Sign in

DPRs RAGA

DPR INFRA PROJECTS PRIVATE LIMITED · Medchal-Malkajgiri · RERA P02200010267

DPRs RAGA is a residential apartment project at Plot No. 1376 Western Part, Uppal, Uppal mandal, Medchal-Malkajgiri district, developed by DPR INFRA PROJECTS PRIVATE LIMITED. The registered site area is 399.61 sq. m, with one residential building comprising 1 Stilt + 5 Floors and 10 homes, configured as 3BHK. It is registered with TG-RERA under P02200010267, with proposed completion on 02/01/2029.

More from Dpr Infra Projects Pvt Ltd · 6 projects →

01What we found

RegisteredTG-RERA - valid till 2 Sep 2028
22documents on file - each fact links to its page
3court cases on this project's land (survey 1, Uppal)
8items to check - 3 high

Read from TG-RERA filings, approvals, land and registration records and court records. A court case is counted only when the court record states this project's survey number with its village, or names the project.

02Check before you pay

8 items to check before you pay, 3 high - from the title chain, court records and approvals, each with what to ask the builder or your advocate. An item may not be a problem with the project: records can be incomplete.

Sign in to see each item and what to do

1. Project at a glance

Project identity

ItemTG-RERA record
Registered project nameDPRs RAGA RERA record
Project typeResidential apartment project RERA record
Phase / registered portionNo separate phase name is stated; registration covers the project identified at Plot No. 1376 Western Part RERA record
TG-RERA registration numberP02200010267 RERA record
Registration validity02/09/2025 to 02/09/2028; this is registration validity, not a statement that the project is completed by that date RERA record
Registered promoterDPR INFRA PROJECTS PRIVATE LIMITED RERA record Corporate record
RERA statusRegistered; TG-RERA data identifies the project as New Project RERA record Approvals record

Land and geographic identity

ItemRecord
Locality / plotUppal; PLOT NO 1376 WESTERN PART RERA filing
Revenue villageUppal; the building-permit record describes the site as Uppal Bhagayath, Uppal RERA record
MandalUppal RERA record
DistrictMedchal-Malkajgiri RERA record
PIN500039 RERA record
Project survey numbers1 to 40, 282 TO 368, 369/PART, 370 TO 373, 374/PART, 375 TO 387, 395 TO 401, 454, 456 TO 459, 505/PART, 510 TO 564 RERA record
Registered site extent399.61 sq. m (also recorded as 399.61 Sq. Mt.) RERA filing
Total / net areaTotal area 399.61 sq. m; net area 399.61 sq. m RERA filing
Boundaries in RERA filingNorth: 60 FEET WIDE ROAD; south: PLOT NO 1407; east: PART IN PLOT NO 1376 EASTERN PART; west: PLOT NO 1375 RERA filing

Development identity

ItemRecord
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC)
Principal building approvalBuilding Permit Order 0926/GHMC/SWBP/LBN2/2025, approved 02/09/2025 Approvals record
File number001358/GHMC/00867/SWBP/LBN2/2025
Approved built-up area1103.45 sq. m excluding parking; the record separately states 1324.14 sq. m including parking
Building count and configurationOne residential building, Building - 1; 1 Stilt + 5 Floors
Floor arrangement in approval recordStilt and first to fifth floors; the fifth floor is identified as TDR
Building height17.95m recorded as proposed; the approval record also lists permissible height 12.00m
Parking provision6.00 Car Parking Spaces; proposed parking area 220.69 sq. m
Approved / RERA-declared homes10 dwelling units in the building-permit record; TG-RERA unit data also records 10 units RERA unit table

Offering and status

ItemRecord
RERA-filed configuration3BHK RERA unit table
RERA-filed saleable area138.89 sq. m per unit RERA unit table
Booked / available0 booked; 10 available, as last read from the TG-RERA portal. No as-of date is supplied, so counts are indicative RERA unit table
Construction stageNo independently verified site-progress stage is supplied. TG-RERA amenities data reports 0% against listed progress items; this does not independently establish site construction progress RERA amenities
Completion datesGHMC permit record: construction to be completed before 02/09/2028. Form B declaration: completion on or before 02/09/2028. The project header separately records proposed completion 02/01/2029 RERA record
Occupancy / completion certificateThe supplied approval extraction records completion_certified: false; no occupancy or completion certificate is supplied

2. The project story

DPRs RAGA is a registered residential apartment project on Plot No. 1376 Western Part at Uppal, in Uppal mandal, Medchal-Malkajgiri district. The registered site is 399.61 sq. m and is identified by the project survey-number schedule listed above. RERA record RERA filing

The GHMC permit record describes one residential building with a stilt and five floors, and records 10 dwelling units. TG-RERA records the offering as ten 3BHK units. The portal’s last-read inventory shows all ten available and none booked; the portal data has no as-of date. RERA unit table

The supplied material does not establish a verified current construction stage or a completed or occupancy-certified portion. The permit and Form B record a completion deadline of 02/09/2028, while the project header records a proposed completion date of 02/01/2029; the dates are stated here as recorded, without treating either as evidence of progress or completion. RERA record

3. Master plan, architecture & building design

The sanctioned record describes a single residential building on a 399.61 sq. m net plot. It records proposed coverage of 220.68 sq. m (55.00 %), vacant plot area of 176.81 sq. m, and proposed built-up area of 1103.45 sq. m excluding parking. The same approval data separately records 1324.14 sq. m including parking and 1343.21 sq. m as gross BUA; these are distinct filed area measures.

The building is recorded as 1 Stilt + 5 Floors, with residential upper floors from first through fifth; the fifth-floor area is identified as TDR. The floor-level BUA entries are 220.69 sq. m each for stilt and floors one through five, with terrace BUA 19.07 sq. m. The recorded proposed building height is 17.95m; the approval record also lists permissible height 12.00m.

The approval extract gives setbacks of front 4.00m, rear 2.00m, and 2.00m on each side. It refers to an 18.0m road width. The supplied material does not provide a reliable drawing-derived account of the building footprint layout, flats per floor, lifts, stairs, entrances, internal circulation, or detailed common-area arrangement.

4. Homes, configurations & floor plans

TG-RERA records ten 3BHK units, with a saleable area of 138.89 sq. m each. The supplied floor-plan measurement data identifies 3BHK drawings and reports software-measured carpet area of 69.3–69.6 sq. m (median 69.3 sq. m; 746–749 sq. ft.). These drawing-based measurements are not RERA disclosures and are marked as needing review. Saleable area and carpet area are different measures; the supplied material does not provide a verified breakdown of common-area loading. RERA unit table Floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
3BHK10010138.89 sq. m69.3–69.6 sq. m; software-measured from drawings, not RERA-filed50% Floor plans

The floor-plan measurement extract describes a three-bedroom arrangement and marks balcony and utility areas separately from carpet area. The supplied room-level measurements are incomplete for some spaces, so this overview does not treat them as a complete unit specification. RERA unit details

5. Parking & vehicle circulation

The GHMC approval record provides 6.00 Car Parking Spaces and 220.69 sq. m of proposed parking area. Parking is associated with the stilt in the building record; the approval conditions state that approved cellar and stilt parking must be used exclusively for vehicle parking. No separate visitor, accessible, two-wheeler, or mechanical-parking counts are supplied, and no unit-specific parking allocation is established by the supplied documents.

The permit identifies an 18.0m road width but the supplied evidence does not describe ramp dimensions, driveway layout, vehicle entry/exit arrangements, or pedestrian separation. GHMC’s approval record includes an EV charging infrastructure condition for parking places; it does not establish that charging equipment has been installed or completed.

6. Amenities, recreation & open spaces

The GHMC approval record names a tot-lot, rainwater-harvesting pit(s), trees, transformer space, garbage house and EV charging infrastructure. Its conditions also require periphery greenery and maintenance of the tot-lot as greenery. TG-RERA’s amenities record lists the following items and records 0% progress for the listed progress fields; this is a portal declaration, not independent verification of site completion. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Tot-lot / green stripSize not supplied; approval condition says tot-lot to be fenced and maintained as greeneryRERA amenitiesGHMC approval condition; TG-RERA progress field 0%; completion not independently verified
Trees / periphery greeneryApproval record specifies 10 trees and periphery greeneryApproval-record provision; planting status not independently verified
Rainwater harvestingOne rainwater-harvesting pit is recordedApproval-record provision; completion not independently verified
Internal roads and footpathsNo dimensions suppliedRERA amenitiesTG-RERA progress field 0%; completion not independently verified
Water supplyListed as available “YES” in the TG-RERA amenities recordRERA amenitiesPortal-listed; progress field 0%; operating status not independently verified
Sewerage / sewage treatment“Sewerage (Chamber, Lines, Septic Tank, STP)” listed as available “YES”RERA amenitiesPortal-listed; progress field 0%; facility type and operating status not independently verified
Storm-water drainsNo dimensions or design details suppliedRERA amenitiesTG-RERA progress field 0%; completion not independently verified
Street lightingNo details suppliedRERA amenitiesTG-RERA progress field 0%; completion not independently verified
Community buildingsNo description or size suppliedRERA amenitiesTG-RERA progress field 0%; completion not independently verified
Sewage and sullage treatment/disposalNo capacity or process details suppliedRERA amenitiesTG-RERA progress field 0%; completion not independently verified
Solid-waste management and disposalNo capacity or method details suppliedRERA amenitiesTG-RERA progress field 0%; completion not independently verified
Electrical meter room / sub-station / receiving stationApproval record requires space for a transformerRERA amenitiesPortal-listed; installed or operational status not independently verified
Recreational open spaceArea not suppliedRERA amenitiesTG-RERA progress field 0%; completion not independently verified

7. Utilities, building services & safety

The approval record requires space for a transformer, a garbage house and rainwater harvesting, and contains conditions relating to sanitation, plumbing, fire-safety requirements, lifts and electrical installations. The supplied project-specific evidence does not state water-source or storage capacities, STP capacity, reuse arrangements, backup-power capacity, lift count or capacity, or a completed fire-safety installation. RERA amenities

The permit conditions require an Occupancy Fire NOC from the Director (EV&DM) before an occupancy certificate. They also state that an occupancy certificate is required before occupation and that regular service connections are to be provided before possession. These are approval conditions, not evidence that the systems or certificates have been completed or obtained.

The approval record includes an EV charging infrastructure condition for parking places. No installed EV charger, CCTV, security system, accessibility arrangement, ramp or accessible-circulation detail is established by the supplied project-specific records.

8. Location, access & connectivity

The registered location is Uppal, Uppal mandal, Medchal-Malkajgiri district, PIN 500039, at Plot No. 1376 Western Part. The RERA filing’s site boundary description identifies a 60-foot-wide road to the north. The building permit record also refers to an 18.0m road width. RERA record RERA filing

The supplied location data identifies Financial District (Nanakramguda), 2.0 km as a location anchor, measured from the cadastral parcel centroid recorded at 17.40121, 78.35418. The evidence does not provide a project-specific public-transport or approach-road route description. Location record

9. Developer & development status

The registered legal promoter is DPR INFRA PROJECTS PRIVATE LIMITED, a private limited company, GSTIN 36AAICD4960B1ZT. The promoter address recorded in the project filing is SHIV RESIDENCY, ROAD NO 1, SAI NAGAR COLONY, UPPAL BAGAYATH HMDA LAYOUT, UNDER GHMC UPPAL CIRCLE, UPPAL, Uppal, Medchal-Malkajgiri, 500039. The project filing identifies NAYINI DHARMAPAL REDDY as authorized signatory and NAYINI SAI CHARAN REDDY as director. Corporate record Parties record

The project is registered as a single-building apartment development. No independently verified construction-progress assessment is provided in the supplied records. The Form B affidavit, verified at Hyderabad on 10/10/2025, declares a completion date on or before 02/09/2028; the GHMC permit also records construction to be completed before 02/09/2028. The project header separately records 02/01/2029 as the proposed completion date. RERA record

10. Approvals, official records & documents

TG-RERA registration certificate
Identifier / dateP02200010267; validity 02/09/2025–02/09/2028
What it establishesRegistration of DPRs RAGA under DPR INFRA PROJECTS PRIVATE LIMITED
GHMC building permit order
Identifier / date0926/GHMC/SWBP/LBN2/2025; approved 02/09/2025
What it establishesBuilding permit for one residential building at Plot No. 1376 Western Part, recording 10 dwelling units
GHMC file number
Identifier / date001358/GHMC/00867/SWBP/LBN2/2025
What it establishesPermit-file identifier
Approved layout reference recorded in permit
Identifier / date71563/HMDA / DEVELOPMENT/PD-1/UPPAL BHAGATH V/17
What it establishesLayout reference cited in the GHMC permit
Form B affidavit-cum-declaration
Identifier / dateVerified 10/10/2025
What it establishesPromoter declaration concerning title, encumbrances, project funds, approvals and completion undertaking
Building permit / approved-plan extract
What it establishesBuilding configuration, areas, parking, setbacks and permit conditions
Occupancy / completion certificate
Identifier / dateNot supplied; approval extract records completion certification as false
What it establishesNo supplied evidence of an issued occupancy or completion certificate

The GHMC permit names the building as Building - 1 and identifies the project survey schedule as 1 To 40; 282 To 368; 369 Part; 370 To 373; 374 Part; 375 To 387; 395 To 401; 454; 456 To 459; 505 Part; 510 To 564.

Frequently asked questions

Is DPRs RAGA registered with Telangana RERA?

Yes. DPRs RAGA is registered with the Telangana Real Estate Regulatory Authority as P02200010267; the registration status is New Project.

Who is the developer of DPRs RAGA?

The promoter named in the RERA registration is DPR INFRA PROJECTS PRIVATE LIMITED.

Where is DPRs RAGA located?

DPRs RAGA is in UPPAL, Medchal-Malkajgiri, Telangana (500039).

When will DPRs RAGA be completed?

The promoter's proposed date of completion filed with RERA is 02/01/2029. This is the promoter's declaration, not a guarantee.

More projects in Uppal