DPRs RAGA
DPR INFRA PROJECTS PRIVATE LIMITED · Medchal-Malkajgiri · RERA P02200010267
DPRs RAGA is a residential apartment project at Plot No. 1376 Western Part, Uppal, Uppal mandal, Medchal-Malkajgiri district, developed by DPR INFRA PROJECTS PRIVATE LIMITED. The registered site area is 399.61 sq. m, with one residential building comprising 1 Stilt + 5 Floors and 10 homes, configured as 3BHK. It is registered with TG-RERA under P02200010267, with proposed completion on 02/01/2029.
More from Dpr Infra Projects Pvt Ltd · 6 projects →
01What we found
Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.
02Check before you pay
8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.
1. Project at a glance
Project identity
| Item | TG-RERA record |
|---|---|
| Registered project name | DPRs RAGA RERA record |
| Project type | Residential apartment project RERA record |
| Phase / registered portion | No separate phase name is stated; registration covers the project identified at Plot No. 1376 Western Part RERA record |
| TG-RERA registration number | P02200010267 RERA record |
| Registration validity | 02/09/2025 to 02/09/2028; this is registration validity, not a statement that the project is completed by that date RERA record |
| Registered promoter | DPR INFRA PROJECTS PRIVATE LIMITED RERA record Corporate record |
| RERA status | Registered; TG-RERA data identifies the project as New Project RERA record Approvals record |
Land and geographic identity
| Item | Record |
|---|---|
| Locality / plot | Uppal; PLOT NO 1376 WESTERN PART RERA filing |
| Revenue village | Uppal; the building-permit record describes the site as Uppal Bhagayath, Uppal RERA record |
| Mandal | Uppal RERA record |
| District | Medchal-Malkajgiri RERA record |
| PIN | 500039 RERA record |
| Project survey numbers | 1 to 40, 282 TO 368, 369/PART, 370 TO 373, 374/PART, 375 TO 387, 395 TO 401, 454, 456 TO 459, 505/PART, 510 TO 564 RERA record |
| Registered site extent | 399.61 sq. m (also recorded as 399.61 Sq. Mt.) RERA filing |
| Total / net area | Total area 399.61 sq. m; net area 399.61 sq. m RERA filing |
| Boundaries in RERA filing | North: 60 FEET WIDE ROAD; south: PLOT NO 1407; east: PART IN PLOT NO 1376 EASTERN PART; west: PLOT NO 1375 RERA filing |
Development identity
| Item | Record |
|---|---|
| Sanctioning authority | Greater Hyderabad Municipal Corporation (GHMC) |
| Principal building approval | Building Permit Order 0926/GHMC/SWBP/LBN2/2025, approved 02/09/2025 Approvals record |
| File number | 001358/GHMC/00867/SWBP/LBN2/2025 |
| Approved built-up area | 1103.45 sq. m excluding parking; the record separately states 1324.14 sq. m including parking |
| Building count and configuration | One residential building, Building - 1; 1 Stilt + 5 Floors |
| Floor arrangement in approval record | Stilt and first to fifth floors; the fifth floor is identified as TDR |
| Building height | 17.95m recorded as proposed; the approval record also lists permissible height 12.00m |
| Parking provision | 6.00 Car Parking Spaces; proposed parking area 220.69 sq. m |
| Approved / RERA-declared homes | 10 dwelling units in the building-permit record; TG-RERA unit data also records 10 units RERA unit table |
Offering and status
| Item | Record |
|---|---|
| RERA-filed configuration | 3BHK RERA unit table |
| RERA-filed saleable area | 138.89 sq. m per unit RERA unit table |
| Booked / available | 0 booked; 10 available, as last read from the TG-RERA portal. No as-of date is supplied, so counts are indicative RERA unit table |
| Construction stage | No independently verified site-progress stage is supplied. TG-RERA amenities data reports 0% against listed progress items; this does not independently establish site construction progress RERA amenities |
| Completion dates | GHMC permit record: construction to be completed before 02/09/2028. Form B declaration: completion on or before 02/09/2028. The project header separately records proposed completion 02/01/2029 RERA record |
| Occupancy / completion certificate | The supplied approval extraction records completion_certified: false; no occupancy or completion certificate is supplied |
2. The project story
DPRs RAGA is a registered residential apartment project on Plot No. 1376 Western Part at Uppal, in Uppal mandal, Medchal-Malkajgiri district. The registered site is 399.61 sq. m and is identified by the project survey-number schedule listed above. RERA record RERA filing
The GHMC permit record describes one residential building with a stilt and five floors, and records 10 dwelling units. TG-RERA records the offering as ten 3BHK units. The portal’s last-read inventory shows all ten available and none booked; the portal data has no as-of date. RERA unit table
The supplied material does not establish a verified current construction stage or a completed or occupancy-certified portion. The permit and Form B record a completion deadline of 02/09/2028, while the project header records a proposed completion date of 02/01/2029; the dates are stated here as recorded, without treating either as evidence of progress or completion. RERA record
3. Master plan, architecture & building design
The sanctioned record describes a single residential building on a 399.61 sq. m net plot. It records proposed coverage of 220.68 sq. m (55.00 %), vacant plot area of 176.81 sq. m, and proposed built-up area of 1103.45 sq. m excluding parking. The same approval data separately records 1324.14 sq. m including parking and 1343.21 sq. m as gross BUA; these are distinct filed area measures.
The building is recorded as 1 Stilt + 5 Floors, with residential upper floors from first through fifth; the fifth-floor area is identified as TDR. The floor-level BUA entries are 220.69 sq. m each for stilt and floors one through five, with terrace BUA 19.07 sq. m. The recorded proposed building height is 17.95m; the approval record also lists permissible height 12.00m.
The approval extract gives setbacks of front 4.00m, rear 2.00m, and 2.00m on each side. It refers to an 18.0m road width. The supplied material does not provide a reliable drawing-derived account of the building footprint layout, flats per floor, lifts, stairs, entrances, internal circulation, or detailed common-area arrangement.
4. Homes, configurations & floor plans
TG-RERA records ten 3BHK units, with a saleable area of 138.89 sq. m each. The supplied floor-plan measurement data identifies 3BHK drawings and reports software-measured carpet area of 69.3–69.6 sq. m (median 69.3 sq. m; 746–749 sq. ft.). These drawing-based measurements are not RERA disclosures and are marked as needing review. Saleable area and carpet area are different measures; the supplied material does not provide a verified breakdown of common-area loading. RERA unit table Floor plans
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 138.89 sq. m | 69.3–69.6 sq. m; software-measured from drawings, not RERA-filed | 50% Floor plans |
The floor-plan measurement extract describes a three-bedroom arrangement and marks balcony and utility areas separately from carpet area. The supplied room-level measurements are incomplete for some spaces, so this overview does not treat them as a complete unit specification. RERA unit details
5. Parking & vehicle circulation
The GHMC approval record provides 6.00 Car Parking Spaces and 220.69 sq. m of proposed parking area. Parking is associated with the stilt in the building record; the approval conditions state that approved cellar and stilt parking must be used exclusively for vehicle parking. No separate visitor, accessible, two-wheeler, or mechanical-parking counts are supplied, and no unit-specific parking allocation is established by the supplied documents.
The permit identifies an 18.0m road width but the supplied evidence does not describe ramp dimensions, driveway layout, vehicle entry/exit arrangements, or pedestrian separation. GHMC’s approval record includes an EV charging infrastructure condition for parking places; it does not establish that charging equipment has been installed or completed.
6. Amenities, recreation & open spaces
The GHMC approval record names a tot-lot, rainwater-harvesting pit(s), trees, transformer space, garbage house and EV charging infrastructure. Its conditions also require periphery greenery and maintenance of the tot-lot as greenery. TG-RERA’s amenities record lists the following items and records 0% progress for the listed progress fields; this is a portal declaration, not independent verification of site completion. RERA amenities
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green strip | Size not supplied; approval condition says tot-lot to be fenced and maintained as greenery | RERA amenities | GHMC approval condition; TG-RERA progress field 0%; completion not independently verified |
| Trees / periphery greenery | Approval record specifies 10 trees and periphery greenery | Approval-record provision; planting status not independently verified | |
| Rainwater harvesting | One rainwater-harvesting pit is recorded | Approval-record provision; completion not independently verified | |
| Internal roads and footpaths | No dimensions supplied | RERA amenities | TG-RERA progress field 0%; completion not independently verified |
| Water supply | Listed as available “YES” in the TG-RERA amenities record | RERA amenities | Portal-listed; progress field 0%; operating status not independently verified |
| Sewerage / sewage treatment | “Sewerage (Chamber, Lines, Septic Tank, STP)” listed as available “YES” | RERA amenities | Portal-listed; progress field 0%; facility type and operating status not independently verified |
| Storm-water drains | No dimensions or design details supplied | RERA amenities | TG-RERA progress field 0%; completion not independently verified |
| Street lighting | No details supplied | RERA amenities | TG-RERA progress field 0%; completion not independently verified |
| Community buildings | No description or size supplied | RERA amenities | TG-RERA progress field 0%; completion not independently verified |
| Sewage and sullage treatment/disposal | No capacity or process details supplied | RERA amenities | TG-RERA progress field 0%; completion not independently verified |
| Solid-waste management and disposal | No capacity or method details supplied | RERA amenities | TG-RERA progress field 0%; completion not independently verified |
| Electrical meter room / sub-station / receiving station | Approval record requires space for a transformer | RERA amenities | Portal-listed; installed or operational status not independently verified |
| Recreational open space | Area not supplied | RERA amenities | TG-RERA progress field 0%; completion not independently verified |
7. Utilities, building services & safety
The approval record requires space for a transformer, a garbage house and rainwater harvesting, and contains conditions relating to sanitation, plumbing, fire-safety requirements, lifts and electrical installations. The supplied project-specific evidence does not state water-source or storage capacities, STP capacity, reuse arrangements, backup-power capacity, lift count or capacity, or a completed fire-safety installation. RERA amenities
The permit conditions require an Occupancy Fire NOC from the Director (EV&DM) before an occupancy certificate. They also state that an occupancy certificate is required before occupation and that regular service connections are to be provided before possession. These are approval conditions, not evidence that the systems or certificates have been completed or obtained.
The approval record includes an EV charging infrastructure condition for parking places. No installed EV charger, CCTV, security system, accessibility arrangement, ramp or accessible-circulation detail is established by the supplied project-specific records.
8. Location, access & connectivity
The registered location is Uppal, Uppal mandal, Medchal-Malkajgiri district, PIN 500039, at Plot No. 1376 Western Part. The RERA filing’s site boundary description identifies a 60-foot-wide road to the north. The building permit record also refers to an 18.0m road width. RERA record RERA filing
The supplied location data identifies Financial District (Nanakramguda), 2.0 km as a location anchor, measured from the cadastral parcel centroid recorded at 17.40121, 78.35418. The evidence does not provide a project-specific public-transport or approach-road route description. Location record
9. Developer & development status
The registered legal promoter is DPR INFRA PROJECTS PRIVATE LIMITED, a private limited company, GSTIN 36AAICD4960B1ZT. The promoter address recorded in the project filing is SHIV RESIDENCY, ROAD NO 1, SAI NAGAR COLONY, UPPAL BAGAYATH HMDA LAYOUT, UNDER GHMC UPPAL CIRCLE, UPPAL, Uppal, Medchal-Malkajgiri, 500039. The project filing identifies NAYINI DHARMAPAL REDDY as authorized signatory and NAYINI SAI CHARAN REDDY as director. Corporate record Parties record
The project is registered as a single-building apartment development. No independently verified construction-progress assessment is provided in the supplied records. The Form B affidavit, verified at Hyderabad on 10/10/2025, declares a completion date on or before 02/09/2028; the GHMC permit also records construction to be completed before 02/09/2028. The project header separately records 02/01/2029 as the proposed completion date. RERA record
10. Approvals, official records & documents
| Identifier / date | P02200010267; validity 02/09/2025–02/09/2028 |
|---|---|
| What it establishes | Registration of DPRs RAGA under DPR INFRA PROJECTS PRIVATE LIMITED |
| Identifier / date | 0926/GHMC/SWBP/LBN2/2025; approved 02/09/2025 |
|---|---|
| What it establishes | Building permit for one residential building at Plot No. 1376 Western Part, recording 10 dwelling units |
| Identifier / date | 001358/GHMC/00867/SWBP/LBN2/2025 |
|---|---|
| What it establishes | Permit-file identifier |
| Identifier / date | 71563/HMDA / DEVELOPMENT/PD-1/UPPAL BHAGATH V/17 |
|---|---|
| What it establishes | Layout reference cited in the GHMC permit |
| Identifier / date | Verified 10/10/2025 |
|---|---|
| What it establishes | Promoter declaration concerning title, encumbrances, project funds, approvals and completion undertaking |
| What it establishes | Building configuration, areas, parking, setbacks and permit conditions |
|---|
| Identifier / date | Not supplied; approval extract records completion certification as false |
|---|---|
| What it establishes | No supplied evidence of an issued occupancy or completion certificate |
The GHMC permit names the building as Building - 1 and identifies the project survey schedule as 1 To 40; 282 To 368; 369 Part; 370 To 373; 374 Part; 375 To 387; 395 To 401; 454; 456 To 459; 505 Part; 510 To 564.
1. Project at a glance
Project identity
Registered project name: DPRs RAGA
Project type: Residential apartment project
Phase / registered portion: No separate phase name is stated; registration covers the project identified at Plot No. 1376 Western Part
TG-RERA registration number: P02200010267
Registration validity: 02/09/2025 to 02/09/2028; this is registration validity, not a statement that the project is completed by that date
Registered promoter: DPR INFRA PROJECTS PRIVATE LIMITED
RERA status: Registered; TG-RERA data identifies the project as New Project
Land and geographic identity
Locality / plot: Uppal; PLOT NO 1376 WESTERN PART
Revenue village: Uppal; the building-permit record describes the site as Uppal Bhagayath, Uppal
Mandal: Uppal
District: Medchal-Malkajgiri
PIN: 500039
Project survey numbers: 1 to 40, 282 TO 368, 369/PART, 370 TO 373, 374/PART, 375 TO 387, 395 TO 401, 454, 456 TO 459, 505/PART, 510 TO 564
Registered site extent: 399.61 sq. m (also recorded as 399.61 Sq. Mt.)
Total / net area: Total area 399.61 sq. m; net area 399.61 sq. m
Boundaries in RERA filing: North: 60 FEET WIDE ROAD; south: PLOT NO 1407; east: PART IN PLOT NO 1376 EASTERN PART; west: PLOT NO 1375
Development identity
Sanctioning authority: Greater Hyderabad Municipal Corporation (GHMC)
Principal building approval: Building Permit Order 0926/GHMC/SWBP/LBN2/2025, approved 02/09/2025
File number: 001358/GHMC/00867/SWBP/LBN2/2025
Approved built-up area: 1103.45 sq. m excluding parking; the record separately states 1324.14 sq. m including parking
Building count and configuration: One residential building, Building - 1; 1 Stilt + 5 Floors
Floor arrangement in approval record: Stilt and first to fifth floors; the fifth floor is identified as TDR
Building height: 17.95m recorded as proposed; the approval record also lists permissible height 12.00m
Parking provision: 6.00 Car Parking Spaces; proposed parking area 220.69 sq. m
Approved / RERA-declared homes: 10 dwelling units in the building-permit record; TG-RERA unit data also records 10 units
Offering and status
RERA-filed configuration: 3BHK
RERA-filed saleable area: 138.89 sq. m per unit
Booked / available: 0 booked; 10 available, as last read from the TG-RERA portal. No as-of date is supplied, so counts are indicative
Construction stage: No independently verified site-progress stage is supplied. TG-RERA amenities data reports 0% against listed progress items; this does not independently establish site construction progress
Completion dates: GHMC permit record: construction to be completed before 02/09/2028. Form B declaration: completion on or before 02/09/2028. The project header separately records proposed completion 02/01/2029
Occupancy / completion certificate: The supplied approval extraction records completion_certified: false; no occupancy or completion certificate is supplied
2. The project story
DPRs RAGA is a registered residential apartment project on Plot No. 1376 Western Part at Uppal, in Uppal mandal, Medchal-Malkajgiri district. The registered site is 399.61 sq. m and is identified by the project survey-number schedule listed above.
The GHMC permit record describes one residential building with a stilt and five floors, and records 10 dwelling units. TG-RERA records the offering as ten 3BHK units. The portal’s last-read inventory shows all ten available and none booked; the portal data has no as-of date.
The supplied material does not establish a verified current construction stage or a completed or occupancy-certified portion. The permit and Form B record a completion deadline of 02/09/2028, while the project header records a proposed completion date of 02/01/2029; the dates are stated here as recorded, without treating either as evidence of progress or completion.
3. Master plan, architecture & building design
The sanctioned record describes a single residential building on a 399.61 sq. m net plot. It records proposed coverage of 220.68 sq. m (55.00 %), vacant plot area of 176.81 sq. m, and proposed built-up area of 1103.45 sq. m excluding parking. The same approval data separately records 1324.14 sq. m including parking and 1343.21 sq. m as gross BUA; these are distinct filed area measures.
The building is recorded as 1 Stilt + 5 Floors, with residential upper floors from first through fifth; the fifth-floor area is identified as TDR. The floor-level BUA entries are 220.69 sq. m each for stilt and floors one through five, with terrace BUA 19.07 sq. m. The recorded proposed building height is 17.95m; the approval record also lists permissible height 12.00m.
The approval extract gives setbacks of front 4.00m, rear 2.00m, and 2.00m on each side. It refers to an 18.0m road width. The supplied material does not provide a reliable drawing-derived account of the building footprint layout, flats per floor, lifts, stairs, entrances, internal circulation, or detailed common-area arrangement.
4. Homes, configurations & floor plans
TG-RERA records ten 3BHK units, with a saleable area of 138.89 sq. m each. The supplied floor-plan measurement data identifies 3BHK drawings and reports software-measured carpet area of 69.3–69.6 sq. m (median 69.3 sq. m; 746–749 sq. ft.). These drawing-based measurements are not RERA disclosures and are marked as needing review. Saleable area and carpet area are different measures; the supplied material does not provide a verified breakdown of common-area loading.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| 3BHK | 10 | 0 | 10 | 138.89 sq. m | 69.3–69.6 sq. m; software-measured from drawings, not RERA-filed | 50% |
The floor-plan measurement extract describes a three-bedroom arrangement and marks balcony and utility areas separately from carpet area. The supplied room-level measurements are incomplete for some spaces, so this overview does not treat them as a complete unit specification.
5. Parking & vehicle circulation
The GHMC approval record provides 6.00 Car Parking Spaces and 220.69 sq. m of proposed parking area. Parking is associated with the stilt in the building record; the approval conditions state that approved cellar and stilt parking must be used exclusively for vehicle parking. No separate visitor, accessible, two-wheeler, or mechanical-parking counts are supplied, and no unit-specific parking allocation is established by the supplied documents.
The permit identifies an 18.0m road width but the supplied evidence does not describe ramp dimensions, driveway layout, vehicle entry/exit arrangements, or pedestrian separation. GHMC’s approval record includes an EV charging infrastructure condition for parking places; it does not establish that charging equipment has been installed or completed.
6. Amenities, recreation & open spaces
The GHMC approval record names a tot-lot, rainwater-harvesting pit(s), trees, transformer space, garbage house and EV charging infrastructure. Its conditions also require periphery greenery and maintenance of the tot-lot as greenery. TG-RERA’s amenities record lists the following items and records 0% progress for the listed progress fields; this is a portal declaration, not independent verification of site completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Tot-lot / green strip | Size not supplied; approval condition says tot-lot to be fenced and maintained as greenery | GHMC approval condition; TG-RERA progress field 0%; completion not independently verified | |
| Trees / periphery greenery | Approval record specifies 10 trees and periphery greenery | Approval-record provision; planting status not independently verified | |
| Rainwater harvesting | One rainwater-harvesting pit is recorded | Approval-record provision; completion not independently verified | |
| Internal roads and footpaths | No dimensions supplied | TG-RERA progress field 0%; completion not independently verified | |
| Water supply | Listed as available “YES” in the TG-RERA amenities record | Portal-listed; progress field 0%; operating status not independently verified | |
| Sewerage / sewage treatment | “Sewerage (Chamber, Lines, Septic Tank, STP)” listed as available “YES” | Portal-listed; progress field 0%; facility type and operating status not independently verified | |
| Storm-water drains | No dimensions or design details supplied | TG-RERA progress field 0%; completion not independently verified | |
| Street lighting | No details supplied | TG-RERA progress field 0%; completion not independently verified | |
| Community buildings | No description or size supplied | TG-RERA progress field 0%; completion not independently verified | |
| Sewage and sullage treatment/disposal | No capacity or process details supplied | TG-RERA progress field 0%; completion not independently verified | |
| Solid-waste management and disposal | No capacity or method details supplied | TG-RERA progress field 0%; completion not independently verified | |
| Electrical meter room / sub-station / receiving station | Approval record requires space for a transformer | Portal-listed; installed or operational status not independently verified | |
| Recreational open space | Area not supplied | TG-RERA progress field 0%; completion not independently verified |
7. Utilities, building services & safety
The approval record requires space for a transformer, a garbage house and rainwater harvesting, and contains conditions relating to sanitation, plumbing, fire-safety requirements, lifts and electrical installations. The supplied project-specific evidence does not state water-source or storage capacities, STP capacity, reuse arrangements, backup-power capacity, lift count or capacity, or a completed fire-safety installation.
The permit conditions require an Occupancy Fire NOC from the Director (EV&DM) before an occupancy certificate. They also state that an occupancy certificate is required before occupation and that regular service connections are to be provided before possession. These are approval conditions, not evidence that the systems or certificates have been completed or obtained.
The approval record includes an EV charging infrastructure condition for parking places. No installed EV charger, CCTV, security system, accessibility arrangement, ramp or accessible-circulation detail is established by the supplied project-specific records.
8. Location, access & connectivity
The registered location is Uppal, Uppal mandal, Medchal-Malkajgiri district, PIN 500039, at Plot No. 1376 Western Part. The RERA filing’s site boundary description identifies a 60-foot-wide road to the north. The building permit record also refers to an 18.0m road width.
The supplied location data identifies Financial District (Nanakramguda), 2.0 km as a location anchor, measured from the cadastral parcel centroid recorded at 17.40121, 78.35418. The evidence does not provide a project-specific public-transport or approach-road route description.
9. Developer & development status
The registered legal promoter is DPR INFRA PROJECTS PRIVATE LIMITED, a private limited company, GSTIN 36AAICD4960B1ZT. The promoter address recorded in the project filing is SHIV RESIDENCY, ROAD NO 1, SAI NAGAR COLONY, UPPAL BAGAYATH HMDA LAYOUT, UNDER GHMC UPPAL CIRCLE, UPPAL, Uppal, Medchal-Malkajgiri, 500039. The project filing identifies NAYINI DHARMAPAL REDDY as authorized signatory and NAYINI SAI CHARAN REDDY as director.
The project is registered as a single-building apartment development. No independently verified construction-progress assessment is provided in the supplied records. The Form B affidavit, verified at Hyderabad on 10/10/2025, declares a completion date on or before 02/09/2028; the GHMC permit also records construction to be completed before 02/09/2028. The project header separately records 02/01/2029 as the proposed completion date.
10. Approvals, official records & documents
| Identifier / date | P02200010267; validity 02/09/2025–02/09/2028 |
|---|---|
| What it establishes | Registration of DPRs RAGA under DPR INFRA PROJECTS PRIVATE LIMITED |
| Identifier / date | 0926/GHMC/SWBP/LBN2/2025; approved 02/09/2025 |
|---|---|
| What it establishes | Building permit for one residential building at Plot No. 1376 Western Part, recording 10 dwelling units |
| Identifier / date | 001358/GHMC/00867/SWBP/LBN2/2025 |
|---|---|
| What it establishes | Permit-file identifier |
| Identifier / date | 71563/HMDA / DEVELOPMENT/PD-1/UPPAL BHAGATH V/17 |
|---|---|
| What it establishes | Layout reference cited in the GHMC permit |
| Identifier / date | Verified 10/10/2025 |
|---|---|
| What it establishes | Promoter declaration concerning title, encumbrances, project funds, approvals and completion undertaking |
| What it establishes | Building configuration, areas, parking, setbacks and permit conditions |
|---|
| Identifier / date | Not supplied; approval extract records completion certification as false |
|---|---|
| What it establishes | No supplied evidence of an issued occupancy or completion certificate |
The GHMC permit names the building as Building - 1 and identifies the project survey schedule as 1 To 40; 282 To 368; 369 Part; 370 To 373; 374 Part; 375 To 387; 395 To 401; 454; 456 To 459; 505 Part; 510 To 564.
Frequently asked questions
Is DPRs RAGA registered with Telangana RERA?
Yes. DPRs RAGA is registered with the Telangana Real Estate Regulatory Authority as P02200010267; the registration status is New Project.
Who is the developer of DPRs RAGA?
The promoter named in the RERA registration is DPR INFRA PROJECTS PRIVATE LIMITED.
Where is DPRs RAGA located?
DPRs RAGA is in UPPAL, Medchal-Malkajgiri, Telangana (500039).
When will DPRs RAGA be completed?
The promoter's proposed date of completion filed with RERA is 02/01/2029. This is the promoter's declaration, not a guarantee.