ARYA HOMES is a plotted development in Dabilguda and Mansanpally, Maheshwaram mandal, Ranga Reddy district. The registered promoter is DECCANPLATUE INFRASTRUCTURE PRIVATE LIMITED. The layout has a site extent of 85,093.62 sq.m and is read from the drawing as containing 105 residential plots; drawing-derived plot sizes range from 319.4 sq.m to 1,496.67 sq.m. It is registered under TG-RERA number P02400007649, with proposed completion on 08/08/2024.

01What we found

Period endedTG-RERA registration ran to 8 Aug 2024 - check its extension on TG-RERA
35documents on file - each fact links to its page
0court cases on this project's land in the court records searched
11items to check - 5 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

11 items to check before you pay, 5 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Dabilguda, Maheshwaram, Ranga Reddy · geocoded — approximate.

1. Project at a glance

Project identity

ItemProject record
Registered nameARYA HOMES RERA record
Project typePlotted development / draft open-plot layout RERA record
Phase or registered portionThe registration identifies the project across the stated survey numbers; no separately named phase is disclosed.
TG-RERA registrationP02400007649
Registration validity29/01/2024 to 08/08/2024; the certificate states “0 years.” This is the registration-validity period, separate from the completion undertaking. No extension is recorded in the supplied certificate. Approvals record
Registered promoterDECCANPLATUE INFRASTRUCTURE PRIVATE LIMITED (also rendered “Deccan Platue Infrastructure Pvt Ltd” in filed documents) RERA record Corporate record
RERA status in supplied recordThe certificate records registration; the supplied materials do not establish a later extension or current registration status. Approvals record

Land and geographic identity

ItemProject record
Locality / revenue villagesDabilguda; Mansanpally (also rendered “Mansanpalle” in the draft-plan document). The registration certificate says “Dabilguda and Mansanpally.” RERA record
MandalMaheshwaram (also rendered “Maheswaram” in the draft-layout document) RERA record
DistrictRanga Reddy RERA record
PIN509325 RERA record
Project survey numbers14PART, 15PART of Dabilguda and 327 of Mansanpally; the registration certificate and layout documents also list them as 14PART, 15PART and 327. RERA record
Registered site extent85,093.62 sq.m RERA filing
Net / total areaTotal site area 85,093.62 sq.m and net site area 85,093.62 sq.m in the draft-layout land statement.
Boundaries recorded in RERA fieldsEast: 100 FEET ROAD; west: 60 FEET ROAD; north and south: OTHERS LAND. RERA filing

Development identity

ItemProject record
Sanctioning authorityHyderabad Metropolitan Development Authority (HMDA) Approvals record
Principal approvalDraft layout permit 000138/LO/Plg/HMDA/2022, dated 16 July, 2022 Approvals record
Application / file reference049443/SMD/LT/U6/HMDA/07102021 Approvals record
Approved built-up areaRERA fields record 51,067.16 sq.m as approved built-up area; the layout plan identifies 51,067.16 sq.m as plotted area. These are the figures and labels in the supplied record, not a building-area specification. RERA filing
Buildings / floor configurationNot applicable to the filed open-plot layout; no building count, floor configuration or parking levels are disclosed.
Plot count105 plots, read from plot numbers and areas printed on the approved layout drawing; software-read and subject to drawing verification. Layout record
HMDA-mortgaged plotsPlots 25–42, extent 7,735.68 sq.m, identified as mortgaged to HMDA pending development works and release.

Offering and status

ItemProject record
OfferingResidential plots; no RERA-filed plot-wise unit schedule or RERA saleable-area range is supplied in this evidence.
Drawing-based plot sizesSoftware-read range: 319.4–1,496.67 sq.m (382–1,790 sq.yd); median 418.06 sq.m (500 sq.yd). These are drawing-derived measurements, not RERA-filed unit figures. Layout record
Booked / availableNot disclosed in the supplied project evidence. Document index
Construction / development stageNo independently verified site-progress record is supplied. RERA-filed progress fields show varying percentages for infrastructure items; these are reported progress figures, not independent site verification. RERA amenities
Completion dateRERA registration records a proposed completion date of 08/08/2024; the supplied Form B extraction contains a truncated completion undertaking, so its text cannot be read reliably. RERA filing
Occupancy / completion certificateNo occupancy or completion certificate is included in the supplied documents. The project is a plotted layout; no phase- or plot-specific OC status is established here. Document index

2. The project story

ARYA HOMES is registered as a residential plotted development at Dabilguda, Maheshwaram, Ranga Reddy district, covering survey land recorded as 14PART and 15PART of Dabilguda and 327 of Mansanpally. The filed HMDA material describes a draft open-plot layout, with a layout permit dated 16 July 2022 and a site extent of 85,093.62 sq.m. RERA record

The approved drawing is read as showing 105 plots. Plot numbers and sizes were extracted by software from the drawing; they should be checked against the original sheets. The available materials do not provide a reliable project-wide count of booked plots or an independently verified account of completed infrastructure. The RERA filing reports progress percentages for selected infrastructure categories, but those figures are not proof of on-site completion. Layout record RERA amenities

3. Master plan, architecture & building design

This is an open-plot layout, not a multi-storey building scheme in the supplied approval documents. The HMDA draft-layout material gives a total and net site area of 85,093.62 sq.m and identifies 51,067.16 sq.m as plotted area. The drawing-derived land-use statement also identifies 23,784.64 sq.m of roads, 7,245.11 sq.m of parks/open space, 491.64 sq.m of utilities and 2,128.01 sq.m of social infrastructure. The project-level layout extraction labels the 7,245.11 sq.m figure as “Parks / open space”; the draft approval separately lists park and social-infrastructure areas. Layout record

The layout drawing is software-read as showing 105 plots across two sheets. Plot-size bands are: 2 plots at 300–400 sq.yd, 78 at 400–500 sq.yd, 17 at 500–1,000 sq.yd and 8 at 1,000+ sq.yd. The drawing-derived median is 500 sq.yd. These plot counts and areas are software-measured from the drawing and are not a RERA-filed plot schedule. Layout record

The RERA fields record 51,067.16 sq.m as “Approved Built up Area”; the layout record labels that same figure “Plotted Area.” No separate building gross area, FSI-counted area, carpet area, or saleable built-up area is disclosed for this plotted project. RERA filing

4. Homes, configurations & floor plans

No apartment or villa configuration schedule is supplied. The offering is plots. The layout drawing was read by software as containing 105 plots, with the following size bands; these are drawing-derived, not a RERA-filed saleable-area schedule. Layout record

Plot-size bandPlotsEvidence / measurement basis
300–400 sq.yd (251–334 sq.m)2Software-read from approved layout drawing Layout record
400–500 sq.yd (334–418 sq.m)78Software-read from approved layout drawing Layout record
500–1,000 sq.yd (418–836 sq.m)17Software-read from approved layout drawing Layout record
1,000+ sq.yd (836+ sq.m)8Software-read from approved layout drawing Layout record

The smallest, median and largest software-read plot areas are 319.4 sq.m (382 sq.yd), 418.06 sq.m (500 sq.yd) and 1,496.67 sq.m (1,790 sq.yd), respectively. No carpet-area measurement applies to the plots. Layout record

5. Parking & vehicle circulation

The supplied project evidence does not establish a parking-space count, visitor or accessible parking provision, parking allocation to individual plots, or EV-charging provision. The layout drawing is described as an open layout without an enclosing compound wall; its approval material specifies road provision and accessibility conditions, but does not provide a verified parking schedule.

HMDA’s draft-layout conditions require roads to be opened for access to neighbouring sites and prohibit a compound wall or fencing around the site. The approval material refers to road widths of 18 mts and above and 60 feet and above; the drawing extraction also records road-width values 30.00 and 12.19m.

6. Amenities, recreation & open spaces

The filed draft-layout approval identifies layout land allocations and infrastructure requirements. The RERA progress record reports percentages for certain categories; the percentages below are filing-reported, not independent verification of completion. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Park / open space7,245.11 sq.m; draft approval records 8.51% for parkHMDA draft-layout approvalRERA progress record: Green Strip/TOT LOT/Park 50%; not independently verified RERA amenities
Social infrastructure2,128.01 sq.m; draft approval records 2.50%HMDA draft-layout approvalNo delivery verification supplied
Amenities area866.46 sq.m in draft approvalHMDA draft-layout approvalNo delivery verification supplied
ClubhouseNo size or capacity statedLayout-plan extractionRERA progress record: Community Buildings 0%; no independent verification RERA amenities
Cycling trackNo size statedLayout-plan extractionNo completion verification supplied
Avenue plantation / landscaped open spaceRequired by draft-layout conditions; no planting quantity or area stated beyond the open-space allocationHMDA draft-layout approvalRERA progress record: Green Strip/TOT LOT/Park 50%; not independently verified RERA amenities

The promoter/vendor materials list a swimming pool, gym, children’s play areas, landscaped greens, community hall and clubhouse. These are vendor/marketing claims, not established as sanctioned or delivered facilities in the supplied project records. Promoter website

7. Utilities, building services & safety

The HMDA draft-layout approval specifies infrastructure obligations, including internal water-supply pipelines, an overhead tank, a common septic tank/STP, underground storm-water drainage, underground ducting for utilities, a transformer yard, LED street lighting, a bio-compost unit, rainwater-harvesting pits and source segregation of garbage. These are approval requirements or plan features; the supplied record does not independently verify their installation or operation.

The approval also requires arrangements for potable-water connectivity to an approved trunk/connecting pipeline, solid-waste disposal space and avenue planting. It specifies a sewerage-treatment provision for a layout site of more than 10 acres and a septage-treatment mechanism for layouts under 10 acres. The approval document lists both a common septic tank/STP and STP-related plan features; the supplied evidence does not establish which facilities are completed or their capacity.

RERA-filed infrastructure progress includes water supply 80%, sewerage 100%, storm-water drains 90%, rainwater harvesting 80%, street lighting 60%, internal roads and footpaths 100%, and green strip/TOT LOT/park 50%. These are declared progress figures, not independent verification. The same progress record lists treatment and disposal of sewage and sullage water 0%, fire protection and fire safety requirements 0%, and electrical meter room/sub-station/receiving station 0%. RERA amenities

No project-specific evidence establishes fire-safety systems, emergency access, accessibility features, lift services, backup power, CCTV, security access systems, or utility capacities. The vendor’s “24x7 security” claim is not confirmed by the supplied RERA-filed or approval records. Promoter website Document index

8. Location, access & connectivity

The registered project location is Dabilguda, Maheshwaram mandal, Ranga Reddy district, PIN 509325, with land also identified in survey 327 of Mansanpally. The RERA fields record the site as bounded by a 100 FEET ROAD on the east and a 60 FEET ROAD on the west. RERA record RERA filing

The cadastral parcel centroid supplied for survey 14PART is 17.156351953827752, 78.38325100118747. The nearest sampled Outer Ring Road interchange is approximately 9.6 km away. Cadastral map Location record

Vendor material names Nizamabad Road (NH 44) and the Nehru Outer Ring Road, and gives distances to Sant Sevalal Temple (1.75 km), Ramarao X Road (1.72 km), Sanjoe Public School (5.41 km) and Institute of Management Technology Hyderabad (5.73 km). These are vendor-supplied location claims; no travel times are established in the supplied evidence. Promoter website

9. Developer & development status

The registered promoter is DECCANPLATUE INFRASTRUCTURE PRIVATE LIMITED, a private limited company, GSTIN 36AACCD4140M2ZN. The project’s RERA materials identify K Narsing Rao as authorised signatory. RERA record Corporate record Parties record

The registration certificate gives the promoter-office address as Village: Guttala begumPet, Mandal: Serilingampally, District: Ranga Reddy, Pin: 500081. The project record separately lists an address at Flat No. 402, Fourth Floor, Plot No. 119, Ivy Terrace, Kavuri Hills. RERA filing

The RERA filing records proposed completion as 08/08/2024. The registration certificate is valid only through 08/08/2024, and the supplied certificate does not record an extension. No independently verified construction or infrastructure-completion status, and no occupancy or completion certificate, is included. The vendor’s description of the project as completed is a vendor claim, not verified completion evidence. RERA filing Document index Promoter website

10. Approvals, official records & documents

RecordWhat the supplied material establishes
TG-RERA certificateForm C registration for ARYA HOMES, P02400007649, issued 29/01/2024; validity stated through 08/08/2024.
HMDA draft layout letterDraft open-plot layout permit 000138/LO/Plg/HMDA/2022, dated 16 July, 2022, for the stated survey land; includes conditions for infrastructure, transfer of specified areas to the local body by registered gift deed, and HMDA mortgage of plots 25–42.
HMDA layout drawingApproved drawing extraction identifies a residential open layout, 105 plots, and layout land-use entries; extraction states that the drawing-derived values should be checked against the original sheets. Layout record
Form B declarationPromoter affidavit by K Narsing Rao for the project; it declares a legal-title basis, land free from encumbrances, and statutory undertakings. The extracted completion undertaking is truncated.
Encumbrance statementsFiled encumbrance-statement documents include IDs 379237–379244 and 382158–382166; the supplied evidence cautions that the parsed statements do not substitute for a fresh current encumbrance certificate. Document index Encumbrance record
Completion / occupancy certificateNo completion or occupancy certificate is included in the supplied project documents. Document index

Frequently asked questions

Is ARYA HOMES registered with Telangana RERA?

Yes. ARYA HOMES is registered with the Telangana Real Estate Regulatory Authority as P02400007649; the registration status is New Project.

Who is the developer of ARYA HOMES?

The promoter named in the RERA registration is DECCANPLATUE INFRASTRUCTURE PRIVATE LIMITED.

Where is ARYA HOMES located?

ARYA HOMES is in DABILGUDA, Maheshwaram, Rangareddy, Telangana (509325).

When will ARYA HOMES be completed?

The promoter's proposed date of completion filed with RERA is 08/08/2024. This is the promoter's declaration, not a guarantee.