VIGNESHWARA COLONY is a plotted development in Palkonda / Palakonda Thanda, Mahabubnagar Urban mandal, Mahabubnagar district. The registered promoter is KUMMARI RAMAKRISHNA AND SYED ABRAR MOHIUDDIN. The project covers 4350.37 sq. m and comprises 19 plots; no towers, blocks, floors or home configurations are stated. It is registered with TG-RERA as P01400006914, with a promoter-declared completion undertaking of 24 May, 2025.

01What we found

Period endedTG-RERA registration ran to 24 May 2025 - check its extension on TG-RERA
12documents on file - each fact links to its page
3court cases on this project's land (survey 324, Palakonda Thanda) or naming the project
8items to check - 2 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 2 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

Palakonda Thanda, Mahabubnagar Urban, Mahabubnagar · geocoded — approximate.

1. Project at a glance

Project identity

FieldRecord
Registered project nameVIGNESHWARA COLONY RERA record
Project typePlotted development / tentative layout RERA record
Phase / registered portionNo phase number is disclosed; registration covers the plotted project identified by survey numbers 30/P and 324/P.
TG-RERA registrationP01400006914
Registration validity08/09/2023 to 24/05/2025; the certificate records no extension. This is the registration period, not a statement that an occupancy or completion certificate was issued.
Registered promoterKUMMARI RAMAKRISHNA AND SYED ABRAR MOHIUDDIN RERA record
RERA statusNew Project in the supplied project record. The registration validity end date has passed; current registration status is not established by the supplied record. RERA record

Land and geographic identity

FieldRecord
LocalityPalkonda / Palakonda Thanda RERA record
Revenue villagePALKONDA Revenue Village, also rendered as Palakonda in the supplied record
MandalMahabubnagar Urban; the layout approval describes Mahaboobnagar Mandal RERA record
District / PINMahabubnagar / 509001 RERA record
Project survey numbers30/P and 324/P
Registered site extentRERA project record: 4350.37 sq. m. The approved layout document states 1 Acer 3 Gts 5203 Sq. Yds. RERA filing
Net / total land areaThe RERA land record states total area and net area as 4350.37 sq. m, with road-widening/FTL/nala-widening area recorded as 0 sq. m. RERA filing
BoundariesEast: PROPOSED 60 FEET ROAD; West: LAND IN SY NO 31; North: LAND IN SY NO 30; South: LAND IN SY NO 324. RERA filing

Development identity

FieldRecord
Sanctioning authorityMAHABOOBNAGAR Municipality/Municipal Corporation
Principal layout approvalTentative Layout Plan 0021/LO/3063/2023, dated 24 May, 2023; application number 003989/LO/DTCP/3063/0032/2023. Approvals record
Approved developmentLayout of 19 plots. The supplied evidence does not state an approved built-up area, building count or floor configuration.
Layout land-use areasPlotted Area: 0 Acer 24.16 Gts 2923 Sq. Yds (58.32%); Road Area: 0 Acer 11.89 Gts 1439 Sq. Yds (28.72%); Open space (Park): 0 Acer 3.77 Gts 456 Sq. Yds (9.1%); Social Infrastructure: 0 Acer 1.18 Gts 143 Sq. Yds (2.86%); Utilities: 0 Acer 0.42 Gts 50 Sq. Yds (1.01%).
Mortgage recorded in layout approvalPlots 11, 19 and 15, stated extent 0 Acer 4.22 Gts 510 Sq. Yds, in favour of the Municipality/Municipal Corporation.

Offering and status

FieldRecord
Unit typePlots; the approved layout records 19 plots.
Plot-size scheduleSoftware-read from the approved layout drawing: 19 plots, with sizes from 87.85 sq. m (105.1 sq. yd) to 166.68 sq. m (199.3 sq. yd); median 145.19 sq. m (173.6 sq. yd). The drawing-derived schedule should be checked against the drawing. Layout record
Booked / availableNot disclosed in the supplied evidence.
Construction / development stageNo independently verified site-progress report is supplied. The RERA record identifies the project as “New Project”; the layout approval requires the promoter to carry out the layout infrastructure works. RERA record
Completion datePromoter-declared completion undertaking: 24 May, 2025; the day is partially obscured in the filed Form B.
Occupancy / completion certificateNot supplied; the project is a plotted layout, and the available record does not establish issuance of a completion or occupancy certificate.

2. The project story

VIGNESHWARA COLONY is a plotted residential layout registered with TG-RERA as P01400006914, located at Palkonda/Palakonda Thanda in Mahabubnagar Urban mandal, Mahabubnagar district. The registered land is identified as survey numbers 30/P and 324/P.

The tentative layout approval describes 19 plots and reserves land for roads, a park/open space, social infrastructure and utilities. The approval assigns responsibility for layout development and infrastructure works to the applicant/promoter. It also requires designated areas to be handed over to the municipality by registered gift deed before release of the tentative layout.

The promoter’s Form B declares a completion undertaking for May 2025, but the supplied evidence does not establish actual construction or infrastructure progress, completion, or certificate issuance.

3. Master plan, architecture & building design

This is a plotted layout, not a multi-storey building project in the supplied record. The approved tentative layout is for 19 plots on survey numbers 30/P and 324/P. The drawing-derived land-use table records 58.32% as plotted area, 28.72% as roads, 9.1% as park/open space, 2.86% as social infrastructure and 1.01% as utilities.

The layout approval lists infrastructure and site works including internal roads, storm-water drains, underground drainage lines, internal water-supply pipelines, street lights and rainwater-harvesting pits. It also names a water reservoir, septic tank or sewerage treatment plant, electric transformer and solid-waste management. These are listed as required or proposed works; completion is not verified in the supplied evidence.

No building count, floor configuration, building footprint, approved built-up area or building-level plan is established by the supplied record. The available drawing files are layout sheets rather than measured home floor plans. Floor plans

4. Homes, configurations & floor plans

The offering is plots, not apartment configurations. The approved layout document records 19 plots. A software reading of the approved layout drawing gives the following plot-size range and distribution; these are drawing-derived measurements, not RERA-filed saleable-area disclosures. Layout record

Plot size bandPlot count
100–150 sq. yd (84–125 sq. m)7
150–200 sq. yd (125–167 sq. m)12

The drawing-derived smallest plot is 87.85 sq. m (105.1 sq. yd), the median is 145.19 sq. m (173.6 sq. yd), and the largest is 166.68 sq. m (199.3 sq. yd). Plot-specific availability, booking status, sale prices and contractual plot areas are not supplied. Layout record

5. Parking & vehicle circulation

No separate parking count, visitor or accessible parking provision, or plot-wise parking allocation is disclosed in the supplied evidence. The layout approval requires roads to be opened for accessibility to neighbouring sites and states that the layout owner/developer shall not construct a compound wall or fencing around the site.

6. Amenities, recreation & open spaces

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Park / open space0 Acer 3.77 Gts 456 Sq. Yds (9.1%)Approved tentative layoutReserved in the layout; completion or handover not verified.
Social infrastructure site0 Acer 1.18 Gts 143 Sq. Yds (2.86%)Approved tentative layoutReserved in the layout; facility type and completion not established.
Internal roadsLayout road area: 0 Acer 11.89 Gts 1439 Sq. Yds (28.72%)Approved tentative layoutRequired layout works; completion not verified.
Community buildingsListed in RERA amenity fields; no size or facility detail suppliedRERA amenity record RERA amenitiesDeclared/listed; progress shown as 0%.
Green strip / tot lot / parkListed in RERA amenity fieldsRERA amenity record RERA amenitiesDeclared/listed; progress shown as 0%.

The layout approval requires the open space to be handed over to the municipality by registered gift deed before release of the tentative layout. The supplied record does not confirm that handover.

7. Utilities, building services & safety

The approved layout document identifies utility land of 0 Acer 0.42 Gts 50 Sq. Yds (1.01%) and lists proposed or required works including water reservoir/overhead tank, internal water-supply pipelines, septic tank or sewerage treatment plant, underground drainage lines, storm-water drains, electric transformer, street lighting, solid-waste management and rainwater-harvesting pits.

These are layout-approval provisions, not evidence that the facilities have been installed or are operational. The supplied record does not give capacities, service connections, backup power, fire systems, security systems or accessibility details. RERA amenities

8. Location, access & connectivity

The registered location is Palkonda/Palakonda Thanda, Mahabubnagar Urban mandal, Mahabubnagar district, Telangana, 509001. The RERA land record identifies a proposed 60 FEET ROAD on the eastern boundary; the layout approval also requires roads to be opened for access to neighbouring sites. RERA record RERA filing

The supplied location record gives the nearest sampled Outer Ring Road interchange as approximately 69.4 km away. This is a location-data distance, not a stated travel time. Location record

9. Developer & development status

The registered promoter is KUMMARI RAMAKRISHNA AND SYED ABRAR MOHIUDDIN. The RERA record describes the organization type as “Others” and identifies the description as “Partnership”; a separate corporate registration identifier or verified entity number is not supplied. The registration certificate gives the promoter office as Village: Madina Masjid, Mandal: Mahabubnagar Urban, District: Mahabubnagar, PIN 509001. RERA record RERA filing

The promoter’s Form B, dated 20th June, 2023, declares that the project would be completed by May 2025; the day is partially obscured in the filed document. The supplied evidence does not establish the current development stage, plot sales, infrastructure completion or handover of reserved land.

10. Approvals, official records & documents

TG-RERA registration certificate, Form C
Identifier / dateP01400006914; issued 08/09/2023; valid through 24/05/2025
What it establishesRegistration of VIGNESHWARA COLONY and stated registration conditions. No extension is recorded in the supplied certificate.
Tentative layout approval
Identifier / date0021/LO/3063/2023, 24 May, 2023; application 003989/LO/DTCP/3063/0032/2023
What it establishesTentative layout approval for 19 plots on survey numbers 30/P and 324/P, with land-use areas and conditions.
Form B promoter declaration
Identifier / date20th June, 2023
What it establishesPromoter declarations concerning title basis, encumbrances, separate-account handling and completion undertaking.

No occupancy or completion certificate is included in the supplied documents. The tentative layout approval itself states that it is not proof of land title.

Frequently asked questions

Is VIGNESHWARA COLONY registered with Telangana RERA?

Yes. VIGNESHWARA COLONY is registered with the Telangana Real Estate Regulatory Authority as P01400006914; the registration status is New Project.

Who is the developer of VIGNESHWARA COLONY?

The promoter named in the RERA registration is KUMMARI RAMAKRISHNA AND SYED ABRAR MOHIUDDIN.

Where is VIGNESHWARA COLONY located?

VIGNESHWARA COLONY is in Palkonda, Palakonda Thanda, Mahabubnagar Urban, Mahabubnagar, Telangana (509001).

When will VIGNESHWARA COLONY be completed?

The promoter's proposed date of completion filed with RERA is 24/05/2025. This is the promoter's declaration, not a guarantee.