Sri Kirshna Residency
VISHWAS CONSTRUCTIONS · Karimnagar · RERA P02700006102
SRI KIRSHNA RESIDENCY is a residential apartment project in Theegalaguttapally, Karimnagar -I mandal, Karimnagar district, developed by registered promoter VISHWAS CONSTRUCTIONS. The registered site extent is 698.63 sq.m.; the project has one residential building with one stilt plus five upper floors and 15 apartments: five 2BHK and ten 3BHK units. Its TG-RERA registration number is P02700006102, and the proposed completion date is 04 June 2025.
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
6 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | Project record |
|---|---|
| Registered name | SRI KIRSHNA RESIDENCY RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | No separate phase name is disclosed. The TG-RERA record identifies the project site as plots 10/A, 11/A and 12/A RERA filing |
| TG-RERA registration | P02700006102 RERA record |
| Registration validity | 19 April 2023 to 4 June 2025; the supplied certificate says “2 years” and no extension is recorded in the supplied registration data RERA record |
| Registered promoter | VISHWAS CONSTRUCTIONS; entity type recorded as Proprietorship Corporate record RERA filing |
| RERA status | The supplied registration record gives an expiry date of 4 June 2025; it does not establish a current extension or a current registration status RERA record |
Land and geographic identity
| Item | Project record |
|---|---|
| Locality | Theegalaguttapally RERA record |
| Revenue village | Arepalle; the building approval describes “Arepalli (Part)” RERA record |
| Mandal | Karimnagar -I RERA record |
| District / PIN | Karimnagar / 505001 RERA record |
| Project survey number and subdivision | 276/B RERA record |
| Registered site extent | 698.63 sq.m. RERA filing |
| Total / net area | Total area 698.63 sq.m.; net area 698.63 sq.m. RERA filing |
| Boundaries | East: Plot of K Ram Reddy and House of M Prabhakar Reddy; West: 30 Feet Wide Road; North: Plot No 9 by A; South: Plot No 13 by A RERA filing |
Development identity
| Item | Project record |
|---|---|
| Sanctioning authority | Karimnagar Municipal Corporation Approvals record |
| Principal building approval | 0015/BP/3011/2022, dated 04 June 2022; file no. 001645/BP/DTCP/3011/0016/2022 Approvals record |
| Approved built-up area | 1,695.40 sq.m. residential upper-floor area; the approval separately records 359.51 sq.m. stilt area |
| Building count and configuration | One residential building, identified in the approval as “Building - RAMESH (VINOD)”; one stilt plus five upper floors |
| Height / parking | Approval records a height of 15 m and states cellar and stilts approved for parking; no parking-space count is supplied |
| Unit count | The filed unit schedule lists 15 apartments. The approval document does not provide an approved unit-count figure in the supplied extraction RERA unit table |
Offering and status
| Item | Project record |
|---|---|
| RERA-filed configurations | 2BHK: 5 units; 3BHK: 10 units RERA unit table |
| RERA-filed saleable area | 2BHK: 120.77 sq.m.; 3BHK: 142.32 sq.m. RERA unit table |
| Booked / available | Portal-derived counts show 0 booked and 5 available 2BHKs; 0 booked and 10 available 3BHKs. The portal record has no as-of date, so these counts are indicative RERA unit table |
| Construction stage | The supplied record does not establish a current construction stage or independently verified site progress. The RERA-filed amenity/status data marks water supply at 30% and the other listed infrastructure items at 0% RERA amenities |
| Completion deadline | The Form-B declaration states a project-completion date of 04 June 2025; this is distinct from the registration-validity period |
| Occupancy / completion certificate | No occupancy or completion certificate is included in the supplied project documents. The building approval requires completion notice and an occupancy certificate before occupation |
2. The project story
SRI KIRSHNA RESIDENCY is a residential apartment project registered for plots 10/A, 11/A and 12/A in Theegalaguttapally, Arepalle (also described in the approval as Arepalli (Part)), Karimnagar district. Its RERA-identified land is survey 276/B, with a site extent of 698.63 sq.m. RERA record RERA filing
The building approval describes one residential building with one stilt and five upper floors. The RERA schedule lists 15 apartments: five 2BHK and ten 3BHK units. These are filed project and unit details; the supplied evidence does not establish that construction is complete, independently confirm the current site condition, or document an occupancy certificate RERA unit table RERA amenities.
3. Master plan, architecture & building design
The supplied building approval is for a residential building on the project plots and records a site area and net area of 698.63 sq.m. It identifies one building, “Building - RAMESH (VINOD),” configured as one stilt plus five upper floors, with a stated height of 15 m. Approved residential upper-floor area is recorded as 1,695.40 sq.m.; stilt area is separately recorded as 359.51 sq.m. These are approval figures, not carpet or saleable areas.
The approval also records a second-floor area of 220.19 sq.m. associated with a mortgage entry, and nine rainwater-harvesting structures. It lists no tot-lot area (“NA”) and no tree count (“NA”) in the supplied approval extraction. The site plan/layout-plan document filed with TG-RERA is not extracted into usable layout details here; internal building circulation, lifts, stairs, floor-by-floor apartment arrangement, building footprint, and detailed open-space design are therefore not established by the supplied material.
4. Homes, configurations & floor plans
The unit counts and saleable areas below are from the TG-RERA unit schedule. Carpet-area figures are software measurements from the filed floor-plan drawing, not RERA-filed carpet-area declarations; the drawing measurements are noted as requiring review RERA unit table Floor plans.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 120.77 sq.m. | 63.8–76.5 sq.m. (median 70.2 sq.m.) | 42% |
| 3BHK | 10 | 0 | 10 | 142.32 sq.m. | 92.8–96.6 sq.m. (median 95.9 sq.m.) | 33% |
The floor-plan extraction includes a 2BHK example with a living/dining area, kitchen, two bedrooms, two toilets, balcony and utility. A 3BHK example includes a hall, dining area, kitchen, three bedrooms, three toilets and a balcony. The listed room dimensions are drawing-derived measurements; they are not RERA disclosures RERA unit details.
Carpet area is the software-measured internal area from the drawing geometry. The filed saleable area is a separate RERA figure and includes more than the measured carpet area; the supplied drawing analysis describes it as also counting the home’s share of common areas. Balcony and utility are identified separately from carpet area in the drawing extraction Floor plans RERA unit details.
5. Parking & vehicle circulation
The approval states that the cellar and stilt areas approved for parking are to be used exclusively for vehicle parking and not partitioned, shuttered or converted to another use. It does not provide a count of car or two-wheeler spaces, visitor or accessible spaces, or a documented parking-allocation schedule.
The project’s RERA unit schedule marks both the 2BHK and 3BHK configurations as mortgaged, but does not establish parking allotment or ownership for any apartment RERA unit table. No parking ramp, driveway, entry/exit or pedestrian-separation details are available in the supplied drawing-derived data.
6. Amenities, recreation & open spaces
The listed items and percentages below are from the supplied RERA amenity record. The percentages are recorded status figures, not independent verification of completion RERA amenities.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Clubhouse / indoor | No clubhouse or indoor facility is identified in the supplied record | RERA amenities | Not disclosed |
| Sports / recreation | Green Strip/TOT LOT/Park; no area or capacity stated | RERA amenities | 0%; not independently verified |
| Landscape / open space | Green Strip/TOT LOT/Park; approval requires a fenced tot-lot maintained as greenery and a peripheral green strip; no area stated | RERA amenities | RERA amenity record: 0%; no completion verification |
| Convenience / community | Community Buildings; no description or size stated | RERA amenities | 0% |
| Convenience / community | Internal Roads & Footpaths | RERA amenities | 0% |
| Convenience / community | Street Lighting | RERA amenities | 0% |
7. Utilities, building services & safety
The RERA amenity record marks water supply as available, with progress recorded at 30%; it does not specify the source, storage, treatment or capacity. Sewerage (chamber, lines, septic tank, STP), storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management and disposal, and water conservation/rainwater harvesting are marked “YES,” each with 0% progress. The record does not give capacities or establish completed operation RERA amenities.
The approval records nine rainwater-harvesting structures and requires a transformer space, a garbage house within the premises, and a rainwater-harvesting percolation pit. It also states that public water and electricity connections will be provided only on production of an occupancy certificate. No water-treatment or reuse capacity, electrical backup details, lift count or capacity, fire-system specification, CCTV/security system, waste-segregation details, or accessible circulation details are established by the supplied project records. The approval assigns responsibility for structural and fire safety to the owner, builder/developer and technical professionals, but that condition alone does not establish completed systems or statutory compliance.
8. Location, access & connectivity
The registered project location is Theegalaguttapally, revenue village Arepalle, mandal Karimnagar -I, district Karimnagar, PIN 505001. The building approval describes the site as Arepalli (Part), and records a 30 Feet Wide Road along the west boundary RERA record.
The supplied location data lists an approximate distance of 113.0 km to the nearest sampled Outer Ring Road interchange. No public-transport links, additional approach-road details or local landmark distances are documented in the supplied evidence Location record.
9. Developer & development status
TG-RERA identifies VISHWAS CONSTRUCTIONS as the registered promoter and records the organization type as Proprietorship. The supplied promoter record names ARUNA SANGA as proprietor and authorized signatory. A PAN-like identifier is partially masked in the record; no unmasked corporate identifier or official promoter website/contact details are supplied Corporate record RERA filing.
The RERA Form-B declaration by Smt. Sanga Aruna states a completion date of 04 June 2025 and gives project fund-management undertakings. The supplied evidence does not provide independently verified construction progress or an occupancy certificate. The registration validity period ending 4 June 2025 is separate from that completion undertaking.
10. Approvals, official records & documents
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form ‘C’ registration certificate for SRI KIRSHNA RESIDENCY, P02700006102, valid from 19/04/2023 through 04/06/2025 |
| Building approval | Karimnagar Municipal Corporation building-construction approval 0015/BP/3011/2022, dated 04 June 2022; file no. 001645/BP/DTCP/3011/0016/2022 |
| Approved building configuration | One stilt plus five upper floors; approval records a 15 m height, 1,695.40 sq.m. residential upper-floor area and 359.51 sq.m. stilt area |
| Layout / floor-plan material | A layout-plan document is listed in the TG-RERA filings but has no extracted layout detail in the supplied material; floor-plan drawing measurements are available from document 291820 |
| Form-B declaration | Promoter declaration identifies Sanga Ramesh and Lambu Vinod as landowners and states a 04 June 2025 completion undertaking; the extracted record does not show a completed declaration date |
| Occupancy / completion evidence | No occupancy or completion certificate is included in the supplied project documents Document index |
1. Project at a glance
Project identity
Registered name: SRI KIRSHNA RESIDENCY
Project type: Residential apartment project
Phase / registered portion: No separate phase name is disclosed. The TG-RERA record identifies the project site as plots 10/A, 11/A and 12/A
TG-RERA registration: P02700006102
Registration validity: 19 April 2023 to 4 June 2025; the supplied certificate says “2 years” and no extension is recorded in the supplied registration data
Registered promoter: VISHWAS CONSTRUCTIONS; entity type recorded as Proprietorship
RERA status: The supplied registration record gives an expiry date of 4 June 2025; it does not establish a current extension or a current registration status
Land and geographic identity
Locality: Theegalaguttapally
Revenue village: Arepalle; the building approval describes “Arepalli (Part)”
Mandal: Karimnagar -I
District / PIN: Karimnagar / 505001
Project survey number and subdivision: 276/B
Registered site extent: 698.63 sq.m.
Total / net area: Total area 698.63 sq.m.; net area 698.63 sq.m.
Boundaries: East: Plot of K Ram Reddy and House of M Prabhakar Reddy; West: 30 Feet Wide Road; North: Plot No 9 by A; South: Plot No 13 by A
Development identity
Sanctioning authority: Karimnagar Municipal Corporation
Principal building approval: 0015/BP/3011/2022, dated 04 June 2022; file no. 001645/BP/DTCP/3011/0016/2022
Approved built-up area: 1,695.40 sq.m. residential upper-floor area; the approval separately records 359.51 sq.m. stilt area
Building count and configuration: One residential building, identified in the approval as “Building - RAMESH (VINOD)”; one stilt plus five upper floors
Height / parking: Approval records a height of 15 m and states cellar and stilts approved for parking; no parking-space count is supplied
Unit count: The filed unit schedule lists 15 apartments. The approval document does not provide an approved unit-count figure in the supplied extraction
Offering and status
RERA-filed configurations: 2BHK: 5 units; 3BHK: 10 units
RERA-filed saleable area: 2BHK: 120.77 sq.m.; 3BHK: 142.32 sq.m.
Booked / available: Portal-derived counts show 0 booked and 5 available 2BHKs; 0 booked and 10 available 3BHKs. The portal record has no as-of date, so these counts are indicative
Construction stage: The supplied record does not establish a current construction stage or independently verified site progress. The RERA-filed amenity/status data marks water supply at 30% and the other listed infrastructure items at 0%
Completion deadline: The Form-B declaration states a project-completion date of 04 June 2025; this is distinct from the registration-validity period
Occupancy / completion certificate: No occupancy or completion certificate is included in the supplied project documents. The building approval requires completion notice and an occupancy certificate before occupation
2. The project story
SRI KIRSHNA RESIDENCY is a residential apartment project registered for plots 10/A, 11/A and 12/A in Theegalaguttapally, Arepalle (also described in the approval as Arepalli (Part)), Karimnagar district. Its RERA-identified land is survey 276/B, with a site extent of 698.63 sq.m.
The building approval describes one residential building with one stilt and five upper floors. The RERA schedule lists 15 apartments: five 2BHK and ten 3BHK units. These are filed project and unit details; the supplied evidence does not establish that construction is complete, independently confirm the current site condition, or document an occupancy certificate.
3. Master plan, architecture & building design
The supplied building approval is for a residential building on the project plots and records a site area and net area of 698.63 sq.m. It identifies one building, “Building - RAMESH (VINOD),” configured as one stilt plus five upper floors, with a stated height of 15 m. Approved residential upper-floor area is recorded as 1,695.40 sq.m.; stilt area is separately recorded as 359.51 sq.m. These are approval figures, not carpet or saleable areas.
The approval also records a second-floor area of 220.19 sq.m. associated with a mortgage entry, and nine rainwater-harvesting structures. It lists no tot-lot area (“NA”) and no tree count (“NA”) in the supplied approval extraction. The site plan/layout-plan document filed with TG-RERA is not extracted into usable layout details here; internal building circulation, lifts, stairs, floor-by-floor apartment arrangement, building footprint, and detailed open-space design are therefore not established by the supplied material.
4. Homes, configurations & floor plans
The unit counts and saleable areas below are from the TG-RERA unit schedule. Carpet-area figures are software measurements from the filed floor-plan drawing, not RERA-filed carpet-area declarations; the drawing measurements are noted as requiring review.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 2BHK | 5 | 0 | 5 | 120.77 sq.m. | 63.8–76.5 sq.m. (median 70.2 sq.m.) | 42% |
| 3BHK | 10 | 0 | 10 | 142.32 sq.m. | 92.8–96.6 sq.m. (median 95.9 sq.m.) | 33% |
The floor-plan extraction includes a 2BHK example with a living/dining area, kitchen, two bedrooms, two toilets, balcony and utility. A 3BHK example includes a hall, dining area, kitchen, three bedrooms, three toilets and a balcony. The listed room dimensions are drawing-derived measurements; they are not RERA disclosures.
Carpet area is the software-measured internal area from the drawing geometry. The filed saleable area is a separate RERA figure and includes more than the measured carpet area; the supplied drawing analysis describes it as also counting the home’s share of common areas. Balcony and utility are identified separately from carpet area in the drawing extraction.
5. Parking & vehicle circulation
The approval states that the cellar and stilt areas approved for parking are to be used exclusively for vehicle parking and not partitioned, shuttered or converted to another use. It does not provide a count of car or two-wheeler spaces, visitor or accessible spaces, or a documented parking-allocation schedule.
The project’s RERA unit schedule marks both the 2BHK and 3BHK configurations as mortgaged, but does not establish parking allotment or ownership for any apartment. No parking ramp, driveway, entry/exit or pedestrian-separation details are available in the supplied drawing-derived data.
6. Amenities, recreation & open spaces
The listed items and percentages below are from the supplied RERA amenity record. The percentages are recorded status figures, not independent verification of completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Clubhouse / indoor | No clubhouse or indoor facility is identified in the supplied record | Not disclosed | |
| Sports / recreation | Green Strip/TOT LOT/Park; no area or capacity stated | 0%; not independently verified | |
| Landscape / open space | Green Strip/TOT LOT/Park; approval requires a fenced tot-lot maintained as greenery and a peripheral green strip; no area stated | RERA amenity record: 0%; no completion verification | |
| Convenience / community | Community Buildings; no description or size stated | 0% | |
| Convenience / community | Internal Roads & Footpaths | 0% | |
| Convenience / community | Street Lighting | 0% |
7. Utilities, building services & safety
The RERA amenity record marks water supply as available, with progress recorded at 30%; it does not specify the source, storage, treatment or capacity. Sewerage (chamber, lines, septic tank, STP), storm-water drains, treatment and disposal of sewage and sullage water, solid-waste management and disposal, and water conservation/rainwater harvesting are marked “YES,” each with 0% progress. The record does not give capacities or establish completed operation.
The approval records nine rainwater-harvesting structures and requires a transformer space, a garbage house within the premises, and a rainwater-harvesting percolation pit. It also states that public water and electricity connections will be provided only on production of an occupancy certificate. No water-treatment or reuse capacity, electrical backup details, lift count or capacity, fire-system specification, CCTV/security system, waste-segregation details, or accessible circulation details are established by the supplied project records. The approval assigns responsibility for structural and fire safety to the owner, builder/developer and technical professionals, but that condition alone does not establish completed systems or statutory compliance.
8. Location, access & connectivity
The registered project location is Theegalaguttapally, revenue village Arepalle, mandal Karimnagar -I, district Karimnagar, PIN 505001. The building approval describes the site as Arepalli (Part), and records a 30 Feet Wide Road along the west boundary.
The supplied location data lists an approximate distance of 113.0 km to the nearest sampled Outer Ring Road interchange. No public-transport links, additional approach-road details or local landmark distances are documented in the supplied evidence.
9. Developer & development status
TG-RERA identifies VISHWAS CONSTRUCTIONS as the registered promoter and records the organization type as Proprietorship. The supplied promoter record names ARUNA SANGA as proprietor and authorized signatory. A PAN-like identifier is partially masked in the record; no unmasked corporate identifier or official promoter website/contact details are supplied.
The RERA Form-B declaration by Smt. Sanga Aruna states a completion date of 04 June 2025 and gives project fund-management undertakings. The supplied evidence does not provide independently verified construction progress or an occupancy certificate. The registration validity period ending 4 June 2025 is separate from that completion undertaking.
10. Approvals, official records & documents
TG-RERA registration: Form ‘C’ registration certificate for SRI KIRSHNA RESIDENCY, P02700006102, valid from 19/04/2023 through 04/06/2025
Building approval: Karimnagar Municipal Corporation building-construction approval 0015/BP/3011/2022, dated 04 June 2022; file no. 001645/BP/DTCP/3011/0016/2022
Approved building configuration: One stilt plus five upper floors; approval records a 15 m height, 1,695.40 sq.m. residential upper-floor area and 359.51 sq.m. stilt area
Layout / floor-plan material: A layout-plan document is listed in the TG-RERA filings but has no extracted layout detail in the supplied material; floor-plan drawing measurements are available from document 291820
Form-B declaration: Promoter declaration identifies Sanga Ramesh and Lambu Vinod as landowners and states a 04 June 2025 completion undertaking; the extracted record does not show a completed declaration date
Occupancy / completion evidence: No occupancy or completion certificate is included in the supplied project documents
Frequently asked questions
Is SRI KIRSHNA RESIDENCY registered with Telangana RERA?
Yes. SRI KIRSHNA RESIDENCY is registered with the Telangana Real Estate Regulatory Authority as P02700006102; the registration status is New Project.
Who is the developer of SRI KIRSHNA RESIDENCY?
The promoter named in the RERA registration is VISHWAS CONSTRUCTIONS.
Where is SRI KIRSHNA RESIDENCY located?
SRI KIRSHNA RESIDENCY is in Theegalaguttapally, Arepalle, Karimnagar -I, Karimnagar, Telangana (505001).
When will SRI KIRSHNA RESIDENCY be completed?
The promoter's proposed date of completion filed with RERA is 04/06/2025. This is the promoter's declaration, not a guarantee.
More projects in Arepalle