Deshai Towers
SRI MUDRA CONSTRUCTIONS · Hanamkonda · RERA P00300003458
DESHAI TOWERS is a residential apartment project in Hanamkonda, Hanamkonda mandal, Warangal Urban district. It is being developed by the registered promoter, SRI MUDRA CONSTRUCTIONS, a partnership. The project occupies 2023.36 m² and comprises one building with 1 stilt and 5 upper floors, with 40 apartments: 30 2BHK and 10 3BHK. It is registered with TG-RERA as P00300003458, and its proposed completion date is 8 March 2027.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | DESHAI TOWERS RERA record |
| Project type / registered portion | Residential apartment project; phase or separately registered portion not disclosed RERA record RERA filing |
| TG-RERA registration | P00300003458; registered from 24 September 2021 to 8 March 2027 RERA record |
| RERA status | New Project; registration certificate records registration under section 5 RERA record |
| Registered promoter | SRI MUDRA CONSTRUCTIONS; partnership RERA record RERA filing Corporate record |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / address | Hanamkonda; Jawahar Nagar is stated in the promoter address. The project’s RERA locality is HANAMKONDA RERA record RERA filing |
| Revenue village | Hanamkonda is recorded in the project identity; the title documents identify Waddepally Revenue village, and the occupancy certificate identifies Gopalpur. These location descriptions are retained as recorded RERA record Land records |
| Mandal | Hanamkonda is recorded on the occupancy certificate; the project land record does not disclose a mandal Land records |
| District / PIN | Warangal Urban / 506001 in the project header and address fields RERA record RERA filing |
| Survey numbers | 22 (NEW), 900 (OLD); also recorded as 22 (New), 900 (Old) Land records |
| Site extent | 2023.36 m²; the title and development agreement describe Ac.0-20 gts. (2420 sq. yards / 2023.36 sq. metres) Land records |
| Total / net area | Total 2023.36 m²; net 2023.36 m²; road-affected area recorded as 0 RERA filing |
| Boundaries | North: EXISTING BUILDING; South: 12M ROAD; East and West: VACANT LAND RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Greater Warangal Municipal Corporation (GWMC) Approvals record |
| Principal building permit | 3006/26751/W31/2020, approved 08 March 2021 Approvals record |
| Approved built-up area | 4,508.55 m² RERA filing |
| Building count | One building/unit is recorded in the project land details RERA filing |
| Sanctioned configuration | 1 Stilt + 5 upper floors; the permit records a height of 17.94 m |
| Parking levels / provision | The permit says cellar and stilt approved for parking; the extracted sanctioned parameters identify 1, with 992.48 m², as stilt. No parking-space count is supplied |
| Units | 40 RERA-filed units: 30 2BHK and 10 3BHK. Approved-plan unit count is recorded as 1 building/unit; a separate approved apartment count is not supplied RERA filing RERA unit table |
Offering and status
| Field | Record |
|---|---|
| RERA-filed configurations and saleable area | 2BHK: 30 units, 22.67 m² each; 3BHK: 10 units, 86.4 m² each RERA unit table |
| Booked / available | RERA portal snapshot records 0 booked and 40 available (30 2BHK; 10 3BHK); no as-of date is supplied, so counts are indicative RERA unit table |
| Construction stage | RERA status is “New Project”; the supplied RERA record does not state a current construction-progress percentage RERA record RERA amenities |
| Promoter-declared completion | 8 March 2027 |
| Registration validity | Through 8 March 2027, unless extended by the Authority |
| Occupancy certificate | GWMC OC 0061/OC/3006/2024, dated 17 June 2024, covers the residential apartment building at survey numbers 22 (NEW), 900 (OLD) |
2. The project story
DESHAI TOWERS is registered with TG-RERA as a residential apartment project on land identified by survey numbers 22 (NEW) and 900 (OLD), with a registered site extent of 2023.36 m². The RERA record identifies Hanamkonda, Warangal Urban; title records describe the land as Waddepally Revenue village, while the occupancy-certificate record identifies Gopalpur. RERA record Land records
The building permit describes one residential semi-detached building with 1 stilt and 5 upper floors. The registration filing lists 40 apartments—30 2BHK and 10 3BHK—and the portal counts show all as available, with no as-of date recorded. These are portal-recorded counts, not a dated independent inventory check. RERA unit table
The supplied GWMC occupancy-certificate record states that the inspected building is fit for occupation and records completion on 17 March 2024 and issue of OC 0061/OC/3006/2024 on 17 June 2024. The project’s RERA certificate nevertheless records registration validity through 8 March 2027, and the promoter’s Form B declares that date as its completion undertaking. These dates describe different records and statuses; the evidence does not provide a current independent site-progress assessment.
3. Master plan, architecture & building design
The building permit records a 2023.36 m² site, 4,508.55 m² of residential area, a 1 Stilt + 5 upper-floor configuration and a stated building height of 17.94 m. The occupancy-certificate extraction records 4,508.55 m² floor area as per sanctioned plan and a height of 14.95 m as per sanctioned plan. These figures are quoted as stated in the respective records; no further area or height measurement is derived here.
The permit identifies one proposed residential building, and the occupancy certificate identifies a residential apartment building with stilt and five upper floors. The permit also records cellar and stilt parking provisions, but the supplied material does not establish a parking-space count, floor-by-floor apartment arrangement, footprint, lift or stair count, or detailed circulation plan.
The permit records 14% open space and a 110.48 m² tot-lot. It also calls for a transformer space, garbage house and rainwater-harvesting structure. No detailed landscape plan, internal-road plan or phase organization is provided in the supplied evidence.
4. Homes, configurations & floor plans
TG-RERA records 40 apartments across two configurations. The filed saleable-area figures are presented below as recorded; the evidence does not provide measured carpet areas for these RERA-filed 2BHK and 3BHK configurations. RERA unit table RERA unit details
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 30 | 0 | 30 | 22.67 m² | Not measured for this configuration in supplied drawings | Not supplied |
| 3BHK | 10 | 0 | 10 | 86.4 m² | Not measured for this configuration in supplied drawings | Not supplied |
The booking and availability figures are from the TG-RERA portal record; no as-of date is included. RERA unit table
The floor-plan measurement data identifies a 1BHK drawing configuration in document 181767, measured by software from the drawing geometry, with a median carpet area of 64.5 m² and a range of 64.0–65.0 m². It is not identified as a TG-RERA-filed configuration and should not be treated as part of the filed unit inventory. The drawing measurement is flagged as needing review. RERA unit details Floor plans
Carpet area and saleable area are distinct measures: the supplied floor-plan note says saleable area includes the home’s share of common areas, while the drawing-derived carpet measurement is software-measured and not a RERA disclosure. No loading figure is supplied. Floor plans
5. Parking & vehicle circulation
The building permit states that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking and not partitioned or repurposed. The extracted permit parameters identify a stilt area of 992.48 m². The occupancy-certificate extraction records parking area of 110.48 m². No total car or two-wheeler space count, visitor or accessible-space provision, mechanical parking, EV charging, ramp arrangement, or unit-wise parking allocation is supplied.
The promoter-supplied vendor record lists “Open Parking” and “Covered Parking,” but provides no counts or allocation details; these are not evidence of a legally documented exclusive parking allotment. Promoter website
6. Amenities, recreation & open spaces
The sanctioned building-permit extraction specifies a 110.48 m² tot-lot, records open space as 14%, and calls for a transformer space, garbage house and rainwater-harvesting structure. The RERA amenity record lists project infrastructure and facilities with declared progress percentages; these are reported portal fields, not independent completion verification. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green space | Tot-lot: 110.48 m²; permit records 14% open space | RERA amenities | Permit requirement recorded; RERA amenity progress 0%; independently completed status not established |
| Water supply | No source, storage or capacity specified | RERA amenities | RERA amenity progress 50%; completion not independently verified |
| Sewerage | Listed as “Sewerage (Chamber, Lines, Septic Tank, STP)”; specific installed system not established | RERA amenities | RERA amenity progress 50%; completion not independently verified |
| Internal roads and footpaths | No dimensions or plan details supplied | RERA amenities | RERA progress 0% |
| Storm-water drains | No design or capacity supplied | RERA amenities | RERA progress 0% |
| Street lighting | No specification supplied | RERA amenities | RERA progress 0% |
| Rainwater harvesting / water conservation | Permit calls for a rainwater-harvesting percolation pit; no capacity supplied | RERA amenities | RERA progress 0%; completion not independently verified |
| Community buildings | No facility details or size supplied | RERA amenities | Progress 0% |
| Solid-waste management and disposal | Permit calls for a garbage house; no capacity or operating details supplied | RERA amenities | RERA progress 0%; completion not independently verified |
| Recreational open space | Aggregate area not specified beyond permit’s 14% open-space record and 110.48 m² tot-lot | RERA amenities | RERA progress 0%; completion not independently verified |
No clubhouse or indoor-recreation facility is evidenced in the supplied project records. RERA amenities Document index
7. Utilities, building services & safety
The permit calls for a transformer space, rainwater-harvesting percolation pit and garbage house. The RERA amenity record lists water supply, sewerage, storm-water drainage, energy management, fire protection and electrical meter room/sub-station/receiving station, but does not provide capacities, equipment specifications or commissioning evidence. RERA amenities
The occupancy-certificate extraction identifies the building as fit for occupation, but the supplied materials do not detail water source or storage, sewage-treatment and reuse arrangements, electrical backup, lift count or capacity, fire-fighting systems, escape-stair configuration, accessibility features, CCTV or access-control arrangements. No such technical specification is inferred from the certificate or amenity listing. RERA amenities Promoter website
8. Location, access & connectivity
The project identity places DESHAI TOWERS in Hanamkonda, Warangal Urban, PIN 506001. The land boundary record identifies a 12M ROAD to the south. The title documents refer to Waddepally Revenue village, and the OC extraction identifies Gopalpur, Hanamkonda mandal, Warangal (Urban) district. RERA record RERA filing
The supplied location record provides a cadastral parcel-centroid coordinate of 17.41528, 78.35459 and lists Financial District (Nanakramguda) at 1.2 km. The evidence provides no measured route, travel time, public-transport details or approach-road description beyond the recorded southern road boundary. Location record
9. Developer & development status
The registered promoter is SRI MUDRA CONSTRUCTIONS, recorded as a partnership. Its project filing lists registered office details at Sri Nilayam, Chaitanyapuri Colony, Jawahar Nagar, Hanamkonda, Warangal Urban, PIN 506001. The project record identifies two authorised signatories, Satyanarayana Reddy Chandupatla and Krishna Koutam, and lists four other partners. RERA filing RERA filing Parties record
The promoter’s Form B affidavit, dated 25 February 2021, declares a completion undertaking of 8 March 2027 and states that the project land is free from encumbrances. These are promoter declarations in the filing. The RERA certificate records registration validity through 8 March 2027.
The supplied records do not state a current construction-progress percentage. The occupancy-certificate extraction records completion on 17 March 2024 for the building it identifies; it does not provide a current site inspection or unit-by-unit status. RERA amenities
10. Approvals, official records & documents
| Identifier / date | P00300003458; issued 24 September 2021; valid through 8 March 2027 |
|---|---|
| Scope and evidence | Form C for DESHAI TOWERS, with promoter conditions including the separate-account requirement |
| Identifier / date | 3006/26751/W31/2020; 8 March 2021 |
|---|---|
| Scope and evidence | Permit for a residential building at survey numbers 22 (NEW), 900 (OLD); includes sanctioned configuration and site conditions |
| Identifier / date | 0061/OC/3006/2024; 17 June 2024 |
|---|---|
| Scope and evidence | GWMC certificate for the residential apartment building at survey numbers 22 (NEW), 900 (OLD); the extraction records completion on 17 March 2024 |
| Identifier / date | Dated 26 July 2021 |
|---|---|
| Scope and evidence | Advocate S. Jayachandra’s title search report for the land identified as survey numbers 22 (New), 900 (Old), Waddepally |
| Identifier / date | 15696/2021; 15 June 2021 |
|---|---|
| Scope and evidence | Owner–developer development document for the identified survey land |
| Identifier / date | 25 February 2021 |
|---|---|
| Scope and evidence | Promoter affidavit containing project declarations and a completion undertaking |
The supplied evidence does not include an extracted approved-layout drawing or a detailed floor-plan description sufficient to establish apartment-level layouts, circulation, or technical service specifications. The building-permit and occupancy-certificate records above are the available project approval records used in this Overview. Document index
1. Project at a glance
Project identity
Registered project name: DESHAI TOWERS
Project type / registered portion: Residential apartment project; phase or separately registered portion not disclosed
TG-RERA registration: P00300003458; registered from 24 September 2021 to 8 March 2027
RERA status: New Project; registration certificate records registration under section 5
Registered promoter: SRI MUDRA CONSTRUCTIONS; partnership
Land and geographic identity
Locality / address: Hanamkonda; Jawahar Nagar is stated in the promoter address. The project’s RERA locality is HANAMKONDA
Revenue village: Hanamkonda is recorded in the project identity; the title documents identify Waddepally Revenue village, and the occupancy certificate identifies Gopalpur. These location descriptions are retained as recorded
Mandal: Hanamkonda is recorded on the occupancy certificate; the project land record does not disclose a mandal
District / PIN: Warangal Urban / 506001 in the project header and address fields
Survey numbers: 22 (NEW), 900 (OLD); also recorded as 22 (New), 900 (Old)
Site extent: 2023.36 m²; the title and development agreement describe Ac.0-20 gts. (2420 sq. yards / 2023.36 sq. metres)
Total / net area: Total 2023.36 m²; net 2023.36 m²; road-affected area recorded as 0
Boundaries: North: EXISTING BUILDING; South: 12M ROAD; East and West: VACANT LAND
Development identity
Sanctioning authority: Greater Warangal Municipal Corporation (GWMC)
Principal building permit: 3006/26751/W31/2020, approved 08 March 2021
Approved built-up area: 4,508.55 m²
Building count: One building/unit is recorded in the project land details
Sanctioned configuration: 1 Stilt + 5 upper floors; the permit records a height of 17.94 m
Parking levels / provision: The permit says cellar and stilt approved for parking; the extracted sanctioned parameters identify 1, with 992.48 m², as stilt. No parking-space count is supplied
Units: 40 RERA-filed units: 30 2BHK and 10 3BHK. Approved-plan unit count is recorded as 1 building/unit; a separate approved apartment count is not supplied
Offering and status
RERA-filed configurations and saleable area: 2BHK: 30 units, 22.67 m² each; 3BHK: 10 units, 86.4 m² each
Booked / available: RERA portal snapshot records 0 booked and 40 available (30 2BHK; 10 3BHK); no as-of date is supplied, so counts are indicative
Construction stage: RERA status is “New Project”; the supplied RERA record does not state a current construction-progress percentage
Promoter-declared completion: 8 March 2027
Registration validity: Through 8 March 2027, unless extended by the Authority
Occupancy certificate: GWMC OC 0061/OC/3006/2024, dated 17 June 2024, covers the residential apartment building at survey numbers 22 (NEW), 900 (OLD)
2. The project story
DESHAI TOWERS is registered with TG-RERA as a residential apartment project on land identified by survey numbers 22 (NEW) and 900 (OLD), with a registered site extent of 2023.36 m². The RERA record identifies Hanamkonda, Warangal Urban; title records describe the land as Waddepally Revenue village, while the occupancy-certificate record identifies Gopalpur.
The building permit describes one residential semi-detached building with 1 stilt and 5 upper floors. The registration filing lists 40 apartments—30 2BHK and 10 3BHK—and the portal counts show all as available, with no as-of date recorded. These are portal-recorded counts, not a dated independent inventory check.
The supplied GWMC occupancy-certificate record states that the inspected building is fit for occupation and records completion on 17 March 2024 and issue of OC 0061/OC/3006/2024 on 17 June 2024. The project’s RERA certificate nevertheless records registration validity through 8 March 2027, and the promoter’s Form B declares that date as its completion undertaking. These dates describe different records and statuses; the evidence does not provide a current independent site-progress assessment.
3. Master plan, architecture & building design
The building permit records a 2023.36 m² site, 4,508.55 m² of residential area, a 1 Stilt + 5 upper-floor configuration and a stated building height of 17.94 m. The occupancy-certificate extraction records 4,508.55 m² floor area as per sanctioned plan and a height of 14.95 m as per sanctioned plan. These figures are quoted as stated in the respective records; no further area or height measurement is derived here.
The permit identifies one proposed residential building, and the occupancy certificate identifies a residential apartment building with stilt and five upper floors. The permit also records cellar and stilt parking provisions, but the supplied material does not establish a parking-space count, floor-by-floor apartment arrangement, footprint, lift or stair count, or detailed circulation plan.
The permit records 14% open space and a 110.48 m² tot-lot. It also calls for a transformer space, garbage house and rainwater-harvesting structure. No detailed landscape plan, internal-road plan or phase organization is provided in the supplied evidence.
4. Homes, configurations & floor plans
TG-RERA records 40 apartments across two configurations. The filed saleable-area figures are presented below as recorded; the evidence does not provide measured carpet areas for these RERA-filed 2BHK and 3BHK configurations.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 30 | 0 | 30 | 22.67 m² | Not measured for this configuration in supplied drawings | Not supplied |
| 3BHK | 10 | 0 | 10 | 86.4 m² | Not measured for this configuration in supplied drawings | Not supplied |
The booking and availability figures are from the TG-RERA portal record; no as-of date is included.
The floor-plan measurement data identifies a 1BHK drawing configuration in document 181767, measured by software from the drawing geometry, with a median carpet area of 64.5 m² and a range of 64.0–65.0 m². It is not identified as a TG-RERA-filed configuration and should not be treated as part of the filed unit inventory. The drawing measurement is flagged as needing review.
Carpet area and saleable area are distinct measures: the supplied floor-plan note says saleable area includes the home’s share of common areas, while the drawing-derived carpet measurement is software-measured and not a RERA disclosure. No loading figure is supplied.
5. Parking & vehicle circulation
The building permit states that cellar and stilt areas approved for parking are to be used exclusively for vehicle parking and not partitioned or repurposed. The extracted permit parameters identify a stilt area of 992.48 m². The occupancy-certificate extraction records parking area of 110.48 m². No total car or two-wheeler space count, visitor or accessible-space provision, mechanical parking, EV charging, ramp arrangement, or unit-wise parking allocation is supplied.
The promoter-supplied vendor record lists “Open Parking” and “Covered Parking,” but provides no counts or allocation details; these are not evidence of a legally documented exclusive parking allotment.
6. Amenities, recreation & open spaces
The sanctioned building-permit extraction specifies a 110.48 m² tot-lot, records open space as 14%, and calls for a transformer space, garbage house and rainwater-harvesting structure. The RERA amenity record lists project infrastructure and facilities with declared progress percentages; these are reported portal fields, not independent completion verification.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green space | Tot-lot: 110.48 m²; permit records 14% open space | Permit requirement recorded; RERA amenity progress 0%; independently completed status not established | |
| Water supply | No source, storage or capacity specified | RERA amenity progress 50%; completion not independently verified | |
| Sewerage | Listed as “Sewerage (Chamber, Lines, Septic Tank, STP)”; specific installed system not established | RERA amenity progress 50%; completion not independently verified | |
| Internal roads and footpaths | No dimensions or plan details supplied | RERA progress 0% | |
| Storm-water drains | No design or capacity supplied | RERA progress 0% | |
| Street lighting | No specification supplied | RERA progress 0% | |
| Rainwater harvesting / water conservation | Permit calls for a rainwater-harvesting percolation pit; no capacity supplied | RERA progress 0%; completion not independently verified | |
| Community buildings | No facility details or size supplied | Progress 0% | |
| Solid-waste management and disposal | Permit calls for a garbage house; no capacity or operating details supplied | RERA progress 0%; completion not independently verified | |
| Recreational open space | Aggregate area not specified beyond permit’s 14% open-space record and 110.48 m² tot-lot | RERA progress 0%; completion not independently verified |
No clubhouse or indoor-recreation facility is evidenced in the supplied project records.
7. Utilities, building services & safety
The permit calls for a transformer space, rainwater-harvesting percolation pit and garbage house. The RERA amenity record lists water supply, sewerage, storm-water drainage, energy management, fire protection and electrical meter room/sub-station/receiving station, but does not provide capacities, equipment specifications or commissioning evidence.
The occupancy-certificate extraction identifies the building as fit for occupation, but the supplied materials do not detail water source or storage, sewage-treatment and reuse arrangements, electrical backup, lift count or capacity, fire-fighting systems, escape-stair configuration, accessibility features, CCTV or access-control arrangements. No such technical specification is inferred from the certificate or amenity listing.
8. Location, access & connectivity
The project identity places DESHAI TOWERS in Hanamkonda, Warangal Urban, PIN 506001. The land boundary record identifies a 12M ROAD to the south. The title documents refer to Waddepally Revenue village, and the OC extraction identifies Gopalpur, Hanamkonda mandal, Warangal (Urban) district.
The supplied location record provides a cadastral parcel-centroid coordinate of 17.41528, 78.35459 and lists Financial District (Nanakramguda) at 1.2 km. The evidence provides no measured route, travel time, public-transport details or approach-road description beyond the recorded southern road boundary.
9. Developer & development status
The registered promoter is SRI MUDRA CONSTRUCTIONS, recorded as a partnership. Its project filing lists registered office details at Sri Nilayam, Chaitanyapuri Colony, Jawahar Nagar, Hanamkonda, Warangal Urban, PIN 506001. The project record identifies two authorised signatories, Satyanarayana Reddy Chandupatla and Krishna Koutam, and lists four other partners.
The promoter’s Form B affidavit, dated 25 February 2021, declares a completion undertaking of 8 March 2027 and states that the project land is free from encumbrances. These are promoter declarations in the filing. The RERA certificate records registration validity through 8 March 2027.
The supplied records do not state a current construction-progress percentage. The occupancy-certificate extraction records completion on 17 March 2024 for the building it identifies; it does not provide a current site inspection or unit-by-unit status.
10. Approvals, official records & documents
| Identifier / date | P00300003458; issued 24 September 2021; valid through 8 March 2027 |
|---|---|
| Scope and evidence | Form C for DESHAI TOWERS, with promoter conditions including the separate-account requirement |
| Identifier / date | 3006/26751/W31/2020; 8 March 2021 |
|---|---|
| Scope and evidence | Permit for a residential building at survey numbers 22 (NEW), 900 (OLD); includes sanctioned configuration and site conditions |
| Identifier / date | 0061/OC/3006/2024; 17 June 2024 |
|---|---|
| Scope and evidence | GWMC certificate for the residential apartment building at survey numbers 22 (NEW), 900 (OLD); the extraction records completion on 17 March 2024 |
| Identifier / date | Dated 26 July 2021 |
|---|---|
| Scope and evidence | Advocate S. Jayachandra’s title search report for the land identified as survey numbers 22 (New), 900 (Old), Waddepally |
| Identifier / date | 15696/2021; 15 June 2021 |
|---|---|
| Scope and evidence | Owner–developer development document for the identified survey land |
| Identifier / date | 25 February 2021 |
|---|---|
| Scope and evidence | Promoter affidavit containing project declarations and a completion undertaking |
The supplied evidence does not include an extracted approved-layout drawing or a detailed floor-plan description sufficient to establish apartment-level layouts, circulation, or technical service specifications. The building-permit and occupancy-certificate records above are the available project approval records used in this Overview.
Frequently asked questions
Is DESHAI TOWERS registered with Telangana RERA?
Yes. DESHAI TOWERS is registered with the Telangana Real Estate Regulatory Authority as P00300003458; the registration status is New Project.
Who is the developer of DESHAI TOWERS?
The promoter named in the RERA registration is SRI MUDRA CONSTRUCTIONS.
Where is DESHAI TOWERS located?
DESHAI TOWERS is in HANAMKONDA, Telangana (506001).
When will DESHAI TOWERS be completed?
The promoter's proposed date of completion filed with RERA is 08/03/2027. This is the promoter's declaration, not a guarantee.