Sign in

Sansa County Phase - I

AUROBINDO TATTVA TOWNSHIP DEVELOPERS LLP · Sangareddy · RERA P01100005179

SANSA COUNTY PHASE - I is a residential project at Peddakanjarla Village, PATANCHERU Mandal, Sangareddy District. The registered promoter is AUROBINDO TATTVA TOWNSHIP DEVELOPERS LLP. Phase I is approved over Ac. 95.09 and includes 953 residential villas at Ground + 2 upper floors, 120 LIG units in three blocks at Stilt + 5 upper floors, and a Work Centre / Office at Cellar + Ground + 3 upper floors; RERA-filed configurations are 1BHK, 2BHK and 3BHK. The TG-RERA registration is P01100005179, and the proposed completion date is 27/01/2028.

More from Aurobindo Tattva Township Developers LLP · 5 projects →

01What we found

RegisteredTG-RERA - valid till 27 Sep 2027
47documents on file - each fact links to its page
3court cases on this project's land (survey 120, 121, 125, Peddakanjarla)
11items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

11 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

FieldRecord
Registered project nameSANSA COUNTY PHASE - I RERA record
Project typeResidential in the TG-RERA project record; the HMDA sanction describes an Integrated Township with residential, LIG and work-centre uses. RERA record
Phase / registered portionPhase I; HMDA records Phase-I over Ac. 95.09 out of a total township area of Ac. 460. RERA record
TG-RERA registrationP01100005179, granted 13/10/2022; certificate states a four-year validity period ending 27/09/2027. This is registration validity, not the completion deadline. RERA record
Registered promoterAUROBINDO TATTVA TOWNSHIP DEVELOPERS LLP RERA record Corporate record
RERA statusNew Project; registration certificate records registration under section 5. The supplied record does not establish an extension. RERA record

Land and geographic identity

FieldRecord
Locality / revenue villagePeddakanjarla Village; also rendered “Peddakanjerla” in filed land records. RERA record Land records
Mandal / district / PINPATANCHERU / Sangareddy / 502319. RERA record RERA filing
Project survey numbers120, 121, 123, 124 & 125; the HMDA approval also writes them as Sy.No.120, Sy.No.121, Sy.No.123, Sy.No.124 and Sy.No.125. RERA record Land records
SubdivisionsThe overall project identity does not provide a complete subdivision schedule. Filed title and encumbrance records refer to portions including 120/38/1/1, 120/45/2, 120/110/1, 120/110/2, 120/112/2, 120/112/3, 120/117/A, 120/118, 120/119, 120/120, 120/122/2 and 120/130. These are record references, not a confirmation that the list exhausts every subdivision in the approved site. Land records
Registered land areaRERA land details state 274174.52 sq.mts total and net area, with 0 area affected in road widening/FTL/Nala widening. RERA filing Land records
Phase-I sanctioned site areaHMDA approval states Ac. 95.09 for Phase I; its area statement separately records Ac 94.27 net site area and Ac. 0.82 Nala area.
Boundaries in RERA filingEast: OTHER LAND; West: OTHER LAND; North: OTHER LAND; South: ROAD WIDTH. RERA filing
HMDA area-statement componentsGreen Area: 38,983.57 sq.mts; 4,19,619.15 Sft; 9.63 acres; Nala 01 buffer area: 1,300.34 sq.mts; 13,996.86 Sft; 0.32 acres; villa plots: 1,59,606.96 sq.mts; 17,18,009.32 Sft; 39.44 acres; club house land: 7,944.17 sq.mts; 85,511.07 Sft; 1.26 acres; services land: 1,883.33 sq.mts; 20,272.17 Sft; work centre: 72,862.23 sq.mts; 7,84,289.09 Sft; 18.00 acres; LIG: 5,083.71 sq.mts; 54,721.05 Sft; roads: 93,851.11 sq.mts; 10,10,213.37 Sft; 23.19 acres.

Development identity

FieldRecord
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA), Planning Department. Approvals record
Principal approvalIntegrated Township approval 35/LO/PLG/HMDA/2022, dated 27.09.2022; proceedings 01/Plg/Township/2022; file SIA/TG/MIS/78390/2022. Approvals record
Approved built-up areaRERA project fields record 226415.78 sqmts approved built-up area. The supplied HMDA approval extract does not provide a single overall approved built-up-area total for Phase I. RERA filing
Buildings / units in RERA fieldsRERA fields state 955 total building units as per approved plan and 955 proposed building units as per agreement. RERA filing
Uses and floors in HMDA Phase-I approval953 residential villas, Ground + 2 upper floors; 120 LIG units in three blocks, Stilt + 5 upper floors; Work Centre / Office, Cellar + Ground + 3 upper floors.
Parking / basement and podium levelsNo project-wide parking count or complete parking-level schedule is stated in the supplied Phase-I approval extract. It does identify a cellar in the Work Centre / Office configuration.
RERA mortgage-area field22302.72 sqmts recorded as mortgage area. RERA filing

Offering and status

FieldRecord
RERA-filed configurationsNormalised RERA unit data identifies 1BHK, 2BHK and 3BHK configurations; the filing also contains rows that could not be reliably classified as a home configuration. RERA unit table RERA unit details
Booked / available countsRERA portal-derived counts are indicative; the record has no as-of date. Normalised configuration counts: 1BHK 951 (849 booked, 102 available); 2BHK 953 (851 booked, 102 available); 3BHK 1 (1 booked, 0 available). RERA unit table RERA unit details
Saleable area recorded for configurations1BHK: 99.89–100.78 sq.m; 2BHK: 96.48–107.87 sq.m; 3BHK: 99.63 sq.m. These are RERA-filed saleable areas, not carpet-area measurements. RERA unit table RERA unit details
Completion date / undertakingRERA project fields state proposed completion 27/01/2028. The Form B declaration dated 30 September 2022 records a completion undertaking for Sansa County (Ph-1), 953 villas & 2 Clubhouses, with completion date 27-September-2027. RERA filing
Construction stageNo reliable construction-progress percentage or independently verified site-stage report is supplied. The RERA amenities table marks listed infrastructure as available “YES” but shows 0 progress for each recorded item. RERA amenities
OC / completion certificateNo occupancy or completion certificate for Phase I or for individual buildings/towers is supplied in the reviewed records. Document index

2. The project story

The TG-RERA-registered Phase I is recorded as a residential project at Peddakanjarla Village, Patancheru Mandal, Sangareddy District, on project land identified as Sy.Nos. 120, 121, 123, 124 and 125. HMDA’s township approval describes a broader mixed township scheme and identifies Phase I as Ac. 95.09 within a total township area of Ac. 460. RERA record Land records

The HMDA Phase-I approval describes 953 residential villas, 120 LIG units in three blocks, and a Work Centre / Office. Its land-use statement includes villa plots, LIG, work-centre, club-house and services land, green area, a Nala buffer area and roads. The supplied materials do not establish that these approved components are completed or occupied.

The registration certificate remains valid through 27/09/2027 unless extended; the project information field gives a proposed completion date of 27/01/2028. These are separate records and dates. The supplied evidence includes no occupancy certificate and no verified construction-progress assessment, so current build stage and completion of any phase or building cannot be confirmed from this material. RERA filing Document index

3. Master plan, architecture & building design

HMDA’s approval is for an Integrated Township, Phase I. It records a site area of Ac. 95.09, a net site area of Ac 94.27 and Ac. 0.82 identified as Nala Area. The approval’s land-use statement assigns 41.83% to villa plots, 19.10% to the work centre, 1.33% to LIG, 24.60% to roads, 10.22% to green area, 2.08% to club-house land, 0.49% to services land and 0.34% to Nala 01 buffer area; the same document also lists parks, gardens and playgrounds including Nala buffer as 9.95 Ac (10.56%).

The approved Phase-I building descriptions are 953 villas at Ground + 2 upper floors, three LIG blocks with 120 units at Stilt + 5 upper floors, and a Work Centre / Office at Cellar + Ground + 3 upper floors. The project fields separately record approved built-up area of 226415.78 sqmts. The supplied materials do not provide a complete Phase-I building-by-building floor schedule, overall FSI-counted area, villa-by-villa layout, or comprehensive dimensioned layout drawing. RERA filing

Filed HMDA technical drawings show villa types labelled East Facing Type-1, West Facing Type-2 and East Facing Type-2, with Ground, First and Second floor plans. The drawings describe technical approval / forwarding for local-body final sanction subject to stated conditions; they are not a complete township layout or proof that every villa type has final sanction.

The supplied clubhouse drawings include a technical approval record for Clubhouse-1 and sanction-drawing material for Clubhouse-2. The Clubhouse-2 drawing identifies “B+C+I” floors; a separate sheet is identified as Club House-2, Sections A&B. These drawing extracts do not establish the completed condition of either clubhouse.

4. Homes, configurations & floor plans

The table below uses normalised TG-RERA configuration data. Bookings and availability are indicative because the portal record carries no as-of date. The supplied approved floor-plan drawings are scans pending measurement: no software-measured carpet area or room-dimension data is available. RERA unit table RERA unit details Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
1BHK95184910299.89–100.78 sq.mNot measuredNot supplied
2BHK95385110296.48–107.87 sq.mNot measuredNot supplied
3BHK11099.63 sq.mNot measuredNot supplied
Homes (configuration not filed; filed labels include “1 ST FLOOR”, “97.10”, “GROUND FLOOR” and “THEATREROOM”)104635.6–1324.84 sq.m as recorded across those rowsNot measuredNot supplied

The filed unit table also includes many “THEATRE ROOM” variants and floor labels that are not counted here as home configurations. The available data does not establish their intended use beyond the normaliser’s classification notes. The RERA saleable-area figures should not be read as carpet-area figures: the supplied drawing-measurement record states that carpet measurement would be software-derived from drawings and would require review, but no drawings have yet been measured. RERA unit table RERA unit table Floor plans

5. Parking & vehicle circulation

The HMDA Phase-I approval extract does not state a project-wide sanctioned parking-space count, resident or visitor allocation, accessible parking provision, or a complete parking-level plan. It identifies a cellar in the Work Centre / Office configuration. The RERA filing extract and supplied documents do not establish parking allocations for an individual unit; no parking allotment arrangement can be confirmed here. RERA unit table Document index

The Clubhouse-1 technical-approval extract contains a parking-area reference, but its figures are not sufficiently clear in the supplied extraction to report as a reliable sanctioned count or area. A parking bay shown in a drawing would not by itself establish an exclusive allotment.

6. Amenities, recreation & open spaces

The HMDA approval identifies township land for green area, roads, club-house, services and a Nala buffer, and lists school, sports complex, market, resort/retreat, office space and services among the proposed township uses. The approval states that details for the School, Sports Complex, Market and Resort/Retreat proposed as part of the Work Centre were to be submitted within six months. The supplied material does not establish the delivery or current operating status of these facilities.

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Club houseClub house land area: 7,944.17 sq.mts; 85,511.07 Sft; 1.26 acres in the approval’s land-use statement; HMDA-filed drawings identify Clubhouse-1 and Clubhouse-2.HMDA approval and filed drawingsApproved / drawing-recorded; completion not verified.
Green area38,983.57 sq.mts; 4,19,619.15 Sft; 9.63 acres.HMDA approvalAllocated in approval; landscaping completion not verified.
Parks, gardens and playgrounds including Nala buffer9.95 Ac (10.56%).HMDA approvalRecorded as planned allocation; completion not verified.
Nala 01 buffer1,300.34 sq.mts; 13,996.86 Sft; 0.32 acres.HMDA approvalRecorded in approval; site condition not independently verified.
School4-00 acres.HMDA approvalIdentified as a proposed Work Centre component; separate detail plans were required by the approval. Completion not verified.
Sports complex6-00 acres.HMDA approvalIdentified as a proposed Work Centre component; separate detail plans were required by the approval. Completion not verified.
Market1-00 acres.HMDA approvalIdentified as a proposed Work Centre component; separate detail plans were required by the approval. Completion not verified.
Resort & retreat3-00 acres.HMDA approvalIdentified as a proposed Work Centre component; separate detail plans were required by the approval. Completion not verified.
Services land1,883.33 sq.mts; 20,272.17 Sft.HMDA approvalLand-use allocation recorded; facility delivery not verified.
Internal roads93,851.11 sq.mts; 10,10,213.37 Sft; 23.19 acres in the approval’s land-use statement.HMDA approvalApproved allocation; construction and handover status not verified.

The separate amenities filing lists infrastructure categories including internal roads and footpaths, water supply, sewerage/STP, storm-water drains, green strip/park, street lighting, community buildings, sewage and sullage treatment, solid-waste management, rainwater harvesting, fire protection, electrical meter room/sub-station and recreational open space. It records 0 progress for each item; this is a filed status entry, not independent site verification. RERA amenities

7. Utilities, building services & safety

HMDA’s approval requires the developer to develop a drinking-water source excluding groundwater, or secure a firm commitment from the relevant water authority, with a stated minimum requirement of 140 liters per capita per day and storage capacity of at least 1.5 times the actual required quantity. It also requires internal distribution and maintenance systems, rainwater harvesting, groundwater recharge and wastewater recycling. These are approval conditions; supplied evidence does not verify installation or operation.

The approval states a zero-discharge concept for waste, requires sewage and solid-waste treatment/disposal, use of recycled water for gardening, and that no liquid waste goes out. It also requires compost from solid waste to be used within the township and non-biodegradable waste to be handled through an agency, subject to stated approvals. No STP capacity, water-treatment capacity, operating data or completion certificate is supplied.

For power, HMDA requires continuous and quality supply, and a firm commitment from TSSPDCL if an existing supply system is used. It also requires ECBC/IGBC compliance for the township’s non-residential buildings and cool roofs for residential buildings. The approval requires underground storm-water drains, cabling and public-utility lines, and lists street lighting, drainage, roads and rainwater-harvesting structures among infrastructure requirements. These are requirements recorded in the approval, not evidence of completed systems or statutory compliance.

The amenities filing lists fire-protection and fire-safety requirements, but the supplied material does not detail installed systems, clearances, evacuation arrangements, lift numbers or capacities, accessibility provisions, CCTV/access control, or waste-collection operations for Phase I. RERA amenities Document index

8. Location, access & connectivity

The registered project location is Peddakanjarla Village, Patancheru Mandal, Sangareddy District, Telangana, PIN 502319. The project record supplies no verified approach-road description, public-transport route or measured distance to local services. RERA record RERA filing

A supplied location record gives a cadastral parcel-centroid coordinate of 17.41528, 78.35459. It also lists Financial District (Nanakramguda) at 1.2 km as an anchor, but the supplied data does not establish a measurement method or travel time for that distance. Location record

9. Developer & development status

The registered promoter is AUROBINDO TATTVA TOWNSHIP DEVELOPERS LLP, an LLP, with GSTIN 36ABUFA5646B1ZB. The promoter address in the project record is B, MIYAPUR, PATANCHERU MANDAL, PEDDAKANJARLA VILLAGE, PATANCHERU, Sangareddy, 502319. The supplied corporate record identifies VANGAVARAGU RAMIREDDY VENKATA as authorised signatory and GAJAVALLI TULASI SAMBHU LINGESWARA PRASAD and TARAKA RAMA RAJU ALLURI as partners. Corporate record Parties record RERA filing

The project Form B declaration, dated 30 September 2022, records the promoter’s undertaking to complete Sansa County (Ph-1), described there as 953 villas and 2 Clubhouses, by 27-September-2027. The project information field separately records proposed completion on 27/01/2028. The supplied evidence does not include a verified construction-progress report, an OC, or a certificate confirming completion of any Phase-I building. RERA filing Document index

The project record lists a website for the promoter at https://tattvadevelopers.com/projects/sansa-county/. No official contact telephone number or email is supplied in the reviewed project data. Parties record

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP01100005179; issued 13/10/2022; valid to 27/09/2027
What the supplied record establishesForm C records registration of SANSA COUNTY PHASE - I and its stated validity period.
HMDA Integrated Township approval
Identifier / date35/LO/PLG/HMDA/2022; 27.09.2022; proceedings 01/Plg/Township/2022; file SIA/TG/MIS/78390/2022
What the supplied record establishesApproval for Phase I over Ac. 95.09 in the township, with land-use allocations, development components and conditions. The approval expressly says it is not proof of land title.
Environmental-clearance reference stated in HMDA approval
Identifier / dateEC22B039TG168243, file SIA/TG/MIS/78390/2022, dated 27.09.2022
What the supplied record establishesThe HMDA approval cites this environmental-clearance identifier and requires compliance with its conditions. The supplied extract is not the environmental-clearance decision itself.
Villa technical-approval drawings
Identifier / dateVilla East Facing Type-1; Villa West Facing Type-2; Villa East Facing Type-2
What the supplied record establishesFiled drawings show villa plans and identify HMDA technical approval / local-body forwarding subject to stated conditions.
Clubhouse drawings
Identifier / dateClubhouse-1 and Clubhouse-2
What the supplied record establishesSupplied records include a clubhouse technical approval and clubhouse drawings; the extracts do not establish completion or operation.
Form B promoter declaration
Identifier / date30t day of September 2022
What the supplied record establishesPromoter declaration for Sansa County (Ph-1), including completion undertaking and project-fund, audit and approval undertakings.
Occupancy / completion certificate
Identifier / dateNot supplied
What the supplied record establishesNo OC or completion certificate for Phase I or a specific building is present in the reviewed evidence. Document index

The HMDA approval records six mortgage deeds dated 24.09.2022: 33048/2022, 33045/2022, 33044/2022, 33049/2022, 33047/2022 and 33046/2022, in favour of the Metropolitan Commissioner, HMDA, covering the listed villas and portions of the Work Centre/LIG buildings.

Other registrations of Sansa County

Frequently asked questions

Is SANSA COUNTY PHASE - I registered with Telangana RERA?

Yes. SANSA COUNTY PHASE - I is registered with the Telangana Real Estate Regulatory Authority as P01100005179; the registration status is New Project.

Who is the developer of SANSA COUNTY PHASE - I?

The promoter named in the RERA registration is AUROBINDO TATTVA TOWNSHIP DEVELOPERS LLP.

Where is SANSA COUNTY PHASE - I located?

SANSA COUNTY PHASE - I is in PEDDAKANJARLA VILLAGE, PATANCHERU, Sangareddy, Telangana (502319).

When will SANSA COUNTY PHASE - I be completed?

The promoter's proposed date of completion filed with RERA is 27/01/2028. This is the promoter's declaration, not a guarantee.

More projects in Patancheru