Build Urban Aavaas
BUILD URBAN CONSTRUCTIONS · Karimnagar · RERA P02700006331
BUILD URBAN AAVAAS is a residential apartment project in Rampur / Indraprastha Colony, Karimnagar District / 505001; the mandal is not disclosed. The registered promoter is BUILD URBAN CONSTRUCTIONS. The project occupies 668.87 sq.m. and comprises one residential apartment building with 1 stilt + 5 upper floors and 15 2BHK units, each with a recorded saleable area of 70.55 sq.m. Its TG-RERA registration number is P02700006331, and the RERA header lists proposed completion as 30/11/2026.
More from Build Urban Constructions · 3 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
9 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Project record |
|---|---|
| Registered project name | BUILD URBAN AAVAAS RERA record |
| Project type / phase | Residential apartment project; phase or separately identified registered portion: not disclosed. RERA record RERA filing |
| TG-RERA registration | P02700006331; registered from 07/07/2023 to 26/04/2026. The record says registration was not extended; registration validity is distinct from the stated project completion date. RERA record Approvals record |
| Registered promoter | BUILD URBAN CONSTRUCTIONS. RERA record Corporate record |
| RERA-record status | The project is registered. The registration certificate records validity through 26/04/2026; the evidence supplied does not establish a current post-expiry registration status. Approvals record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality | Rampur / Indraprastha Colony, Karimnagar town locality, as stated across the RERA-filed land and approval records. RERA record Land records |
| Revenue village | RERA identity: Rampur. The building approval extraction identifies the village as KARIMNAGAR; the supplied records do not resolve this naming difference. RERA record Land records |
| Mandal | Not disclosed. Land records |
| District / PIN | Karimnagar / 505001. RERA record |
| Survey number(s) and subdivisions | Survey No. 820; title records also describe Sy.No.820/Part and one development-agreement record transcribes it as Sy.No.B20/Part. RERA record Land records |
| Registered plot references | Plots 14, 17 and 19. RERA filing |
| Site extent | 668.87 sq.m. in the RERA land record and approval extraction. Approval extraction separately states Net Area 666.94 sq.m. Land records |
| Boundaries | East: PLOT NO S 18 16 AND 15; west: 9M ROAD; north: PLOT NO 13; south: 9M ROAD. RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Karimnagar Municipal Corporation. Approvals record |
| Principal building approval | 0009/BP/3011/2023, approved 26 April 2023; file number 001069/BP/DTCP/3011/0007/2023. Approvals record |
| Approved built-up area | 1,609.25 sq.m. recorded as residential upper-floor area; the approval also lists 322.27 sq.m. for the stilt. These are the areas as labelled in the approval extraction, not saleable or carpet areas. Approvals record |
| Building count and floors | One residential apartment building, 1 stilt + 5 upper floors; sanctioned height 14.99 m. RERA filing |
| Parking levels | Stilt is approved for parking; no parking-space count is supplied. |
| Approved versus RERA-filed units | Approval conditions say sanctioned unit numbers must not be increased without prior approval, but the supplied approval extraction does not give the sanctioned unit count. The RERA filing lists 15 2BHK units. RERA unit table |
Offering and status
| Field | Project record |
|---|---|
| RERA-filed configuration | 2BHK, 15 units; saleable area 70.55 sq.m. per unit as recorded. RERA unit table RERA unit details |
| Booked / available | 0 booked / 15 available, as last read from the TG-RERA portal; the record gives no as-of date, so these counts are indicative. RERA unit table |
| Construction stage | No project construction-progress figure or independently verified site progress is supplied. RERA amenities |
| Completion date | Promoter’s Form B declaration records a completion date transcribed as “?6.0,4-2026”; a clear original/revised completion date is not established by that extraction. The RERA header lists proposed completion 30/11/2026. RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents. The building approval requires a completion notice and occupancy certificate before occupation. Document index |
2. The project story
BUILD URBAN AAVAAS is a RERA-registered residential apartment project on the recorded site at Rampur, Karimnagar, associated in the land and approval documents with Survey No. 820 and plots 14, 17 and 19. The RERA filing describes a single building and offers 15 two-bedroom apartments; the municipal building approval describes one residential building with a stilt and five upper floors. RERA record Land records RERA unit table
The project’s registration certificate and building-construction approval are on file. The supplied evidence does not establish how much construction has been completed, whether the building is occupied, or whether an occupancy certificate has been issued. The approval’s conditions require an occupancy certificate before occupation.
3. Master plan, architecture & building design
The municipal approval describes a single residential building with 1 stilt + 5 upper floors, a sanctioned height of 14.99 m, residential upper-floor area of 1,609.25 sq.m., and stilt area of 322.27 sq.m. The approval extraction gives a site area of 668.87 sq.m. and net area of 666.94 sq.m.
The approval records a rainwater-harvesting structure, space for a transformer and a garbage house within the premises. It also states that the sanctioned plan must be followed, that construction modifications require prior approval, and that the sanctioned plan is to be displayed at the site.
No detailed floor-by-floor arrangement, building footprint, flats per floor, lift or stair specifications, internal circulation drawing, landscaping plan, or residential/common-area schedule is available in the supplied material. See Homes, configurations & floor plans above for the RERA-filed unit inventory. RERA unit table Document index
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 15 | 0 | 15 | 70.55 sq.m. | Not supplied for this configuration | Not supplied |
The configuration, count, booking status and saleable area are RERA-filed figures; the booking snapshot has no stated as-of date. The supplied drawing-measurement record relates to a 1BHK plan, which is not listed in the RERA filing’s 2BHK inventory. Its software-measured carpet area is 51.0 sq.m. (549 sq.ft.), based on two measured flat designs; it is a drawing-derived measurement, not a RERA disclosure, and is not presented as a measurement of the filed 2BHK units. RERA unit table RERA unit details Floor plans
Carpet area and saleable area are different measures: the supplied measurement note says saleable area includes the home’s share of common areas, while the drawing-based carpet measurement is software-derived and needs review. No RERA-filed carpet area, balcony/utility area, or loading figure for the 2BHK units is supplied. Floor plans RERA unit details
5. Parking & vehicle circulation
The building approval identifies the stilt as a parking level and states that approved stilt parking is to be used exclusively for vehicles, without partition walls or rolling shutters. No sanctioned parking-space count, visitor or accessible-space provision, parking allocation by unit, or parking circulation plan is supplied. A parking level in the approval does not establish an exclusive parking allocation to an apartment.
6. Amenities, recreation & open spaces
The amenity schedule contains 14 listed infrastructure or amenity categories. The RERA record shows 0% progress for each listed category where a percentage is stated. This is a filed progress status, not independent confirmation of site conditions. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot lot / park | Size not supplied; building approval lists tot-lot area as NA. | RERA amenities | RERA schedule: 0%; no independent completion verification. |
| Aggregate recreational open space | Area not supplied. | RERA amenities | RERA schedule: 0%; no independent completion verification. |
| Community buildings | No description or size supplied. | RERA amenities | RERA schedule: 0%; no independent completion verification. |
| Internal roads and footpaths | No dimensions supplied. | RERA amenities | RERA schedule: 0%; no independent completion verification. |
| Street lighting | No further details supplied. | RERA amenities | RERA schedule: 0%; no independent completion verification. |
No clubhouse, indoor recreation or sports facility is specified in the supplied project evidence.
7. Utilities, building services & safety
The RERA amenity schedule marks Water Supply, Sewerage (Chamber, Lines, Septic Tank, STP), Water Conservation, Rain water Harvesting, and Electrical Meter Room, Sub-Station, Receiving Station as available, while recording 0% progress. The schedule does not specify water source, storage or treatment capacity; sewerage-system type or capacity; or electrical supply and backup arrangements. RERA amenities
The building approval requires a rainwater-harvesting structure (percolation pit), space for a transformer and a garbage house within the premises. It also requires a completion notice and occupancy certificate before occupation. These are approval requirements; the supplied material does not verify installation or completion.
The RERA schedule also lists storm-water drains, sewage and sullage treatment/disposal, solid-waste management, energy management and fire protection/fire-safety requirements, with 0% progress recorded. No detailed design, capacities, fire-system specifications, lift information, accessibility arrangements or independent compliance verification is supplied. RERA amenities
8. Location, access & connectivity
The project’s RERA-filed location is Rampur, Karimnagar District, Telangana, PIN 505001; the land record identifies the locality as Rampur and the title documents refer to Indraprastha Colony, Rampur locality of Karimnagar town. The mandal is not disclosed. RERA record Land records
A supplied connectivity record lists Financial District (Nanakramguda) — 1.2 km. The underlying record describes the location coordinate as a cadastral parcel centroid; no route, travel time or measurement method for the listed distance is provided. No project approach-road or public-transport details are supplied beyond the two boundary references to 9M roads. Location record RERA filing
9. Developer & development status
The registered promoter is BUILD URBAN CONSTRUCTIONS, recorded as a partnership. Its supplied corporate identifier is GSTIN 36AAWFB5362L1ZS. The RERA-filed promoter address is 1-5-346, Raghavendra Nagar, Indraprasthacolony, Rampur, Karimnagar, 505001. No official contact details are supplied. Corporate record Parties record
The RERA record names SUSHANTH REDDY MADDULA as authorized signatory and KRUPAKAR REDDY MADDULA and SUNANDA MADDULA as partners. Landowner records name SRIRANGAM RADHAKRISHNA and SREEDASYAM SUREKHA under area-share arrangements. Parties record Land records
The promoter’s Form B affidavit declares a completion date transcribed as “?6.0,4-2026” and states that 70% of amounts realised from allottees will be placed in a separate scheduled-bank account. The RERA header separately lists a proposed completion date of 30/11/2026. No construction-progress percentage or occupancy certificate is established by the supplied evidence. RERA record Document index
10. Approvals, official records & documents
| Record | What the supplied document establishes |
|---|---|
| TG-RERA registration certificate — P02700006331 | Form C certificate for BUILD URBAN AAVAAS; records registration from 07/07/2023 to 26/04/2026. |
| Building construction approval — 0009/BP/3011/2023 | Karimnagar Municipal Corporation approval dated 26 April 2023, for a residential apartment building on Survey No. 820, with 1 stilt + 5 upper floors. File number: 001069/BP/DTCP/3011/0007/2023. |
| RERA-filed title report | Advocate’s title opinion dated 08-05-2023 covering an 800 Sq.yds plot in Sy.No.820/Part and describing the landowners’ title, development rights and municipal mortgage. |
| Development Agreement-cum-GPA | RERA-filed agreement dated 25 November 2022 for development of 800.00 square yards; the supplied extraction describes a 40% landowner / 60% developer constructed-area allocation. |
| Encumbrance statement | RERA-filed statement L224609L7 lists three returned transactions and says 3 out of 5 are included in the statement. |
| Form B declaration | Promoter declaration filed in 2023, including its statements on title basis, encumbrances, completion and project accounts. |
| Occupancy / completion certificate | Not included in the supplied project documents. Document index |
The building approval’s conditions include requirements concerning the sanctioned plan, commencement and completion notices, occupancy before occupation, rainwater harvesting, transformer space and stilt parking. This overview records the approval evidence supplied; it does not establish that those works or requirements have been completed.
1. Project at a glance
Project identity
Registered project name: BUILD URBAN AAVAAS
Project type / phase: Residential apartment project; phase or separately identified registered portion: not disclosed.
TG-RERA registration: P02700006331; registered from 07/07/2023 to 26/04/2026. The record says registration was not extended; registration validity is distinct from the stated project completion date.
Registered promoter: BUILD URBAN CONSTRUCTIONS.
RERA-record status: The project is registered. The registration certificate records validity through 26/04/2026; the evidence supplied does not establish a current post-expiry registration status.
Land and geographic identity
Locality: Rampur / Indraprastha Colony, Karimnagar town locality, as stated across the RERA-filed land and approval records.
Revenue village: RERA identity: Rampur. The building approval extraction identifies the village as KARIMNAGAR; the supplied records do not resolve this naming difference.
Mandal: Not disclosed.
District / PIN: Karimnagar / 505001.
Survey number(s) and subdivisions: Survey No. 820; title records also describe Sy.No.820/Part and one development-agreement record transcribes it as Sy.No.B20/Part.
Registered plot references: Plots 14, 17 and 19.
Site extent: 668.87 sq.m. in the RERA land record and approval extraction. Approval extraction separately states Net Area 666.94 sq.m.
Boundaries: East: PLOT NO S 18 16 AND 15; west: 9M ROAD; north: PLOT NO 13; south: 9M ROAD.
Development identity
Sanctioning authority: Karimnagar Municipal Corporation.
Principal building approval: 0009/BP/3011/2023, approved 26 April 2023; file number 001069/BP/DTCP/3011/0007/2023.
Approved built-up area: 1,609.25 sq.m. recorded as residential upper-floor area; the approval also lists 322.27 sq.m. for the stilt. These are the areas as labelled in the approval extraction, not saleable or carpet areas.
Building count and floors: One residential apartment building, 1 stilt + 5 upper floors; sanctioned height 14.99 m.
Parking levels: Stilt is approved for parking; no parking-space count is supplied.
Approved versus RERA-filed units: Approval conditions say sanctioned unit numbers must not be increased without prior approval, but the supplied approval extraction does not give the sanctioned unit count. The RERA filing lists 15 2BHK units.
Offering and status
RERA-filed configuration: 2BHK, 15 units; saleable area 70.55 sq.m. per unit as recorded.
Booked / available: 0 booked / 15 available, as last read from the TG-RERA portal; the record gives no as-of date, so these counts are indicative.
Construction stage: No project construction-progress figure or independently verified site progress is supplied.
Completion date: Promoter’s Form B declaration records a completion date transcribed as “?6.0,4-2026”; a clear original/revised completion date is not established by that extraction. The RERA header lists proposed completion 30/11/2026.
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents. The building approval requires a completion notice and occupancy certificate before occupation.
2. The project story
BUILD URBAN AAVAAS is a RERA-registered residential apartment project on the recorded site at Rampur, Karimnagar, associated in the land and approval documents with Survey No. 820 and plots 14, 17 and 19. The RERA filing describes a single building and offers 15 two-bedroom apartments; the municipal building approval describes one residential building with a stilt and five upper floors.
The project’s registration certificate and building-construction approval are on file. The supplied evidence does not establish how much construction has been completed, whether the building is occupied, or whether an occupancy certificate has been issued. The approval’s conditions require an occupancy certificate before occupation.
3. Master plan, architecture & building design
The municipal approval describes a single residential building with 1 stilt + 5 upper floors, a sanctioned height of 14.99 m, residential upper-floor area of 1,609.25 sq.m., and stilt area of 322.27 sq.m. The approval extraction gives a site area of 668.87 sq.m. and net area of 666.94 sq.m.
The approval records a rainwater-harvesting structure, space for a transformer and a garbage house within the premises. It also states that the sanctioned plan must be followed, that construction modifications require prior approval, and that the sanctioned plan is to be displayed at the site.
No detailed floor-by-floor arrangement, building footprint, flats per floor, lift or stair specifications, internal circulation drawing, landscaping plan, or residential/common-area schedule is available in the supplied material. See Homes, configurations & floor plans above for the RERA-filed unit inventory.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 15 | 0 | 15 | 70.55 sq.m. | Not supplied for this configuration | Not supplied |
The configuration, count, booking status and saleable area are RERA-filed figures; the booking snapshot has no stated as-of date. The supplied drawing-measurement record relates to a 1BHK plan, which is not listed in the RERA filing’s 2BHK inventory. Its software-measured carpet area is 51.0 sq.m. (549 sq.ft.), based on two measured flat designs; it is a drawing-derived measurement, not a RERA disclosure, and is not presented as a measurement of the filed 2BHK units.
Carpet area and saleable area are different measures: the supplied measurement note says saleable area includes the home’s share of common areas, while the drawing-based carpet measurement is software-derived and needs review. No RERA-filed carpet area, balcony/utility area, or loading figure for the 2BHK units is supplied.
5. Parking & vehicle circulation
The building approval identifies the stilt as a parking level and states that approved stilt parking is to be used exclusively for vehicles, without partition walls or rolling shutters. No sanctioned parking-space count, visitor or accessible-space provision, parking allocation by unit, or parking circulation plan is supplied. A parking level in the approval does not establish an exclusive parking allocation to an apartment.
6. Amenities, recreation & open spaces
The amenity schedule contains 14 listed infrastructure or amenity categories. The RERA record shows 0% progress for each listed category where a percentage is stated. This is a filed progress status, not independent confirmation of site conditions.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green strip / tot lot / park | Size not supplied; building approval lists tot-lot area as NA. | RERA schedule: 0%; no independent completion verification. | |
| Aggregate recreational open space | Area not supplied. | RERA schedule: 0%; no independent completion verification. | |
| Community buildings | No description or size supplied. | RERA schedule: 0%; no independent completion verification. | |
| Internal roads and footpaths | No dimensions supplied. | RERA schedule: 0%; no independent completion verification. | |
| Street lighting | No further details supplied. | RERA schedule: 0%; no independent completion verification. |
No clubhouse, indoor recreation or sports facility is specified in the supplied project evidence.
7. Utilities, building services & safety
The RERA amenity schedule marks Water Supply, Sewerage (Chamber, Lines, Septic Tank, STP), Water Conservation, Rain water Harvesting, and Electrical Meter Room, Sub-Station, Receiving Station as available, while recording 0% progress. The schedule does not specify water source, storage or treatment capacity; sewerage-system type or capacity; or electrical supply and backup arrangements.
The building approval requires a rainwater-harvesting structure (percolation pit), space for a transformer and a garbage house within the premises. It also requires a completion notice and occupancy certificate before occupation. These are approval requirements; the supplied material does not verify installation or completion.
The RERA schedule also lists storm-water drains, sewage and sullage treatment/disposal, solid-waste management, energy management and fire protection/fire-safety requirements, with 0% progress recorded. No detailed design, capacities, fire-system specifications, lift information, accessibility arrangements or independent compliance verification is supplied.
8. Location, access & connectivity
The project’s RERA-filed location is Rampur, Karimnagar District, Telangana, PIN 505001; the land record identifies the locality as Rampur and the title documents refer to Indraprastha Colony, Rampur locality of Karimnagar town. The mandal is not disclosed.
A supplied connectivity record lists Financial District (Nanakramguda) — 1.2 km. The underlying record describes the location coordinate as a cadastral parcel centroid; no route, travel time or measurement method for the listed distance is provided. No project approach-road or public-transport details are supplied beyond the two boundary references to 9M roads.
9. Developer & development status
The registered promoter is BUILD URBAN CONSTRUCTIONS, recorded as a partnership. Its supplied corporate identifier is GSTIN 36AAWFB5362L1ZS. The RERA-filed promoter address is 1-5-346, Raghavendra Nagar, Indraprasthacolony, Rampur, Karimnagar, 505001. No official contact details are supplied.
The RERA record names SUSHANTH REDDY MADDULA as authorized signatory and KRUPAKAR REDDY MADDULA and SUNANDA MADDULA as partners. Landowner records name SRIRANGAM RADHAKRISHNA and SREEDASYAM SUREKHA under area-share arrangements.
The promoter’s Form B affidavit declares a completion date transcribed as “?6.0,4-2026” and states that 70% of amounts realised from allottees will be placed in a separate scheduled-bank account. The RERA header separately lists a proposed completion date of 30/11/2026. No construction-progress percentage or occupancy certificate is established by the supplied evidence.
10. Approvals, official records & documents
TG-RERA registration certificate — P02700006331: Form C certificate for BUILD URBAN AAVAAS; records registration from 07/07/2023 to 26/04/2026.
Building construction approval — 0009/BP/3011/2023: Karimnagar Municipal Corporation approval dated 26 April 2023, for a residential apartment building on Survey No. 820, with 1 stilt + 5 upper floors. File number: 001069/BP/DTCP/3011/0007/2023.
RERA-filed title report: Advocate’s title opinion dated 08-05-2023 covering an 800 Sq.yds plot in Sy.No.820/Part and describing the landowners’ title, development rights and municipal mortgage.
Development Agreement-cum-GPA: RERA-filed agreement dated 25 November 2022 for development of 800.00 square yards; the supplied extraction describes a 40% landowner / 60% developer constructed-area allocation.
Encumbrance statement: RERA-filed statement L224609L7 lists three returned transactions and says 3 out of 5 are included in the statement.
Form B declaration: Promoter declaration filed in 2023, including its statements on title basis, encumbrances, completion and project accounts.
Occupancy / completion certificate: Not included in the supplied project documents.
The building approval’s conditions include requirements concerning the sanctioned plan, commencement and completion notices, occupancy before occupation, rainwater harvesting, transformer space and stilt parking. This overview records the approval evidence supplied; it does not establish that those works or requirements have been completed.
Frequently asked questions
Is BUILD URBAN AAVAAS registered with Telangana RERA?
Yes. BUILD URBAN AAVAAS is registered with the Telangana Real Estate Regulatory Authority as P02700006331; the registration status is New Project.
Who is the developer of BUILD URBAN AAVAAS?
The promoter named in the RERA registration is BUILD URBAN CONSTRUCTIONS.
Where is BUILD URBAN AAVAAS located?
BUILD URBAN AAVAAS is in RAMPUR, Karimnagar, Telangana (505001).
When will BUILD URBAN AAVAAS be completed?
The promoter's proposed date of completion filed with RERA is 30/11/2026. This is the promoter's declaration, not a guarantee.
More projects in Karimnagar