Sri Gayathri Residency
MANYAM CONSTRUCTIONS · Hyderabad · RERA P02500006430
SRI GAYATHRI RESIDENCY is a residential apartment project in Gagan Mahal, Himayathnagar Mandal, Hyderabad. The registered promoter is Manyam Constructions. The project occupies a total plot area of 710.88 sq. m and comprises 1 residential building, Block A, with 1 Stilt + 5 upper floors and 10 homes, configured as 3BHK with 187.15 sq. m saleable area per unit. Its TG-RERA registration is P02500006430, and the proposed completion date is 02/02/2026.
More from Manyam Constructions · 4 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
11 items to check before you pay, 4 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Field | Record |
|---|---|
| Registered project name | SRI GAYATHRI RESIDENCY RERA record |
| Project type | Residential apartment project RERA record RERA filing |
| Phase / registered portion | Phase not identified in the supplied TG-RERA record; registration is for the named project. |
| TG-RERA registration | P02500006430; registered from 07/07/2023 to 02/02/2026; the certificate says “2 years.” No extension is recorded in the supplied certificate. RERA record |
| Registered promoter | Manyam Constructions (also recorded as MANYAM CONSTRUCTIONS); entity type: Partnership. Parties record Corporate record RERA filing |
| RERA status | The registration certificate records registration under section 5. Its stated validity ended on 02/02/2026; current extension or registration status is not established by the supplied evidence. |
Land and geographic identity
| Field | Record |
|---|---|
| Locality / address | Gagan Mahal, also described in project documents as Ashok Nagar, Gaganmahal; plot identifiers recorded as 1-10-5, 5/1, 5/2, 5/B, 5/C, 5/A, 5/A/1, 5/A/2 AND 5/A/3. RERA record |
| Revenue village | Gagan Mahal in the GHMC building-permit record; the HMDA certificate uses Gaganmahal. |
| Mandal / district / PIN | Himayathnagar Mandal (HMDA record: Himayathnagar); Hyderabad; 500020. |
| Survey number / subdivision | Not disclosed in the supplied project identity record. The plot identifiers above are reproduced as recorded and are not survey numbers. Land records |
| Registered / sanctioned land area | Total plot area 710.88 sq. m; road-affected area 82.37 sq. m; net plot area 628.51 sq. m. RERA filing |
| Boundaries (RERA filing) | East: 40 ROAD FEET; West: NEIGHBOURS LAND; North: PLOT NO 4; South: PLOTS NO 6 7. RERA filing |
Development identity
| Field | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC). |
| Principal building approval | Building Permit Order 5312/GHMC/SEC/2023-BP, approved 02 February, 2023; file no. 009038/GHMC/4459/SEC1/2022-BP. Approvals record |
| Other principal land-use record | HMDA Land Use Certificate 056028/LU/P5/HMDA/29072022, dated 23 August, 2022; it records a residential use zone and a 60 feet wide road on the east side. Approvals record |
| Approved area figures | Building-permit record: residential upper-floor area 1,576.65 Sq.Mt., stilt area 300.31 Sq.Mt., total parking area 312.4, and height 14.99. The plan record also lists NET BUA RESIDENTIAL NET BUA 1576.65, BUILT UP AREA 1602.30, and 1914.70; the last figure’s label is not clear in the supplied extraction. |
| Buildings and floors | 1 residential building, Block A; sanctioned configuration 1 Stilt + 5 upper floors (six floors as the permit record counts them); building height 14.99. |
| Parking | GHMC plan record lists 10 proposed parking spaces and 312.4 total parking area; plan conditions state that the cellar and stilt parking approved in the plan are for vehicle parking. No cellar level is identified in the extracted floor configuration. |
| Unit counts | 10 units in the TG-RERA filing; the building-plan extraction also records 10 proposed parking spaces, not a unit count. The approved unit count is not separately stated in the supplied permit extraction. RERA unit table |
Offering and status
| Field | Record |
|---|---|
| RERA-filed configuration and saleable area | 3BHK; 187.15 sq. m saleable area per unit, as filed. RERA unit table RERA unit table |
| Booked / available | 0 booked / 10 available in the portal data supplied; no as-of date is attached, so treat this as indicative rather than a current inventory confirmation. RERA unit table |
| Construction stage | TG-RERA progress fields supplied here do not establish a current construction stage. The separate RERA amenity record reports 10% for internal roads and footpaths, and 10% for sewerage; other listed progress entries are 0% or not stated. These are filed progress figures, not independent site verification. RERA amenities |
| Completion deadline | GHMC permit and promoter Form-B declaration state completion before / by 02 February, 2026. This is separate from the registration-validity period. |
| OC / completion certificate | No occupancy certificate or completion certificate is included in the supplied project documents. GHMC’s permit conditions require an occupancy certificate before occupation. Document index |
2. The project story
Sri Gayathri Residency is recorded with TG-RERA as a residential apartment project in Gagan Mahal, Hyderabad. The GHMC permit describes one residential apartment block, Block A, with one stilt floor and five upper floors. The project’s land record identifies plot numbers 1-10-5, 5/1, 5/2, 5/B, 5/C, 5/A, 5/A/1, 5/A/2 AND 5/A/3; survey numbers and subdivisions are not disclosed in the supplied record. RERA record Land records
The RERA filing lists ten 3BHK units, with none recorded as booked and all ten shown as available in the supplied portal data. The registration certificate and promoter’s Form-B declaration set 02/02/2026 as the completion date. The evidence supplied does not establish present construction progress or completion, and does not include an occupancy certificate; filed amenity progress figures should not be read as an independently inspected construction report. RERA unit table RERA amenities Document index
3. Master plan, architecture & building design
The GHMC-approved plan is for a single residential block, identified as Block A, with 1 Stilt + 5 upper floors and a recorded building height of 14.99. The plan extraction gives a plot area of 710.88 sq. m, road-affected area of 82.37 sq. m, and net plot area of 628.51 sq. m. It also lists a proposed coverage area of 315.44 (50.19%), vacant plot area of 313.07, residential net BUA of 1,576.65, built-up area of 1,602.30, and 1914.70; the label associated with the last figure is unclear in the supplied extraction, so it is not assigned a more specific area category here.
The permit records front and rear setbacks of 2.51 m and side setback I of 2.5 m. Its plan references a 9.00 MT WIDE EXISTING road, an 18.00 MT WIDE PROPOSED ROAD, and a 4.50M WIDE DRIVE WAY. The permit requires the 82.37 Sq. Mtrs road-widening area to be left to GHMC under Gift Deed 357/2023, dated 24-01-2023.
The supplied extraction does not provide a reliable description of flats per floor, internal circulation, lift or stair arrangements, detailed residential/common-area distribution, or a phase-wise plan. The approved plan lists a tot-lot and a periphery greenery requirement; the available material does not establish their completed condition.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 187.15 sq. m | Software-measured range: 113.0–138.9 sq. m; median 125.0 sq. m | 33% |
The RERA filing identifies the configuration as 3BHK and gives the unit count and saleable area. The carpet figures are software measurements from the approved floor-plan drawing geometry—not RERA-filed carpet-area disclosures—and the drawing-based measurement is flagged for review. Carpet area, saleable area and any common-area loading are different measures; the supplied record says the filed area may not be carpet area. RERA unit table RERA unit table Floor plans RERA unit details
The measured second-floor flat example includes a living/drawing room, dining area, kitchen, puja room, three bedrooms, three toilets, a balcony and a utility area. In that extracted example, the balcony is labelled 1.64 M. WIDE BALC; the utility is measured at 1.17 × 2.44 m. These are drawing-derived details for one example, not a statement that all units have identical dimensions or layouts. RERA unit details
5. Parking & vehicle circulation
The GHMC plan extraction records 10 proposed parking spaces and 312.4 as total parking area. The plan states that the cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not partitioned or converted to another use. The extracted building configuration specifies one stilt floor but does not establish a cellar level, parking-space type, visitor or accessible allocation, EV charging, ramp arrangement, or parking allotment for individual units. A drawn or sanctioned parking bay does not by itself establish exclusive ownership or a unit-specific allocation.
6. Amenities, recreation & open spaces
The GHMC plan lists a tot-lot, rainwater-harvesting provision, a distribution transformer space and a garbage house. The RERA amenity record gives progress percentages for listed project works; these are filed declarations, not independent verification of delivery. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green strip | Tot-lot identified in the GHMC plan; permit requires it to be fenced and maintained as greenery. No size supplied. | RERA amenities | RERA filing reports Green Strip/TOT LOT/Park at 0%; completion not independently verified. |
| Internal roads and footpaths | No dimensions beyond the plan’s road and driveway references in the preceding section. | RERA amenities | RERA filing: 10%. |
| Water supply | Listed as a project work; no source, storage or treatment details supplied here. | RERA amenities | RERA filing: 0%. |
| Sewerage | RERA category is “Sewerage (Chamber, Lines, Septic Tank, STP)”; the supplied record does not identify which system is provided. | RERA amenities | RERA filing: 10%. |
| Rainwater harvesting | GHMC plan lists RWH and a percolation pit; building-permit extraction records 9 No. of Rain Water Harvesting Pits. | RERA filing: 0% for water conservation/rainwater harvesting; completion not independently verified. | |
| Street lighting | Listed in the RERA amenity record; no specification supplied. | RERA amenities | 0%. |
| Community buildings | Listed in the RERA amenity record; no building or facility description supplied. | RERA amenities | 0%. |
| Sewage and sullage treatment/disposal | Listed as a separate RERA amenity item; no system or capacity supplied. | RERA amenities | 0%. |
| Solid-waste management and disposal | GHMC plan requires a garbage house within the premises; no size or capacity supplied. | RERA amenities | RERA filing: 0% for solid-waste management and disposal. |
| Electrical meter room / substation / receiving station | The RERA record lists this category; GHMC permit requires space for a transformer. | RERA amenities | RERA filing: 0%. |
| Recreational open space | Aggregate area is not supplied. | RERA amenities | RERA filing: 0%. |
7. Utilities, building services & safety
GHMC’s plan lists rainwater harvesting and a percolation pit, and its building-permit extraction records nine rainwater-harvesting pits. The plan also requires space for a transformer and a garbage house within the premises. The supplied material does not specify water source or storage capacity, wastewater-treatment plant capacity, storm-water design, electrical backup, lifts, lift capacity, CCTV, access control, or accessibility arrangements.
The permit requires sanitation, plumbing, fire-safety requirements, lifts and electrical installations to be executed under qualified technical supervision. It also requires structural-safety and means-of-escape safety measures and an occupancy Fire NOC before issue of the occupancy certificate. These are approval conditions; the supplied record does not establish that the works or clearances have been completed.
8. Location, access & connectivity
The registered project location is Gagan Mahal, in Hyderabad district, PIN 500020; project documents also describe the site as Ashok Nagar, Gaganmahal. The GHMC building-permit record identifies Himayathnagar Mandal. RERA record
The permit refers to an existing 9.00 MT road, a proposed 18.00 MT road and a 4.50M driveway. HMDA’s land-use certificate records a 60 feet wide road on the east side under the Master Plan. The supplied location data identifies Financial District (Nanakramguda), 1.2 km from the cadastral parcel centroid; it does not provide a measured route distance or travel time. Location record
9. Developer & development status
The registered promoter is MANYAM CONSTRUCTIONS, recorded as a partnership, with GSTIN 36AAGFM5946H1Z0. The supplied promoter address is B, MOTHI NAGAR, THE AP GOVT EMPLOYEES CO OP HOUSE BUILDING SOCIETY LIMITED, ASHOK NAGAR, GAGAN MAHAL, Hyderabad, 500020. A registered office address and official project contact details are not established in the supplied records; the registration certificate’s promoter-office field states Village: Mandal: District: Hyderabad, Pin: 500018. Parties record Corporate record RERA filing
The GHMC permit identifies Manyam Constructions as developer/builder, represented by V. Timber and D. Ananta Raya Sarma. The project filing identifies Timber Vedaraju as authorized signatory and Subba Laxmi Vedaraju as a partner. The promoter’s Form-B declaration states a completion date of 02/02/2026 and declares that 70% of amounts realized from allottees will be deposited in a separate scheduled-bank account for land and construction costs. These are promoter declarations; the supplied evidence does not establish current construction progress or completion. Parties record
10. Approvals, official records & documents
| Reference / date | P02500006430; issued 07/07/2023; stated validity to 02/02/2026 |
|---|---|
| What the supplied record establishes | Registration of SRI GAYATHRI RESIDENCY under section 5; the certificate includes conditions concerning agreement for sale, conveyance and the separate account. |
| Reference / date | 5312/GHMC/SEC/2023-BP; approved 02 February, 2023; file no. 009038/GHMC/4459/SEC1/2022-BP |
|---|---|
| What the supplied record establishes | Conditional building permission for one residential block, 1 Stilt + 5 upper floors. The permit records the road-affected-area surrender and requires an occupancy certificate before occupation. |
| Reference / date | Approval/application reference TS/052721/2022 |
|---|---|
| What the supplied record establishes | Plan for a single residential apartment block on Plot No. 5, Ashoka Nagar, Gaganmahal; includes building, parking and site-condition information. |
| Reference / date | 056028/LU/P5/HMDA/29072022; dated 23 August, 2022 |
|---|---|
| What the supplied record establishes | Records residential use zoning and an east-side 60 feet road under the Master Plan; the certificate states it is not proof of title. |
| Reference / date | 357/2023, dated 24-01-2023 |
|---|---|
| What the supplied record establishes | GHMC permit records a gift deed for the 82.37 Sq. Mtrs road-widening area in favour of GHMC. |
| Reference / date | Dated 10th day of May 2023 |
|---|---|
| What the supplied record establishes | Promoter’s filed declarations include the project completion undertaking and separate-account commitments. |
| Reference / date | Not present in supplied documents |
|---|---|
| What the supplied record establishes | No OC or completion certificate is established by the materials reviewed here. Document index |
1. Project at a glance
Project identity
Registered project name: SRI GAYATHRI RESIDENCY
Project type: Residential apartment project
Phase / registered portion: Phase not identified in the supplied TG-RERA record; registration is for the named project.
TG-RERA registration: P02500006430; registered from 07/07/2023 to 02/02/2026; the certificate says “2 years.” No extension is recorded in the supplied certificate.
Registered promoter: Manyam Constructions (also recorded as MANYAM CONSTRUCTIONS); entity type: Partnership.
RERA status: The registration certificate records registration under section 5. Its stated validity ended on 02/02/2026; current extension or registration status is not established by the supplied evidence.
Land and geographic identity
Locality / address: Gagan Mahal, also described in project documents as Ashok Nagar, Gaganmahal; plot identifiers recorded as 1-10-5, 5/1, 5/2, 5/B, 5/C, 5/A, 5/A/1, 5/A/2 AND 5/A/3.
Revenue village: Gagan Mahal in the GHMC building-permit record; the HMDA certificate uses Gaganmahal.
Mandal / district / PIN: Himayathnagar Mandal (HMDA record: Himayathnagar); Hyderabad; 500020.
Survey number / subdivision: Not disclosed in the supplied project identity record. The plot identifiers above are reproduced as recorded and are not survey numbers.
Registered / sanctioned land area: Total plot area 710.88 sq. m; road-affected area 82.37 sq. m; net plot area 628.51 sq. m.
Boundaries (RERA filing): East: 40 ROAD FEET; West: NEIGHBOURS LAND; North: PLOT NO 4; South: PLOTS NO 6 7.
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC).
Principal building approval: Building Permit Order 5312/GHMC/SEC/2023-BP, approved 02 February, 2023; file no. 009038/GHMC/4459/SEC1/2022-BP.
Other principal land-use record: HMDA Land Use Certificate 056028/LU/P5/HMDA/29072022, dated 23 August, 2022; it records a residential use zone and a 60 feet wide road on the east side.
Approved area figures: Building-permit record: residential upper-floor area 1,576.65 Sq.Mt., stilt area 300.31 Sq.Mt., total parking area 312.4, and height 14.99. The plan record also lists NET BUA RESIDENTIAL NET BUA 1576.65, BUILT UP AREA 1602.30, and 1914.70; the last figure’s label is not clear in the supplied extraction.
Buildings and floors: 1 residential building, Block A; sanctioned configuration 1 Stilt + 5 upper floors (six floors as the permit record counts them); building height 14.99.
Parking: GHMC plan record lists 10 proposed parking spaces and 312.4 total parking area; plan conditions state that the cellar and stilt parking approved in the plan are for vehicle parking. No cellar level is identified in the extracted floor configuration.
Unit counts: 10 units in the TG-RERA filing; the building-plan extraction also records 10 proposed parking spaces, not a unit count. The approved unit count is not separately stated in the supplied permit extraction.
Offering and status
RERA-filed configuration and saleable area: 3BHK; 187.15 sq. m saleable area per unit, as filed.
Booked / available: 0 booked / 10 available in the portal data supplied; no as-of date is attached, so treat this as indicative rather than a current inventory confirmation.
Construction stage: TG-RERA progress fields supplied here do not establish a current construction stage. The separate RERA amenity record reports 10% for internal roads and footpaths, and 10% for sewerage; other listed progress entries are 0% or not stated. These are filed progress figures, not independent site verification.
Completion deadline: GHMC permit and promoter Form-B declaration state completion before / by 02 February, 2026. This is separate from the registration-validity period.
OC / completion certificate: No occupancy certificate or completion certificate is included in the supplied project documents. GHMC’s permit conditions require an occupancy certificate before occupation.
2. The project story
Sri Gayathri Residency is recorded with TG-RERA as a residential apartment project in Gagan Mahal, Hyderabad. The GHMC permit describes one residential apartment block, Block A, with one stilt floor and five upper floors. The project’s land record identifies plot numbers 1-10-5, 5/1, 5/2, 5/B, 5/C, 5/A, 5/A/1, 5/A/2 AND 5/A/3; survey numbers and subdivisions are not disclosed in the supplied record.
The RERA filing lists ten 3BHK units, with none recorded as booked and all ten shown as available in the supplied portal data. The registration certificate and promoter’s Form-B declaration set 02/02/2026 as the completion date. The evidence supplied does not establish present construction progress or completion, and does not include an occupancy certificate; filed amenity progress figures should not be read as an independently inspected construction report.
3. Master plan, architecture & building design
The GHMC-approved plan is for a single residential block, identified as Block A, with 1 Stilt + 5 upper floors and a recorded building height of 14.99. The plan extraction gives a plot area of 710.88 sq. m, road-affected area of 82.37 sq. m, and net plot area of 628.51 sq. m. It also lists a proposed coverage area of 315.44 (50.19%), vacant plot area of 313.07, residential net BUA of 1,576.65, built-up area of 1,602.30, and 1914.70; the label associated with the last figure is unclear in the supplied extraction, so it is not assigned a more specific area category here.
The permit records front and rear setbacks of 2.51 m and side setback I of 2.5 m. Its plan references a 9.00 MT WIDE EXISTING road, an 18.00 MT WIDE PROPOSED ROAD, and a 4.50M WIDE DRIVE WAY. The permit requires the 82.37 Sq. Mtrs road-widening area to be left to GHMC under Gift Deed 357/2023, dated 24-01-2023.
The supplied extraction does not provide a reliable description of flats per floor, internal circulation, lift or stair arrangements, detailed residential/common-area distribution, or a phase-wise plan. The approved plan lists a tot-lot and a periphery greenery requirement; the available material does not establish their completed condition.
4. Homes, configurations & floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 187.15 sq. m | Software-measured range: 113.0–138.9 sq. m; median 125.0 sq. m | 33% |
The RERA filing identifies the configuration as 3BHK and gives the unit count and saleable area. The carpet figures are software measurements from the approved floor-plan drawing geometry—not RERA-filed carpet-area disclosures—and the drawing-based measurement is flagged for review. Carpet area, saleable area and any common-area loading are different measures; the supplied record says the filed area may not be carpet area.
The measured second-floor flat example includes a living/drawing room, dining area, kitchen, puja room, three bedrooms, three toilets, a balcony and a utility area. In that extracted example, the balcony is labelled 1.64 M. WIDE BALC; the utility is measured at 1.17 × 2.44 m. These are drawing-derived details for one example, not a statement that all units have identical dimensions or layouts.
5. Parking & vehicle circulation
The GHMC plan extraction records 10 proposed parking spaces and 312.4 as total parking area. The plan states that the cellar and stilt areas approved for parking must be used exclusively for vehicle parking and not partitioned or converted to another use. The extracted building configuration specifies one stilt floor but does not establish a cellar level, parking-space type, visitor or accessible allocation, EV charging, ramp arrangement, or parking allotment for individual units. A drawn or sanctioned parking bay does not by itself establish exclusive ownership or a unit-specific allocation.
6. Amenities, recreation & open spaces
The GHMC plan lists a tot-lot, rainwater-harvesting provision, a distribution transformer space and a garbage house. The RERA amenity record gives progress percentages for listed project works; these are filed declarations, not independent verification of delivery.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green strip | Tot-lot identified in the GHMC plan; permit requires it to be fenced and maintained as greenery. No size supplied. | RERA filing reports Green Strip/TOT LOT/Park at 0%; completion not independently verified. | |
| Internal roads and footpaths | No dimensions beyond the plan’s road and driveway references in the preceding section. | RERA filing: 10%. | |
| Water supply | Listed as a project work; no source, storage or treatment details supplied here. | RERA filing: 0%. | |
| Sewerage | RERA category is “Sewerage (Chamber, Lines, Septic Tank, STP)”; the supplied record does not identify which system is provided. | RERA filing: 10%. | |
| Rainwater harvesting | GHMC plan lists RWH and a percolation pit; building-permit extraction records 9 No. of Rain Water Harvesting Pits. | RERA filing: 0% for water conservation/rainwater harvesting; completion not independently verified. | |
| Street lighting | Listed in the RERA amenity record; no specification supplied. | 0%. | |
| Community buildings | Listed in the RERA amenity record; no building or facility description supplied. | 0%. | |
| Sewage and sullage treatment/disposal | Listed as a separate RERA amenity item; no system or capacity supplied. | 0%. | |
| Solid-waste management and disposal | GHMC plan requires a garbage house within the premises; no size or capacity supplied. | RERA filing: 0% for solid-waste management and disposal. | |
| Electrical meter room / substation / receiving station | The RERA record lists this category; GHMC permit requires space for a transformer. | RERA filing: 0%. | |
| Recreational open space | Aggregate area is not supplied. | RERA filing: 0%. |
7. Utilities, building services & safety
GHMC’s plan lists rainwater harvesting and a percolation pit, and its building-permit extraction records nine rainwater-harvesting pits. The plan also requires space for a transformer and a garbage house within the premises. The supplied material does not specify water source or storage capacity, wastewater-treatment plant capacity, storm-water design, electrical backup, lifts, lift capacity, CCTV, access control, or accessibility arrangements.
The permit requires sanitation, plumbing, fire-safety requirements, lifts and electrical installations to be executed under qualified technical supervision. It also requires structural-safety and means-of-escape safety measures and an occupancy Fire NOC before issue of the occupancy certificate. These are approval conditions; the supplied record does not establish that the works or clearances have been completed.
8. Location, access & connectivity
The registered project location is Gagan Mahal, in Hyderabad district, PIN 500020; project documents also describe the site as Ashok Nagar, Gaganmahal. The GHMC building-permit record identifies Himayathnagar Mandal.
The permit refers to an existing 9.00 MT road, a proposed 18.00 MT road and a 4.50M driveway. HMDA’s land-use certificate records a 60 feet wide road on the east side under the Master Plan. The supplied location data identifies Financial District (Nanakramguda), 1.2 km from the cadastral parcel centroid; it does not provide a measured route distance or travel time.
9. Developer & development status
The registered promoter is MANYAM CONSTRUCTIONS, recorded as a partnership, with GSTIN 36AAGFM5946H1Z0. The supplied promoter address is B, MOTHI NAGAR, THE AP GOVT EMPLOYEES CO OP HOUSE BUILDING SOCIETY LIMITED, ASHOK NAGAR, GAGAN MAHAL, Hyderabad, 500020. A registered office address and official project contact details are not established in the supplied records; the registration certificate’s promoter-office field states Village: Mandal: District: Hyderabad, Pin: 500018.
The GHMC permit identifies Manyam Constructions as developer/builder, represented by V. Timber and D. Ananta Raya Sarma. The project filing identifies Timber Vedaraju as authorized signatory and Subba Laxmi Vedaraju as a partner. The promoter’s Form-B declaration states a completion date of 02/02/2026 and declares that 70% of amounts realized from allottees will be deposited in a separate scheduled-bank account for land and construction costs. These are promoter declarations; the supplied evidence does not establish current construction progress or completion.
10. Approvals, official records & documents
| Reference / date | P02500006430; issued 07/07/2023; stated validity to 02/02/2026 |
|---|---|
| What the supplied record establishes | Registration of SRI GAYATHRI RESIDENCY under section 5; the certificate includes conditions concerning agreement for sale, conveyance and the separate account. |
| Reference / date | 5312/GHMC/SEC/2023-BP; approved 02 February, 2023; file no. 009038/GHMC/4459/SEC1/2022-BP |
|---|---|
| What the supplied record establishes | Conditional building permission for one residential block, 1 Stilt + 5 upper floors. The permit records the road-affected-area surrender and requires an occupancy certificate before occupation. |
| Reference / date | Approval/application reference TS/052721/2022 |
|---|---|
| What the supplied record establishes | Plan for a single residential apartment block on Plot No. 5, Ashoka Nagar, Gaganmahal; includes building, parking and site-condition information. |
| Reference / date | 056028/LU/P5/HMDA/29072022; dated 23 August, 2022 |
|---|---|
| What the supplied record establishes | Records residential use zoning and an east-side 60 feet road under the Master Plan; the certificate states it is not proof of title. |
| Reference / date | 357/2023, dated 24-01-2023 |
|---|---|
| What the supplied record establishes | GHMC permit records a gift deed for the 82.37 Sq. Mtrs road-widening area in favour of GHMC. |
| Reference / date | Dated 10th day of May 2023 |
|---|---|
| What the supplied record establishes | Promoter’s filed declarations include the project completion undertaking and separate-account commitments. |
| Reference / date | Not present in supplied documents |
|---|---|
| What the supplied record establishes | No OC or completion certificate is established by the materials reviewed here. |
Frequently asked questions
Is SRI GAYATHRI RESIDENCY registered with Telangana RERA?
Yes. SRI GAYATHRI RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02500006430; the registration status is New Project.
Who is the developer of SRI GAYATHRI RESIDENCY?
The promoter named in the RERA registration is MANYAM CONSTRUCTIONS.
Where is SRI GAYATHRI RESIDENCY located?
SRI GAYATHRI RESIDENCY is in GAGAN MAHAL, Hyderabad, Telangana (500020).
When will SRI GAYATHRI RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 02/02/2026. This is the promoter's declaration, not a guarantee.
More projects in Hyderabad