-measured; median 65.9 sq.m)Not supplied

The drawing measurement record describes a 1BHK example with a hall, bedroom, kitchen, toilet and balcony; the balcony is excluded from its measured carpet area. Its 2BHK example includes a hall, two bedrooms, kitchen, two toilets and a balcony; the balcony is excluded from the measured carpet area. These are drawing-derived room descriptions, not independent site measurements. RERA unit details

Carpet area and saleable area are different measures: the supplied drawing-measurement caveat says saleable area also counts the home’s share of common areas. No separate measured common-area allocation or utility-area figure is supplied. Floor plans

5. Parking & vehicle circulation

The building permit specifies the stilt for parking and states that the cellar and stilts approved for parking must be used exclusively for vehicle parking, without partition walls or rolling shutters. The supplied extract does not specify the number of car or two-wheeler spaces, visitor or accessible spaces, mechanical parking, EV charging, or parking allocations to individual apartments. A drawn or permitted parking provision does not by itself establish exclusive ownership or an allotment to a buyer.

6. Amenities, recreation & open spaces

The RERA amenities record lists the facilities below and records 0% for each item. Its “YES” entries are filing declarations, not independent verification of installation or completion. The building-permit extraction separately specifies a tot-lot and certain site provisions. RERA amenities

Community buildings
Description / sizeNo size or detail supplied
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified status0%; completion not independently verified
Green strip / tot-lot / park
Description / sizePermit lists tot-lot of 162.34 m2 and requires it to be fenced and maintained as greenery before occupancy certification
Evidence sourceRERA amenities record; building permit RERA amenities
Declared progress / verified statusRERA record: 0%; installed status not independently verified
Aggregate recreational open space
Description / sizeListed; no area supplied in the RERA amenities record
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified status“YES” recorded; 0%; completion not independently verified
Internal roads & footpaths
Description / sizeListed; no dimensions or layout details supplied
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified status0%; completion not independently verified
Street lighting
Description / sizeListed; no specifications supplied
Evidence sourceRERA amenities record RERA amenities
Declared progress / verified status0%; completion not independently verified

7. Utilities, building services & safety

The RERA amenities record marks water supply, sewerage, storm-water drains, rainwater harvesting, an electrical meter room/sub-station/receiving station, and recreational open space as “YES”; it records 0% progress for these items. The permit specifically requires a rainwater-harvesting percolation pit, space for a transformer, and a garbage house. These are recorded provisions or declarations; the supplied evidence does not independently verify that they are installed or operational. RERA amenities

The RERA filing lists treatment and disposal of sewage and sullage water, solid-waste management and disposal, energy management, and fire protection/fire-safety requirements, but supplies no system specifications, capacities or completion evidence. The permit states that public water and electricity connections will be provided only on production of an occupancy certificate. No lift details, backup-power capacity, fire-system details, accessible circulation information or waste-management capacity is supplied. RERA amenities

8. Location, access & connectivity

The registered project locality is HANAMKONDA, Warangal Urban, PIN 506319. The building permit identifies Plot Nos. 18 & 19, Survey Nos. 189, 196, 197 & 198, and describes the site as Shayampet, Ward 32. The RERA filing records roads on the north and south boundaries, each described as 9M WIDE ROAD. RERA record RERA filing

No verified public-transport, approach-road or landmark information is supplied for this project. The location dataset contains a cadastral-parcel-centroid coordinate and a connectivity entry for Financial District (Nanakramguda), 1.2 km; the supplied material does not establish that this coordinate or distance describes the registered Hanamkonda site, so it is not relied on here. Location record

9. Developer & development status

The registered promoter is DEVASHREE CONSTRUCTIONS, identified in the project filing as a partnership. Its listed GSTIN is 36AAQFD2356Q1ZQ. The supplied project record gives the promoter address as SRI NILAYAM, KASHIBUGGA, SHAYAMPET, HANAMKONDA, Warangal Urban, 506319. The registration certificate separately prints a promoter-office location in Warangal Urban, PIN 506002. Parties record Corporate record

The RERA record names PURNACHANDER MANDARAPU as authorized signatory and SANTHOSH KUMAR YADA and VIJAY KUMAR YADA as partners. Form B is a promoter declaration, including its completion undertaking of 18/02/2027; it is not a construction-progress certification. The supplied records do not establish an independently verified construction stage or occupancy certification. Parties record

10. Approvals, official records & documents

TG-RERA registration certificate
Scope / identifying detailsVISHWAK ENCLAVE; P00300003840; issued 03/01/2022; certificate states validity through 18/02/2027 and no extension
Building permit order
Scope / identifying detailsGreater Warangal Municipal Corporation; 3006/26457/W32/2020; approved 18 February, 2021; Plot Nos. 18 & 19, Survey Nos. 189, 196, 197 & 198; one residential building, 1 stilt + 5 upper floors
Form B promoter declaration
Scope / identifying detailsDeclaration by MANDARAPU PURNACHANDER for DEVASHREE CONSTRUCTIONS; states title basis, no encumbrances, and completion undertaking of 18/02/2027
Layout-plan document
Scope / identifying detailsListed as a layout plan but not extracted as a readable approval plan in the supplied record
Occupancy / completion certificate
Scope / identifying detailsNo certificate supplied; building-permit extraction records completion as not certified

Frequently asked questions

Is VISHWAK ENCLAVE registered with Telangana RERA?

Yes. VISHWAK ENCLAVE is registered with the Telangana Real Estate Regulatory Authority as P00300003840; the registration status is New Project.

Who is the developer of VISHWAK ENCLAVE?

The promoter named in the RERA registration is DEVASHREE CONSTRUCTIONS.

Where is VISHWAK ENCLAVE located?

VISHWAK ENCLAVE is in HANAMKONDA, Telangana (506319).

When will VISHWAK ENCLAVE be completed?

The promoter's proposed date of completion filed with RERA is 18/06/2027. This is the promoter's declaration, not a guarantee.

More projects in Hanamkonda